Chorley Borough Council
Planning Committee, Tuesday 14 October 2025 at 6.30pm

25/00107/FULMAJ Land To The North West Of Botany Canal Bridge

Approved Planning 3 papers

AI summaryChorley planning committee approved retrospective planning permission for containerised storage units and offices on land at Botany Bay for three years, subject to conditions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPlanning permission granted, subject to conditions
MoneyCIL liable; charge subject to indexation
What happens nextConditions to followSuggested conditions listed as 'to follow' in report
Who it affectsBotany Bay employment siteLand near Grade II listed Canal Mill, M61 and canal

What was decided

Planning permission was approved, subject to conditions, for retrospective erection of containerised storage and office units on land to the north west of Botany Canal Bridge. Report P1, P7

The permission is granted on a temporary basis for a period of three years from the date the permission is granted. Report P9

Officers concluded the scheme would not cause significant harm to the setting of the Grade II listed Canal Mill or to the non-designated heritage value of the canal. Report P83

Why

The site lies within the Chorley settlement boundary and is allocated under policy EP1.2 Botany Bay for employment uses, which include offices and storage, so the proposed use is acceptable in principle. Report P32, P33

The development is treated as an interim use on part of a wider consented business park site, providing some interim economic benefits while the wider scheme progresses. Report P5, P39, P65

Objections on visual impact, highway safety, temporariness, policy conflict, lack of consultation, and retrospective applications were considered, but the planning authority must determine the application on its planning merits. Report P11, P85, P86

What happens next

The temporary access via Blackburn Brow is to remain in use only until improvements to Hartwood Hall roundabout have been delivered, in line with the wider business park consent. Report P15, P48

A condition will be imposed to secure the temporary nature of the permission, as required by the Canal and River Trust. Report P13, P9

Suggested conditions are listed as 'to follow' in the report. Report P97

Options considered

  • Chosen: Approve planning permission subject to conditions (officer recommendation). Scheme acceptable in principle, interim use of allocated employment site, no significant harm to heritage, amenity, highways or drainage Report P1, P33, P65, P83, P88
  • Rejected: Refuse planning permission. No unacceptable impacts identified; objections did not outweigh the assessment on planning merits Report P11, P86, P88

Implications

  • Legal: The duty under section 66(1) of the Planning (Listed Buildings and Conservation Areas) Act 1990 was applied, with great weight given to the conservation of the Grade II listed Canal Mill; officers concluded no significant harm to its significance. Report P68, P70, P83
  • Legal: The Central Lancashire Local Plan 2023 to 2041, submitted to the Secretary of State on 30 June 2025, is a material consideration but carries limited weight at this stage. Report P18, P19, P20
  • Financial: The development is CIL liable and any charge would be subject to indexation under the Chorley CIL Charging Schedule (adopted 16 July 2013, charging commenced 1 September 2013). Report P84
  • Risk: Access via Blackburn Brow is temporary and tied to delivery of Hartwood Hall roundabout improvements for the wider business park consent 24/00597/FULMAJ. Report P15, P48, P94
  • Equalities: Site is level with step-free access to the storage containers, two accessible parking bays, signage, CCTV, lighting and a manned gate, with security fencing. Report P58, P64
  • Climate: Storage buildings are not to be heated; the scheme reuses previously developed hard-surfaced land rather than greenfield, and the permission is time-limited to three years. Report P3, P9, P39, P60

Who and where

  • The applicant, seeking retrospective planning permission for storage and offices Report P3, P7
  • Two individuals who raised objections on visual, highway, policy, consultation and retrospective application grounds Report P11
  • Operators and users of the wider Botany Bay Business Park under construction to the north of Canal Mill Report P4, P5, P90
  • Nearest residents at Botany Bay and Blackburn Brow, over 60 metres to the east Report P43
  • Canal and River Trust, concerned with the character of the canal corridor Report P13, P77

Timeline

  • 25 January 2023: Hybrid planning permission 21/00439/FULMAJ granted for Botany Bay Business Park Report P90
  • 11 January 2024: Minor non-material amendment 23/00960/MNMA to merge units F and G approved Report P91
  • 5 December 2024: Section 73 application 24/00401/FULMAJ approved to vary phasing conditions Report P93
  • 6 December 2024: Section 73 application 24/00597/FULMAJ approved to reposition the internal road Report P94
  • 5 March 2025: Reserved matters 24/00186/REM approved for Unit A drive-thru and Unit B retail units Report P92
  • 30 June 2025: Central Lancashire Local Plan submitted to the Secretary of State for examination Report P18
  • Three years from the date the permission is granted: Expiry of the temporary permission for the containerised storage and offices Report P9

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development to fund infrastructure
  • CLLP: Central Lancashire Local Plan, covering South Ribble, Chorley and Preston for 2023 to 2041
  • NPPF: National Planning Policy Framework, the government's planning policy guidance for England
  • NDHA: Non-designated heritage asset, a building, site or place with heritage significance but not formally listed
  • PERFPP: Planning permission granted, following completion of a planning performance agreement
  • Business in a Box: Double-stacked container units with secure storage below and office space above, accessed by an external metal staircase
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item36e

Resolved

Planning permission approved, subject to conditions.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Planning Committee

Recommendation

1. It is recommended that planning permission is approved subject to conditions.

SITE DESCRIPTION

2. The application site comprises a linear area of open hard surfaced land to the south side of Canal Mill at Botany Bay and is located to the immediate east of the M61 motorway in the settlement area of Chorley, between the motorway and the Leeds and Liverpool canal. The land was open and mainly used for parking of vehicles, until it’s recent development as a storage and associated office facility (for which permission is sought though this application).

3. Access to the site is provided via an existing access road to Botany Brow, which connects to Blackburn Brow to the south of the site. There are no dwellings immediately adjoining the site, which has an industrial character, whilst it is noted that the site is well contained by highways and the canal.

4. It is noted that planning permission was granted for an industrial business park development in January 2023, which is under construction and is well progressed to the north side of the mill building. The business park that is under construction also includes the application site but has not progressed to the south side of the mill other than through works to the access road and landscaping.

DESCRIPTION OF PROPOSED DEVELOPMENT

5. Planning permission is sought retrospectively for the erection of containerised storage units and offices and associated works. This comprises five blocks of single stacked storage containers and one block of double stacked ‘Business in a Box’ office facilities. Each storage container measures approximately 6m by 2.4m and is approximately 2.4m in height. The single stacked storage containers are painted blue, with white logo branding on the side and are arranged in blocks of 8 units, 2 units, 35 units, 5 units and 26 units. The ‘Business in a Box’ units provide secure storage with office space above, accessed from an external metal staircase at the rear of the containers. The ends of the office container are glazed for access and views/natural light. These are arranged in a block of 10 units double stacked.

6. Access is provided via an existing access road from Botany Brow and would provide 13no. parking spaces and manoeuvring areas. The existing fencing and landscaping would retain in situ.

7. Planning permission is sought on a temporary basis for a period of 3 years from the date of any planning permission that be granted.

REPRESENTATIONS

8. Representations in objection have been received from 2 no. individuals raising the following concerns: • Visual impacts and detrimental to the appearance of the area • Highway safety and capacity impacts • There is no mechanism to ensure the development is temporary and risk that it becomes permanent. • Contrary to policy as does not support economic growth. • Lack of community consultation or engagement carried out by the applicant. • Granting retrospective applications undermines public trust in the planning system and erodes confidence in the competency of the local planning authority.

CONSULTATIONS

9. Canal & River Trust: No objections subject to a condition securing a temporary permission.

10. Regulatory Services - Environmental Health: No objections.

11. Lancashire Highway Services: The use of the access should remain temporary until such time as the improvements to Hartwood Hall roundabout have been delivered.

12. Lead Local Flood Authority: have no comments to make on the application.

PLANNING CONSIDERATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/00107/FULMAJ Land To The North West Of Botany Canal BridgeReport 149 KB DownloadRead as text
PDF
Item 3e PresentationReport 4.5 MB Download
PDF
item 3e Location PlanPlan 219 KB Download

At this meeting

Whole meeting

Who was there

11 of 25 attended
JM
Councillor June MolyneauxChair, present
NW
Councillor Neville WhithamVice-Chair, present
GF
Councillor Gordon FranceCommittee Member, present
RG
Councillor Russ GreenCommittee Member, present
AH
Councillor Alex HiltonCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
AS
Councillor Arjun SinghCommittee Member, present
CS
Councillor Chris SnowCommittee Member, present
CS
Councillor Craige SouthernCommittee Member, present
AW
Councillor Alan WhittakerCommittee Member, present
KW
Councillor Katie WilkieCommittee Member, present
AP
Councillor Alan PlattReserve, in attendance

All 25 on the meeting page

On this subject at Chorley

Search all
  1. 25/00107/FULMAJ Land To The North West Of Botany Canal BridgeThis decision
  2. 25/00503/FULMAJ - Land To The West Side Of Blackburn Road ChorleyApproved
  3. 26/00314/FULMAJ - Land Off Wigan Road And Parkhurst Avenue Clayton Le WoodsAgreed
  4. 25/01051/FULMAJ - Land to the West Side of Preston Road, CoppullAgreed
  5. 25/001051/FULMAJ - Land to the West Side of Preston Road, CoppullDeferred
  6. 25/00717/FULMAJ - Land At Barnes Wallis Way Buckshaw VillageDecided

More from Chorley Planning Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Minutes of meeting Tuesday, 4 August 2026 of Planning Committeethat the minutes of meeting Tuesday, 4 August 2026 of the Planning Committee were approved as a correct record. Approved Open
8 Sep 2026 25/01052/FULMAJ - Moor Road, CrostonPlanning permission was minded to be refused for the following reason: ‘The application is contrary to policy 1 of th... Refused Open
8 Sep 2026 25/00503/FULMAJ - Land To The West Side Of Blackburn Road ChorleyPlanning permission approved for the temporary use of land for up to two years subject to conditions including the ap... Approved Open
8 Sep 2026 Appeals Reportthat the be noted. Noted Open
4 Aug 2026 Minutes of meeting Tuesday, 7 July 2026 of Planning CommitteeMinutes approved. Approved Open