Local Plan Update - Final Interim Report on Local Plan progress, including Baseline report, recommended timetable, process and next steps

Decided Executive 3 papers

AI summaryCornwall Cabinet has approved the start of formal Local Plan work, signalled its intent to act as the Strategic Planning Authority for a Cornwall only Spatial Development Strategy, and released a further £1.200m from reserves.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedAll 7 recommendations accepted as in report
Money£1.200m additionalFrom Place and Green Growth reserve
What happens nextPublish notice April 2026Gateway 1 by December, consult January 2027
Who it affectsCornwall residents and planning systemPlus neighbours, parishes, developers, and investors

What was decided

Cabinet approved all 7 recommendations in the report, including delegating authority to the Service Director for Planning and Housing to publish the notices and timetables needed to start formal Local Plan work and to prepare a Spatial Development Strategy for Cornwall. Report P1, P2

Cabinet confirmed the Council's intent to act as the Strategic Planning Authority for Cornwall, subject to relevant enabling legislation. Report P2, 7.4

Cabinet approved an additional £1.200m from the Place and Green Growth reserve, on top of the £2.540m already approved, taking total programme funding to £3.740m. Report P2, 6.1

Why

New national plan making regulations come into force on 25 March 2026, and without proactive progress the Council could face Government sanctions for not having an up to date plan. Report 1.8

A Cornwall only Spatial Development Strategy is presented as the most fitting geography for strategic planning, reflecting the Council's planned Foundation Strategic Authority status and Cornwall's identity and scale. Report 1.5, 1.6, 2.14

Community engagement across 12 Community Area Partnerships set out consistent themes of affordable homes, infrastructure clarity, town centre renewal, protection of green and blue assets, and clearer understanding of how planning decisions are made. Report 2.10, P87, P88, P89, P90

What happens next

Publish a notice of intent for the Local Plan in April 2026, then use the period to summer 2026 to scope strategic and growth distribution matters. Report P69, 2.44

Reach Gateway 1 self assessment in December 2026, with public consultation in January 2027. Report P70, P71, 2.44

Run the Spatial Development Strategy in parallel with the Local Plan on a common evidence base, aiming to have the Local Plan submitted to the Secretary of State within the current administration, with adoption by the next. Report 2.23, 2.45

The money

  • £1.200m Additional funding from the Place and Green Growth reserve approved on 18 March 2026 Report 6.1, P2
  • £2.540m Previously approved funding from the Place and Green Growth reserve for 2025/26 and 2026/27 Report 6.1
  • £3.740m Total approved funding forecast to 2027/28 Report 6.1
  • £1.340m Estimated further funding needed across 2028/29 to 2029/30 to conclude the project

Options considered

  • Chosen: Option 1: Publish notice and progress a new Local Plan, including developing options for a Spatial Development Strategy. Recommended approach as set out in the report Report 10.3, P128
  • Rejected: Option 2: Publish notice and progress a new Local Plan, but do not progress a Spatial Development Strategy at this time Report 10.4
  • Rejected: Option 3: Do not progress a new Local Plan and instead rely on national development management policies as they emerge Report 10.5

Implications

  • Financial: A further £1.200m from the Place and Green Growth reserve takes total programme funding to £3.740m, with an estimated further £1.340m needed across 2028/29 to 2029/30. Report 6.1
  • Legal: Work must align with the National Planning Policy Framework, the Levelling up and Regeneration Act 2023, the Planning and Infrastructure Act 2025, and the emerging English Devolution and Community Empowerment Bill. Report 7.1
  • Risk: National policy direction remains fluid, transport modelling approaches carry challenge risk, and any programme slippage would increase costs. Report 6.5, 8.1, 8.4
  • Staffing: Resources are committed to the programme and a structure of thematic work streams is in place, with most work delivered in house and specialist external support for infrastructure and transport modelling. Report 2.7
  • Other: Cross border cooperation with Devon, Plymouth, and the Council of the Isles of Scilly is reaffirmed, with particular focus on the east of Cornwall, including travel to work, education, and health links. Report 2.17, 2.39, P60

Who and where

  • Cornwall residents across the 12 Community Area Partnerships Report 5.1, 2.10, P85
  • Town and Parish Councils, including through Neighbourhood Priority Statements Report 5.13
  • Neighbouring authorities in Devon, Plymouth, and the Isles of Scilly Report 2.17, 2.39
  • Developers, investors, and infrastructure providers seeking planning certainty Report 1.7
  • Members of the Council, via the Member working group chaired by the Portfolio Holder for Localism, Tourism and Planning Report 5.15, 5.16

Timeline

  • 25 March 2026: Commencement regulations for the new Local Plan system come into force Report 1.8
  • April 2026: Council to publish notice of intent for the Local Plan Report P69, 2.44
  • Summer 2026: Scoping of vision and growth distribution matters Report P69
  • June 2026: Spatial Development Strategy regulations expected to be published Report 1.8, 2.11
  • December 2026: Gateway 1 self assessment for the Local Plan Report P70, 2.44
  • January 2027: Public consultation on the Local Plan Report P71, 2.44
  • End of current administration (May 2029): Local Plan expected to be submitted within this term, with adoption by the next Report 2.23

Plain English for the jargon

  • Spatial Development Strategy (SDS): A strategic level planning document covering broad patterns of settlements, growth, and infrastructure.
  • Foundation Strategic Authority (FSA): The devolution status the Council is working towards.
  • National Planning Policy Framework (NPPF): The Government's national planning policy document.
  • Infrastructure Delivery Plan (IDP): The Council's tool for assessing infrastructure needs, costs, and funding shortfalls.
  • Neighbourhood Priority Statement (NPS): A council level evidence document that feeds into the Local Plan but does not form policy in its own right.
  • Housing and Economic Needs Assessment (HENA): Assessment of housing and economic need used in the plan.
  • Housing and Economic Land Availability Assessment (HELAA): Assessment of land availability used alongside the HENA.
  • Community Area Partnership (CAP): The geographic area used for community engagement events.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB/530

Resolved

DECISION: As contained within the report.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Cabinet, 24 pages

Recommendations

1. That authority be delegated to the Service Director for Planning and Housing to publish the notices and timetables required, as set out in Appendix 1 to the report, to initiate the formal stages of work on a Local Plan for Cornwall. 2. That authority be delegated to the Service Director for Planning and Housing to respond to the Government consultation on Spatial Information Classification: PUBLIC

Development Strategy geographies to set out the Council’s wish to prepare one for Cornwall specifically, consistent with our intended Foundation Strategic Authority status. 3. That authority be delegated to the Service Director for Planning and Housing to commence any necessary work (including publication of notices or timetables, as set out in Appendix 1 to the report, unless otherwise directed by the Cabinet) relating to the preparation of a Spatial Development Strategy for Cornwall, using a common evidence base with the Local Plan and seeking to align the associated timetables, subject to any relevant enabling regulations. 4. That, in respect of recommendation 3 above, the Council confirms its intent to act as the Strategic Planning Authority for Cornwall, subject to the relevant enabling legislation. 5. Notwithstanding recommendations 1 to 4 above, that the Council confirms its intent to properly and fully work in co-operation with neighbouring authorities on matters of shared interest, including but not limited to those informed by relevant travel to work areas, education and health facilities that relate specifically to the east of Cornwall and key rail, road and ferry links, as well as acknowledging the key role of the strategic route to the Isles of Scilly and associated links to further education. 6. That the first report on community engagement work, as set out at Appendix 2 to the report, be accepted as a key reference point for further developing the vision, principles and themes for the Spatial Development Strategy and Local Plan. 7. That a further £1.200m from the Place & Green Growth reserve be approved to support the programme costs which are in addition to the previously approved reserve funding of £2.540m.

Executive summary

1.1This paper is about taking the practical and procedural steps necessary to ensure we can properly plan for development, infrastructure and nature at a level which is relevant to Cornwall and its identity. It provides additional context for this by also reporting on the perspectives gathered from 24 community engagement events held over the winter and an update on ongoing work on the Land Use study.

1.2Much of the paper discusses the interaction between two formal planning documents – a Local Plan and a Spatial Development Strategy. Together, they form the Development Plan. Between those two documents we need to Information Classification: PUBLIC

balance how we deal with broad strategic issues across Cornwall and the more detailed aspects of allocating specific sites.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Plan Update: Final Interim Report on Local Plan progress, including Baseline report, recommended timetable, process and next steps: Appendix 1 /530Appendix 4 pages Download
PDF
Local Plan Update: Final Interim Report on Local Plan progress, including Baseline report, recommended timetable, process and next steps: Appendix 2 /530Appendix 21 pages Download
PDF
Local Plan Update: Final Interim Report on Local Plan progress, including Baseline report, recommended timetable, process and next stepsReport 24 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Cornwall

Search all
  1. Local Plan Update - Final Interim Report on Local Plan progress, including Baseline report, recommended timetable, process and next stepsThis decision
  2. CQC Local Authority Inspection Report and Continuous Improvement Plan FrameworkNoted
  3. Cornwall Local Area SEND Reform PlanAgreed

More from Cornwall Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Minutes of the Meeting Held on 23 September 2026 / Kovnotennow an Kuntelles Synsys 23 mis Gwynngala 2026It was proposed by Councillor Frost, seconded by Councillor Paynter and RESOLVED that the minutes of the Cabinet meet... Decided Open
11 Nov 2026 Council Performance Report 2026/27(Q2)DECISION: As contained within the report. Decided Open
11 Nov 2026 Digital Connectivity Investment ProgrammeDECISION: As contained within the report. Decided Open
11 Nov 2026 Cornwall Education Partnership Education StrategyDECISION: As contained within the report. Decided Open
11 Nov 2026 Farms Strategy 2019-2039 (2026 Review)DECISION: Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies