25/00889/PIP - Land 55m north east of 53 Bradley Lane, Eccleston
RefusedPlanning3 papers
AI summaryChorley Planning Committee refused permission in principle for up to 8 homes on Green Belt land at Eccleston, overturning the officer's recommendation to approve.
Written from the decision and the officer reportPDF Pro
OutcomeRefusedAgainst officer recommendation to grant
MoneyNot stated
What happens nextRight of appeal or resubmission possible
Who it affects8 dwellings proposed, Eccleston0.49 hectare Green Belt site off Bradley Lane
What was decided
Planning permission in principle was refused, overturning the officer recommendation to grant. Report P1, P84
Members found the proposal would be inappropriate development in the Green Belt, with no very special circumstances to outweigh the harm.
Members concluded the scheme did not meet the exceptions at paragraph 154 or the terms of paragraph 155 of the National Planning Policy Framework.
Why
The site lies within the Green Belt as defined by the Chorley Local Plan 2012-2026, and this designation does not change under the submitted Central Lancashire Local Plan 2023-2041. Report P3, P4, P17
Members considered the development would lead to unrestricted sprawl, harm the setting of a historic settlement and would not be in a sustainable location.
The officer had assessed the site as 'grey belt' and concluded the four conditions of paragraph 155 were met, including a 3.4 year housing supply shortfall and a sustainable location in Eccleston. Report P37, P40, P58, P69, P77, P83
What happens next
If permission in principle had been granted, the applicant would have had 3 years to submit a technical details consent application; that route is now closed. Report P84
CIL liability was not calculated at this stage but would have applied on any subsequent technical consent approval. Report P81
Options considered
Rejected: Grant permission in principle, as recommended by the officer (grey belt, unmet housing need, sustainable location, no strategic Green Belt harm). Members considered the scheme would cause unrestricted sprawl, harm the setting of a historic settlement and be in an unsustainable location, with no very special circumstances Report P1, P83, P84
Chosen: Refuse permission in principle on Green Belt grounds. Inappropriate development in the Green Belt contrary to the National Planning Policy Framework
Implications
Legal: Decision is stated to be contrary to the National Planning Policy Framework; the applicant may seek to challenge or appeal.
Legal: Determination was made under section 38(6) of the Planning and Compulsory Purchase Act 2004, with the tilted balance engaged due to a 3.4 year housing supply. Report P28, P85
Other: Objections cited harm to rural landscape, biodiversity, flooding, highway impacts and pressure on schools and doctors. Report P9
Who and where
The applicant seeking permission in principle for up to 8 dwellinghouses Report P6
Residents and Eccleston Parish Council, who objected on Green Belt and settlement boundary grounds Report P9, P12
Chorley Borough Council as local planning authority Report P28, P85
United Utilities, which provided a holding response pending any future technical details application Report P11
Timeline
August 2013: Earlier application 13/00601/FUL for relocation of stable block and muck midden was approved. Report P87
30 June 2025: Central Lancashire Local Plan 2023-2041 submitted to the Secretary of State, becoming a material consideration. Report P18, P19
September 2025: Chorley Five Year Housing Supply Statement published, identifying a 3.4 year deliverable housing supply. Report P28, P69
11 November 2025: Planning Committee refused permission in principle for 25/00889/PIP.
Plain English for the jargon
Permission in Principle (PIP): A two-stage planning route that considers only the principle of housing-led development, with technical detail assessed at a second stage.
Green Belt: Designated open land around built-up areas protected from inappropriate development under national policy.
Grey Belt: Green Belt land that does not strongly contribute to purposes (a), (b) or (d) of Green Belt, where some development may be appropriate under NPPF paragraph 155.
Very special circumstances: The test that must clearly outweigh harm to justify inappropriate development in the Green Belt.
Tilted balance: The presumption in favour of sustainable development in NPPF paragraph 11, engaged where housing policies are out-of-date.
CIL: Community Infrastructure Levy, a charge on new development adopted by Chorley on 16 July 2013.
CLLP: Central Lancashire Local Plan 2023-2041, covering Chorley, South Ribble and Preston.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item40c
Resolved
Planning permission refused due to the following reason: The proposed development would be located within the Green Belt as defined by the Chorley Local Plan 2012 - 2026. The proposed development is not considered to meet with any of the exceptions to inappropriate development set out at paragraph 154 and would not meet with the terms of paragraph 155 of the National Planning Policy Framework as it would lead to unrestricted sprawl, would harm the setting of a historic settlement and would not be in a sustainable location. The proposed development would be inappropriate development in the Green Belt and therefore harmful by definition . It is not considered that there are very special circumstances to overcome the definitional harm to the Green Belt. The proposal is therefore contrary to the National Planning Policy Framework.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. It is recommended that the application for permission in principle is granted.
SITE DESCRIPTION
2. The application site is located in the Green Belt, as defined by the Chorley Local Plan Policies Map and is a broadly rectangular shaped parcel of land that is situated to the southeast of Bradley Lane. The site comprises part of a wider field sandwiched between no.53 Bardley Lane and residential properties off Cotswold Close to the south and a Glassman House which is a detached property with a large residential curtilage to the north.
3. The site falls wholly within the Green Belt, as defined by the Chorley Local Plan Policies Map within a rural area.
DESCRIPTION OF PROPOSED DEVELOPMENT
4. The application is for ‘Permission in Principle’ for up to 8no. dwellinghouses and associated infrastructure. This type of application seeks only to establish the principle of the development. The submitted site plan is indicative only, and does not form part of the assessment of this type of application.
REPRESENTATIONS
5. At the time of this report 12no. objection comments have been received citing the below:
• The proposal is on Green Belt land • The proposal is out of keeping with the character of the area • There is no need to build houses on Green Belt land as there are enough developments currently identified in the local plan to comply with current government obligations. • Highways impacts • The area forms an essential part of the villages rural landscape and contributes greatly to its peaceful atmosphere, natural beauty and community identity • Eccleston has already experienced substantial housing growth in recent years • Strain upon local services – specific regard to schools and doctors • Proximity to the nearby school and playing fields • Wildlife and biodiversity • Flooding • Bradley Lane is not suitable for the proposal • Noise, Pollution and Privacy • Introduction of artificial lighting • Main water supply and electric power lines stetch across the site
CONSULTATIONS
6. United Utilities (UU) – Although not consulted on the proposal given its nature, United Utilities have provided the following comments in respect of the application: “Should this proposal be approved, and a further application submitted for Technical Detail Consent, it is important to note that our response to a subsequent application will be based upon the information that is available at the time of response, and therefore, our position and advice may vary. An accompanying condition was also provided, that would likely be requested if an application for technical detail consent was sought”.
7. Eccleston Parish Council – Commented stating that they object to the application on the grounds of inappropriate development within the Green Belt. Stating that the site lies beyond the defined settlement boundary of Eccleston, within land designated as open countryside in the Chorley Local Plan 2012-2026 and is contrary to Local Plan Policy BNE1 and Core Strategy Policy 1.
PLANNING CONSIDERATIONS
8. The permission in principle route provides an alternative way of obtaining permission for housing-led development which is a two-fold process, separating the consideration of the ‘principle’ of development from the technical details. The first stage is the permission in principle stage, and the second stage assesses the detail of the development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
25/01052/FULMAJ - Moor Road, CrostonPlanning permission was minded to be refused for the following reason: ‘The application is contrary to policy 1 of th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.