AI summaryChorley Planning Committee granted permission for a housing development on Charter Lane, Charnock Richard, subject to a S106 agreement including £40,000 per year for bus services and £182,400 for public open space.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to conditions and a S106 legal agreement
MoneyNot stated
What happens nextS106 and conditions to be finalisedIncluding affordable housing, Section 38 and 278 agreements
Who it affectsCharnock Richard residents and future occupiersNew homes on Charter Lane, 1.45 hectare site
What was decided
Planning permission was granted for the Charter Lane, Charnock Richard housing development, subject to conditions and a S106 legal agreement.
The committee accepted that the additional traffic from the development would not have a detrimental impact on the local highway network. Report P1, P15, P17
Members accepted that the proposal would not cause harm to the character and appearance of the locality or to neighbouring amenity, subject to conditions. Report P27, P30
Why
The Local Highway Authority raised no objection, finding the development would not have a significant impact on highway safety, capacity or amenity. Report P15, P17
Officers considered the design, scale and materials of the proposed dwellings would assimilate with the existing built form in the area. Report P26, P27
All interface distances between existing and proposed dwellings exceed the council's minimum guideline distances, addressing overlooking and privacy concerns raised in objections. Report P30
What happens next
A Section 106 legal agreement must be completed to secure the bus service contribution, public open space contributions and details of affordable housing. Report P10, P11, P16
Off-site highway works are to be delivered under a Section 278 Agreement, with an amendment to the existing Phase 1 Section 38 Agreement also required. Report P7, P16
A full Travel Plan must be developed within 6 months of occupation of the development. Report P13
The money
£40,000 per annum for three years Bus service contribution to support Services 337 and 347 Report P10, P16
£182,400 Public Open Space contributions
£39,900 Additional Public Open Space contribution if a ten year period and private maintenance is not used
£45,000 per annum for a period of five years Phase 1 bus service contribution already secured Report P9
Options considered
Chosen: Grant planning permission subject to conditions and S106 agreement. Officers found the scheme acceptable in highway, design and amenity terms, subject to securing planning obligations Report P15, P17, P27, P30
Implications
Financial: Developer must fund £40,000 per year for three years of bus services from 2029, plus Public Open Space contributions of £182,400, with a possible additional £39,900. Report P10, P11, P16
Legal: A Section 106 legal agreement is required, alongside a Section 278 highways agreement and an amendment to the Phase 1 Section 38 agreement. Report P7, P16
Other: Each dwelling must have an electric vehicle charging point and cycle storage for a minimum of two bicycles. Report P7
Who and where
Future occupants of the Charter Lane development Report P24, P26
Existing residents of surrounding dwellings in Charnock Richard Report P21, P30
Bus passengers using Services 337 and 347 along Chorley Lane Report P9, P10, P16
Timeline
2029: First bus service contribution payment to commence, following the conclusion of Phase 1 contributions or prior to occupation of the 30th dwelling, whichever is later Report P11, P16
Within 6 months of occupation: Full Travel Plan to be developed and submitted Report P13
Plain English for the jargon
S106 agreement: A legal agreement under Section 106 of the Town and Country Planning Act used to secure planning obligations from a developer
S278 agreement: A legal agreement under Section 278 of the Highways Act for the developer to carry out or fund works on the public highway
S38 agreement: An agreement under Section 38 of the Highways Act 1980 for new roads to be adopted by the highway authority
LHA: Local Highway Authority, in this case Lancashire County Council
Public Open Space (POS): Land provided within a development for use by the public for recreation or amenity
CEMP: Construction Environmental Management Plan, a document setting out how construction impacts will be controlled
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7a
Resolved
Planning permission granted, subject to conditions and a S106 legal agreement to secure the following: · A bus service contribution of £40,000 per annum for three years (to be staggered so as to not overlap with payments being made by the developer associated with the Phase I development which is for five years). · Public Open Space contributions totalling £182,400 with an additional £39,900 if for a ten year period if private maintenance is not to be used. · Details of affordable housing.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
APPLICATION REPORT – 25/00457/FULMAJ Validation Date: 19 May 2025
Ward: Eccleston, Heskin And Charnock Richard
Type of Application: Major Full Planning
Proposal: Erection of 57 no. affordable dwellings, access, parking, landscaping and all other associated works
Location: Land 120M East Of 27 Charter Lane Charnock Richard
Case Officer: Mike Halsall
Applicant: Westchurch Homes Ltd
Agent: Maybern Planning & Development Ltd
Consultation expiry: 27 October 2025
Decision due by: 31 January 2026
UPDATE REPORT
1. Members will recall that a decision on this application was deferred at the December Planning Committee to allow Members to visit the application site.
2. The recommendation remains the same as the previous report (below), although officers consider it pertinent to cover some additional issues raised by Members during the debate at the previous planning committee.
The sustainability of the site
3. The sustainability of the site is addressed at paragraphs 25 to 28 and 118 to 122 of the original committee report (below). In summary, it is accepted that Charnock Richard is not identified in either to adopted Chorley Local Plan 2012-2026 or the submitted Central Lancashire Local Plan as an area for major growth and there is policy conflict in this regard. However, the policy forms part of a failing strategy as the Council cannot demonstrate an adequate supply of housing. As such, the policy is only afforded moderate weight and the adverse impacts of the proposed development relating to the conflict with the development strategy would not significantly and demonstrably outweigh the considerable economic and significant social benefits.
Surface water drainage
4. Members queried whether the surface water attenuation pond for the Phase 1 development is sufficient to accommodate the additional load from this new proposal. Surface water drainage is addressed at paragraphs 84 to 92 of the original committee report. Surface water from the Phase 2 development would be stored within the Phase 2 site beneath car parking and public open space areas, and released at a controlled rate of discharge (attenuated) into the Phase 1 drainage basin, before being discharged into the culverted watercourse of Clancutt Brook at an attenuated rate. The hydrobrake within the Phase 1 development would need to be upgraded to take the drainage from the Phase 2 development, however, the pond itself is of a sufficient size to accommodate both schemes. This has been agreed in principle with the Lead Local Flood Authority who are the statutory technical consultee for surface water drainage. The precise details of this would be agreed through pre-commencement conditions and no dwelling is able to be occupied until the drainage system is demonstrated to be working correctly (conditions 24 to 27).
The use of the emergency access road
5. This is addressed at paragraph 69 of the original report which provides a copy of LCC Highway Services’ comments in relation to the proposal. In summary, LCC Highway Services have no objection to the provision of this emergency access, given its anticipated infrequent use, if at all, and to prevent it from functioning as an informal secondary access, internal bollards will be installed. It is worth noting that the link will be used as an active travel link to Charter Lane. The link is not a requirement of the scheme, but simply an alternative access for emergency vehicles in the unlikely event that the road through the Phase 1 scheme is ever blocked and provides a sustainable link for pedestrians and cyclists.
Highway impact on Charter Lane and the Transport Survey being 3 years old
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
25/01052/FULMAJ - Moor Road, CrostonPlanning permission was minded to be refused for the following reason: ‘The application is contrary to policy 1 of th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.