Cabinet, Friday 13 February 2026 at 10.00am

Council Performance Report 2025/26 (Q3)

Decided Executive 4 papers

AI summaryCabinet noted Cornwall Council's Q3 2025/26 performance report, which projects a £9.1m revenue overspend against an £841.8m budget, driven mainly by social care placement costs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedQ3 2025/26 performance report approved as drafted
Money£9.1m overspendAgainst £841.8m budget, forecast spend £850.9m
What happens nextScrutiny reviewFinance and Performance Scrutiny Committee on 17 March 2026
Who it affectsCornwall residentsEspecially social care and housing service users

What was decided

Cabinet received the Q3 2025/26 performance report and approved the recommendations as contained within it. Report 10.1

The report sets out a projected revenue overspend of £9.1m against a budget of £841.8m, an increase of £1.2m from the Q2 position. Report 1.3

The capital programme is tracking broadly in line with budget, with a Q3 forecast of £373.6m against an approved budget of £377.3m. Report 1.6, 2.11

Why

The overspend is driven primarily by rising costs of placements for children and young people with complex needs and increasing Adult Social Care commissioning costs. Report 1.4, 1.17

Adult Social Care commissioning costs, previously reported as a risk, have materialised during the year, adding £10.1m to the forecast overspend. Report 1.4, 2.4

Interventions agreed by Cabinet in November 2025 are being implemented to reduce the in-year overspend with minimal impact on service delivery. Report 1.5, 2.7

What happens next

The Corporate Finance and Performance Overview and Scrutiny Committee will consider the report on 17 March 2026. Report P21

The Council will continue to identify mitigations to manage the forecast position and prevent it increasing further. Report 2.3

The S151 Officer will consider the adequacy of the reserve balance in the budget report also presented to Cabinet on this agenda. Report 2.3

The money

  • £9.1m Projected revenue overspend at year end Report 1.3
  • £841.8m Approved revenue budget for 2025/26 Report 1.3
  • £850.9m Forecast revenue spend at year end Report 1.3
  • £17.7m Children and Family Services forecast overspend Report 2.4, 2.78
  • £10.7m Adult Care Services forecast overspend Report 2.4
  • £10.6m Current Financial Sustainability Reserve balance Report 2.3
  • £1.5m Reserve balance after funding the overspend Report 2.3
  • £48.8m Approved savings target for 2025/26

Options considered

  • Chosen: Approve the recommendations as drafted. Preferred option as set out in the report Report 10.1
  • Rejected: Approve a variance of the recommendations. Would require analysis of implications before decision

Implications

  • Financial: Revenue overspend of £9.1m will be funded from the Financial Sustainability Reserve, reducing the balance from £10.6m to £1.5m. Report 2.3
  • Risk: Strategic risks rated very high include Global and Macro Economic Shocks, Financial and Economic Sustainability, and Sustainable Cornwall. Report 8.4, 8.5, 8.6
  • Staffing: Cornwall Fire and Rescue Service has vacancies affecting Fire Safety Audit performance, and Corserv Facilities has very high staff turnover of 79.80%. Report 2.83, P90
  • Legal: The Council must be mindful of operating within budget and its fiduciary duty to the taxpayer, with risk of legal challenge if service cuts are made unlawfully. Report 7.1

Who and where

  • Children in care, with numbers rising to 654 and average placement cost of £0.104m Report 2.78
  • Adult Social Care service users, facing rising demand and increasing complexity Report 1.18
  • Rough sleepers, with numbers rising from 67 to 81 this quarter
  • Households in temporary or emergency accommodation, around 850 households Report 2.37
  • Bus passengers facing service changes from 14 February 2026 due to a major operator's withdrawal Report 1.19
  • Cornwall residents, with overall satisfaction with the area as a place to live at 83%, 11% above the national figure Report 2.22

Timeline

  • 12 November 2025: Cabinet agreed a series of interventions to reduce the in-year overspend Report 1.5
  • 1 October to 31 December 2025: Q3 reporting period covered by this report Report 1.1
  • 14 February 2026: Major commercial bus operator announced intention to cease service in Cornwall Report 1.19
  • 17 March 2026: Corporate Finance and Performance Overview and Scrutiny Committee to consider the report Report P21
  • 31 March 2026: End of 2025/26 financial year Report 2.1
  • Q1 2026/27: Reformed online performance dashboard to be reintroduced Report 1.2

Plain English for the jargon

  • UNCRC: United Nations Convention on the Rights of the Child, formally adopted by Cabinet in December 2025
  • Awaab's Law: New regulations requiring faster responses to damp and mould issues in social housing
  • EHCP: Education, Health and Care Plan, with rising demand affecting timeliness
  • PWLB: Public Works Loan Board, a benchmark for long-term borrowing rates
  • LOBO: Lender Option Borrower Option loans, two of which were called in 2025/26 totalling £24m
  • S151 Officer: Statutory Chief Finance Officer responsible for the Council's financial affairs
  • Bellwin scheme: Government scheme to help councils recover costs of emergency responses, to be used for Storm Goretti
  • CWP: Cold Weather Provision opened in December for rough sleepers
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB/513

Resolved

DECISION: As contained within the report.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Cabinet, 25 pages

Executive summary

1.1The report provides an overview of the Council’s performance during Quarter 3 (1 October to 31 December 2025). Information Classification: PUBLIC

1.2At the Cabinet meeting on 30 July, the Leader announced a new set of priorities designed to tackle Cornwall’s greatest challenges. These priorities will form the basis of a new Council Plan for 2026-2030. Given the introduction of new priorities, the online performance dashboard is being reformed and will be reintroduced for Q1 2026/27. In the interim, a table of key performance indicators is provided at Appendix 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Performance Report 2025/26 (Q3): Appendix 1: Performance Data /513Appendix 19 pages Download
PDF
Council Performance Report 2025/26 (Q3): Appendix 2: Quarter 3 Finance Performance /513Appendix 28 pages Download
PDF
Council Performance Report 2025/26 (Q3): Appendix 3: Treasury Report /513Appendix 14 pages Download
PDF
Council Performance Report 2025/26 (Q3)Report 25 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Cornwall

Search all
  1. Council Performance Report 2025/26 (Q3)This decision
  2. Council Performance Report 2026/27(Q2)Decided
  3. Adult Social Care Performance, Outcomes and Continuous Improvement UpdateDecided
  4. Individual Decision - Key Performance Indicators for Cornwall Fire and Rescue Service as part of the Community Risk Management PlanApproved
  5. Council Performance Report 2025/26 (Q4)Decided
  6. Cornwall and Isles of Scilly Integrated Performance ReportNoted

More from Cornwall Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Minutes of the Meeting Held on 23 September 2026 / Kovnotennow an Kuntelles Synsys 23 mis Gwynngala 2026It was proposed by Councillor Frost, seconded by Councillor Paynter and RESOLVED that the minutes of the Cabinet meet... Decided Open
11 Nov 2026 Council Performance Report 2026/27(Q2)DECISION: As contained within the report. Decided Open
11 Nov 2026 Digital Connectivity Investment ProgrammeDECISION: As contained within the report. Decided Open
11 Nov 2026 Cornwall Education Partnership Education StrategyDECISION: As contained within the report. Decided Open
11 Nov 2026 Farms Strategy 2019-2039 (2026 Review)DECISION: Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies