Resolved
To receive an update on the Key Contracts and Partnerships. 2. To approve the refreshed Framework.
AI summaryExecutive Cabinet received an update on 15 key contracts and partnerships and approved a refreshed governance framework. Work continues on migrating to a new Technology One finance system due to go live in April 2026.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
To receive an update on the Key Contracts and Partnerships. 2. To approve the refreshed Framework.
1. The report provides an update on the council’s Key Contracts and Partnerships to demonstrate effective governance and monitoring of working arrangements between the council and other parties around service delivery and achievement of corporate priorities.
2. The report also includes a refreshed Key Contracts and Partnerships Framework to ensure that the framework is fit for purpose and is embedded across the council, with a clear understanding of the need for additional scrutiny of certain contracts and partnership arrangements.
Recommendations to Executive Cabinet
3. To receive an update on the Key Contracts and Partnerships.
4. To approve the refreshed Framework.
5. The refreshed Key Contracts and Partnerships Framework will aid understanding and application of the framework requirements and support effective governance and monitoring. The framework ensures that we take a proportionate approach to safeguarding the success of our collaborative working arrangements by identifying and monitoring the contracts and partnerships that are extremely important for council operations and, if not managed effectively, could negatively impact on the delivery of outcomes for our communities. Other options considered and rejected
6. No other options have been considered as it is important that the Council maintains effective governance and monitoring arrangements for key contracts and partnerships.
Corporate priorities
7. The report relates to the following corporate priorities: Housing where residents can live well A green and sustainable borough An enterprising economy with vibrant local centres in urban and rural areas Healthy, safe and engaged communities
Background to the report
8. The Key Contracts and Partnerships Framework was refreshed in 2024, setting out monitoring arrangements for contracts and partnerships deemed to be significant and requiring additional governance and scrutiny.
9. The framework outlined the role of the People, Policy and Partnerships service in maintaining a register of key contracts and partnerships and providing bi-annual updates to SMT and annual reporting to Cabinet.
10. This formal monitoring was intended to supplement ongoing contract management and monitoring including: • production of the Transparency Register which is co-ordinated through the procurement team and updated quarterly. • operational meetings, board meetings and updates to executive members undertaken at a service level as general good practice.
11. Service restructures and shifts in responsibilities have delayed monitoring and reporting. In June an exercise began to clarify the contracts and partnerships for Chorley that meet the criteria as set out in the current framework including:
• Financial – the contract costs the council £100k or more per annum. • Corporate Priorities – the contract or partnership will significantly impact the delivery of one or more of the Council’s corporate priorities. • Risk - there is a high amount of risk associated with the contract or partnership e.g. significant disruption to core services and systems availability; financial impact over £100k • Length – the contract or partnership is for five or more years. • Resource – there will be a large reliance on the proposed partner/contractor for service delivery. 12. For a contract or partnership to be identified as key it should meet at least three of the above criteria.
Register of Key Contracts and Partnerships
13. A total of 15 contracts and partnerships were identified which are set out in the table below.
Criteria
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
for Key Contracts and Partnerships FrameworkAppendix 1 | 493 KB | Download |
PDF |
Key Contracts and Partnerships FrameworkReport | 106 KB | DownloadRead as text |
Follow Executive Cabinet at Chorley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... | Decided | Open |
| 17 Sep 2026 | Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. | Approved | Open |
| 17 Sep 2026 | Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... | Noted | Open |
| 17 Sep 2026 | Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... | Approved | Open |
| 17 Sep 2026 | Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.