To approve the revised approach for procurement from the use of Scape Framework (as agreed by Council on 16th November), to use existing consultants (via routes to be agreed by procurement based on individual contract details) and use of provision of further support from council planning policy teams. 2. To note that the £300k is to be funded from the Local Plan budget, which is split equally between Chorley, Preston and South Ribble Councils. Agree to the continue to release the additional approved funding of £300,000 to the Local Plan Budget as agreed by Council in November and for detailed approval of individual contracts via EMD. 1. To approve the revised approach for procurement from the use of Scape Framework (as agreed by Council on 16th November), to use existing consultants (via routes to be agreed by procurement based on individual contract details) and use of provision of further support from council planning policy teams. 2. To note that the £300k is to be funded from the Local Plan budget, which is split equally between Chorley, Preston and South Ribble Councils. Agree to the continue to release the additional approved funding of £300,000 to the Local Plan Budget as agreed by Council in November and for detailed approval of individual contracts via EMD. Reasons for recommendations: To ensure the progression of the Local Plan in a timely manner. Other options considered and rejected: Alternative option previously approved by Council on 16th November was procurement of support via the Scape Framework. Following pursuit of this option, and discussions with each of the three Councils involved in developing the plan, it is felt this option was no longer appropriate.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. This report presents an update on the procurement process to provide additional support to the Central Lancashire Local Plan team and informs members on the reason for change in approach from that approved on the 16th November 2021.
Recommendations to Executive Cabinet
2. Approve the revised approach for procurement from the use of Scape Framework (as agreed by Council on 16th November), to use existing consultants (via routes to be agreed by procurement based on individual contract details) and use of provision of further support from council planning policy teams.
3. Note that the £300k is to be funded from the Local Plan budget, which is split equally between Chorley, Preston and South Ribble Councils. Agree to the continue to release the additional approved funding of £300,000 to the Local Plan Budget as agreed by Council in November and for detailed approval of individual contracts via EMD.
Reasons for recommendations
4. To ensure the progression of the Local Plan in a timely manner.
Other options considered and rejected
5. Alternative option previously approved by Council on 16th November was procurement of support via the Scape Framework. Following pursuit of this option, and discussions with each of the three Councils involved in developing the plan, it is felt this option was no longer appropriate. Executive summary
6. This report provides an update on the process of procuring additional support to progress the Central Lancashire Local Plan. It sets out the reason why we are no longer progressing support via the Scape framework and the proposed approach going forward to utilise existing consultants working on key evidence base documents alongside resources being deployed from within each Councils Planning Policy teams where available.
Corporate priorities
7. The report relates to the following corporate priorities:
Involving residents in improving their local A strong local economy area and equality of access for all
Clean, safe and healthy communities An ambitious council that does more to meet the needs of residents and the local area
Background to the report
8. A report was presented to Council on 16th November 2021 to support the allocation of additional funding for the Central Lancashire Local Plan to procure additional consultant support via the Scape Framework. Support for this approach was granted at that meeting.
9. Following approval, meetings were set up with Scape to identify suitable consultants to assist in this process, only one option was available to us. An initial outline cost proposal was received for this work which was above the level of support approved. In addition, the Councils identified that the consultant suggested was potentially conflicted due to representing landowners in promoting sites through the Local Plan process. As such it was felt we could not continue down this route
10. An alternative approach is now put which seeks to utilise existing consultants already supporting the plan process, along with policy officer support from the 3 councils, to progress the Local Plan to preferred options stage.
11. The previous report presented to Council was seeking support to progress the plan to preferred options in 2022, this is still the aim and the process and options to be considered for achieving this are set out in this report.
Provision of Support to progress the Local Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.