Resolved
Resolved - That the report be noted.
Governance Committee noted this item on Wednesday 23 November 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - That the report be noted.
1. The purpose of this report is to advise members of the work undertaken in respect of the Internal Audit Plan from April 2022 to September 2022 and to give an appraisal of the Internal Audit Service’s performance to date.
Recommendations to Governance Committee
2. Members are asked to note the position with regard to the Internal Audit Plan.
3. The production of reports setting out progress against the audit plan is a key requirement of the Public Sector Internal Audit Standards.
Other options considered and rejected
4. Not applicable.
Corporate priorities
5. The report relates to the following corporate priorities:
Involving residents in improving their local A strong local economy area and equality of access for all Clean, safe and healthy communities An ambitious council that does more to meet the needs of residents and the local area
Background to the report
6. The Internal Audit Plan for the six months April to September 2022 was approved by this Committee at its meeting in March 2022 and provides for 135 days of audit work. Internal Audit Reports
7. Appendix A provides a snapshot of the overall progress made in relation to the six month Internal Audit Plan, indicating which audits have been completed and their assurance rating, those that are in progress and those that have yet to start.
8. The table below highlights the main pieces of work undertaken during the period together with any issues identified where applicable:
Name of Review Assurance Comments Rating
Annual Not Proactive input was provided to inform the AGS Governance applicable Action plan presented to the Governance Committee Statement (AGS) in June 2022.
National Fraud Not Internal Audit are currently working with data holders Initiative applicable to meet the Cabinet Office data requirements for the forthcoming main NFI 2022/23. We need to ensure that the Council can supply all mandatory datasets by the deadline (including payroll, taxi licence, trade creditors, housing waiting list, Council Tax Reduction Scheme).
Also, we are working with officers to ensure that any outstanding work from the previous exercises is concluded. This includes, Council Tax SPD.
COVID support Not Internal Audit participated in the BEIS post payment work / Business applicable assurance verification process; providing the required Grants Pre and evidence to support the payments made are Post Payment compliant with the grant eligibility criteria. Assurance/ Test and Trace In addition, assurance was provided in relation the Containing Outbreak Management Fund and Test and Trace Support Payment grant determination sign- off.
Safeguarding Adequate Our review was undertaken during a period of transition in the Council’s safeguarding arrangements as both the Lead Designated Safeguarding Officer (DSO) and the Lead Prevent Officer left the organisation during the course of the review. Interim arrangements are in place, but these have not been widely advertised across the organisation, this should be undertaken urgently to ensure that officers and elected members know who to contact should a concern arise.
The council has safeguarding policies and procedures in place which are regularly reviewed and accessible for officers and elected members, and the survey undertaken as part of this review indicates that office- based staff have a good awareness of both policies and the process to report a safeguarding concern.
A range of actions were agreed to improve the control environment by launching the Volunteer Policy, reviewing and strengthening the membership of the Safeguarding Steering Group and ensuring Job descriptions were reflective of the DBS requirements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit PlanAppendix A | 230 KB | Download |
PDF |
Internal Audit Performance IndicatorsAppendix B | 234 KB | Download |
PDF |
Internal Audit Interim Report as at 30th September 2022Report | 147 KB | DownloadRead as text |
Follow Governance Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2025 | Minutes of meeting Wednesday, 22 January 2025 of Governance Committee(Unanimously) That the minutes of the last meeting, held on Wednesday 22 January 2025, be signed as an accurate recor... | Decided | Open |
| 19 Mar 2025 | Minutes of meeting Monday, 24 February 2025 of Governance Committee - Constitution Working Group(Unanimously) That the minutes of the Governance Committee – Constitution Working Group, held on Monday 24 February 2... | Noted | Open |
| 19 Mar 2025 | Internal Audit Plan April - September 2025(Unanimously) That the Committee approve the internal audit plan for April – September 2025. | Approved | Open |
| 19 Mar 2025 | Global Internal Audit Standards in the UK Public Sectorthat the report be noted. | Noted | Open |
| 19 Mar 2025 | Annual Review of Risk Management Strategy(Unanimously) That the Committee approves the revised Risk Management Strategy and requests that regular updates and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.