Resolved
(Unanimously) That the Internal Audit Plan October 2024-March 2025 be approved.
Governance Committee approved this item on Wednesday 25 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
(Unanimously) That the Internal Audit Plan October 2024-March 2025 be approved.
1. This report sets out the programme of work to be undertaken by the Internal Audit Service. The Internal Audit Plan is the vehicle by which audit workload is identified and prioritised.
The main purposes of the report are to:
• Remind members of the respective roles of managers and Internal Audit to maintain a sound system of governance and internal control within the Council. • Provide details and seek the Committee’s approval of the Internal Audit Plan.
2. That the Committee approve the Internal Audit Plan October 24 to March 25.
3. Governance Committee approval of the Internal Audit Plan is a requirement of the Public Sector Internal Audit Standards.
Other options considered and rejected.
4. Not applicable.
Corporate priorities
5. The report relates to the following corporate priorities:
Housing where residents can live well A green and sustainable borough
An enterprising economy with vibrant local Healthy, safe, and engaged communities centres in urban and rural areas The Role of Management and Internal Audit
6. The responsibility for implementing a strong system of governance and internal control within the Council lies primarily with the Shared Senior Management Team. Directors and Heads of Service need to ensure that they maintain effective control procedures not least because services and business systems are subject to on-going change.
7. Internal Audit is an independent appraisal function whose core objective is to evaluate and report on the adequacy of the Council’s system of governance, risk management and internal control. In the main this is achieved through an annual programme of reviews, following a detailed risk assessment of audit need.
Compilation of the Audit Plan
8. Professional standards for Internal Audit in local government specify that “the Chief Audit Executive must establish risk-based plans to determine the priorities of the internal audit activity, consistent with the organisation’s goals”.
9. The Internal Audit Plan October 24 – March 25 has been constructed after taking into consideration the following:
• The Council’s priorities / strategic plan. • A review of corporate strategies. • The corporate risk register. • Information taken from other assurance processes within, and external to, the Council, including External Audit and inspection reports. • Direct engagement with Directors. • The skills, knowledge, and experience of audit staff. • Professional judgement on the risk of fraud and error. • Annual Governance Statement and Service Assurance Statements.
10. The Internal Audit Plan contains the programme of reviews for the period of October 24 to March 25 and is shown at Appendix A. This clearly shows the link between the work of Internal Audit, strategic and operational risks, and corporate objectives. The reviews are clearly highlighted with the quarter for completion. The plan also details our involvement with key project teams assisting with advice and guidance on risk management, internal control, and governance.
Audit Resource
11. Since the approval of the Internal Audit Plan for March 24 to September 24, there has been a reduction in the level of audit resource as one member of the Audit Team is due to retire at the end of September. Whilst a recruitment exercise is currently on- going, there is a small impact on the number of available audit days compared to 2023/24 as shown in the table below. Authority 2023/24 2024/25 Variance
CBC 270 239 (31)
12. Whilst the number of audit days has reduced, delivery of the agreed Plan will result in the production of fifteen audit reports with an assurance rating which is in line with the number of reports produced during 23/24. The Plan will be completed by the in-house team with external support procured for specialist ICT reviews.
Internal Audit Annual Opinion
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Plan October 2024 to March 2025Appendix A | 55 KB | Download |
PDF |
Internal Audit Plan October 2024 to March 2025Report | 102 KB | DownloadRead as text |
Follow Governance Committee at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2025 | Minutes of meeting Wednesday, 22 January 2025 of Governance Committee(Unanimously) That the minutes of the last meeting, held on Wednesday 22 January 2025, be signed as an accurate recor... | Decided | Open |
| 19 Mar 2025 | Minutes of meeting Monday, 24 February 2025 of Governance Committee - Constitution Working Group(Unanimously) That the minutes of the Governance Committee – Constitution Working Group, held on Monday 24 February 2... | Noted | Open |
| 19 Mar 2025 | Internal Audit Plan April - September 2025(Unanimously) That the Committee approve the internal audit plan for April – September 2025. | Approved | Open |
| 19 Mar 2025 | Global Internal Audit Standards in the UK Public Sectorthat the report be noted. | Noted | Open |
| 19 Mar 2025 | Annual Review of Risk Management Strategy(Unanimously) That the Committee approves the revised Risk Management Strategy and requests that regular updates and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.