Resolved
Decision – The report was noted.
Governance Committee noted this item on Wednesday 24 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision – The report was noted.
1. The purpose of this report is to advise members of the work undertaken in respect of the Internal Audit Plan from April 2021 to October 2021 and to give an appraisal of the Internal Audit Service’s performance to date.
Recommendations to Governance Committee
2. Members are asked to note the position with regard to the Internal Audit Plan.
Corporate priorities
3. The report relates to the following corporate priorities:
Involving residents in improving their local A strong local economy area and equality of access for all
Clean, safe and healthy communities An ambitious council that does more X to meet the needs of residents and the local area
Background to the report
4. The Internal Audit Plan for 2021/22 was approved by this Committee at its meeting in April 2021 and provides for 489 days of audit work. 5. This is the first interim report for 2021/22 and covers the period between 1st April and 29th October 2021.
Internal Audit Reports
6. Appendix A provides a snapshot of the overall progress made in relation to the 2021/22 Internal Audit Plan, indicating which audits have been completed and their assurance rating, those that are in progress and those that have yet to start. Appendix A also shows the time planned and actually spent on individual 7. The following work has been completed between April and October 2021:
Name of Review Assurance Comments / Key control findings Rating Annual Governance Not applicable Proactive input was provided in Statement collating information to inform the AGS Action Plan.
COVID Post Payment Not applicable Internal Audit provided documentation Assurance to the Department for Business, Energy and Industrial Strategy (BEIS) to evidence assurance checks undertaken in relation to 15 cases. This included a sample of grants paid from each of the following schemes: Covid- 19 Small Business Grant, Retail, Hospitality and Leisure Grant and Local Authority Discretionary Grant Funds.
Internal Audit have also reviewed all the 31 matches identified by the National Fraud Initiative (NFI) in relation to the payment of the above grants. There are queries arising which are currently being investigated with a view to deciding if any further action is necessary.
COVID Pre Payment Not applicable Internal Audit have reviewed new and Assurance existing procedures to provide assurance that they are robust, meet Government requirements and measures are in place to ensure fraudulent activity is minimised for the Restart Grant, Test & Trace and the Additional Restriction Grant.
Review of Market Walk Substantial This was a risk-based review and only minor improvements are required to strengthen the current arrangements in place. Primrose Gardens Limited A copy of the full report has been made available for Governance Committee members.
Disabled Facilities Grants To follow All fieldwork has been completed for this risk-based review. The report has been drafted and is currently being finalised and will be included in the next interim report to the committee in Jan 22.
Performance Management Adequate This review focussed on corporate performance indicators. The issues identified during the review demonstrate that there is a need for greater oversight of the data collection system by the responsible officers, in conjunction with the authorising officers.
Due to the actions already in progress by the Performance & Partnership Team only a couple of additional improvements are required to strengthen the current control arrangements
Compliance with Contract Substantial From the work undertaken Internal Procedure Rules (CPRs) Audit was able to establish that there was a high level of compliance with the Council’s CPRs and evidence was available to support that the essential processes within the procurement cycle had been followed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit PlanAppendix A | 260 KB | Download |
PDF |
Performance Indicators as at 29th October 2021Appendix B | 233 KB | Download |
PDF |
Internal Audit Interim Report as at 29 October 2021Report | 165 KB | DownloadRead as text |
Follow Governance Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2025 | Minutes of meeting Wednesday, 22 January 2025 of Governance Committee(Unanimously) That the minutes of the last meeting, held on Wednesday 22 January 2025, be signed as an accurate recor... | Decided | Open |
| 19 Mar 2025 | Minutes of meeting Monday, 24 February 2025 of Governance Committee - Constitution Working Group(Unanimously) That the minutes of the Governance Committee – Constitution Working Group, held on Monday 24 February 2... | Noted | Open |
| 19 Mar 2025 | Internal Audit Plan April - September 2025(Unanimously) That the Committee approve the internal audit plan for April – September 2025. | Approved | Open |
| 19 Mar 2025 | Global Internal Audit Standards in the UK Public Sectorthat the report be noted. | Noted | Open |
| 19 Mar 2025 | Annual Review of Risk Management Strategy(Unanimously) That the Committee approves the revised Risk Management Strategy and requests that regular updates and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.