Tamar Bridge and Torpoint Ferry Joint Committee, Friday 26 June 2026 at 10.00am

Budget Outturn Report 2025-2026

Approved Committee 3 papers

AI summaryTamar Bridge and Torpoint Ferry Joint Committee approved the 2025/26 outturn, showing a revenue surplus of £0.498m and capital spend of £4.316m. The draft Annual Governance Statement was also approved.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved2025/26 outturn and Annual Governance Statement approved, subject to audit
Money£0.498m revenue surplusSurplus £0.078m below revised budget
What happens nextAudit review to followCornwall Council Audit Services to review accounts
Who it affectsBridge and ferry usersTamar Bridge and Torpoint Ferry users

What was decided

The 2025/26 outturn report is approved, subject to audit.

The draft Annual Governance Statement is approved.

Why

The outturn shows a revenue surplus of £0.498m against the revised budget, with capital expenditure of £4.316m. Report 2.2

An Annual Governance Statement supports the governance framework required for the Joint Committee's funds, although no longer a statutory requirement. Report 1.5, 1.6, 1.7

Approving the recommendations confirms that finances are being managed effectively and budget variances are explained. Report 10.1

What happens next

Cornwall Council Audit Services will undertake a review of the Joint Committee's governance framework and financial statements for the year ended 31 March 2026. Report 1.7

Capital underspends will be reprofiled into 2026/27, including Bridge Access, Rocker/Pendle, Main Cable Remedial Works, Bridge Structural Fire Protection and Torpoint Office and Workshop schemes. Report P50, P52, P53, P54, P55

Deferred revenue items, including bridge and gantry inspections, the updated Open Road Tolling Business Case and the Economic and Social Benefit Study, will be incurred in 2026/27. Report P19, P39

The money

  • £0.498m Revenue surplus for 2025/26 Report 2.2
  • £0.078m Unfavourable revenue variance against revised budget Report 2.3
  • £4.316m Capital expenditure for 2025/26 Report 2.4
  • £6.765m Revised capital budget for the year
  • £1.414m Reserve position as at 31 March 2026 Report 2.6
  • £1.573m Forecast reserve position (executive summary)
  • £718,000 Overspend on 2024-2026 Ferry Refit programme Report P51
  • £1,675,000 Underspend on Main Cable Remedial Works, reprofiled to 2026/27 Report P53

Options considered

  • Chosen: Agree both recommendations, approve 2025/26 outturn (subject to audit) and Annual Governance Statement. Confirms finances are managed effectively and budget variances are explained Report 10.1
  • Rejected: Do not agree either or both recommendations. Would mean the Joint Committee does not approve the outturn position and/or the Annual Governance Statement

Implications

  • Financial: Revenue outturn was a surplus of £0.498m, £0.078m less than the revised estimate. Report 2.2
  • Financial: Capital spend of £4.316m was £1.553m below the revised forecast, with several schemes reprofiled to 2026/27. Report 2.4, P50, P52, P53, P54, P55
  • Financial: Reserves at 31 March 2026 stood at £1.414m, compared with forecast figures of £1.573m in the executive summary and £1.492m in paragraph 2.6. Report 2.6
  • Other: No legal or governance implications arising from the report. Report 7.1
  • Risk: No risk implications arising from the report. Report 8.1

Who and where

  • Users of the Tamar Bridge and Torpoint Ferry crossings Report 3.1
  • Cornwall Council and Plymouth City Council as constituent authorities Report 1.6
  • Residents and businesses served by the crossings, supporting sustainable economic and social development of the region Report 3.1

Timeline

  • May 2025: Toll revision implemented, later than the original budget assumption Report P12
  • 2026/27: Deferred capital works, bridge inspections, and consultancy studies to be incurred Report P19, P39, P50, P52, P53, P54, P55
  • 31 March 2026: End of 2025/26 financial year; reserves stand at £1.414m Report 2.6
  • 26 June 2026: Joint Committee meeting approves outturn and governance statement

Plain English for the jargon

  • TAG: Electronic toll account used by users of the crossings
  • Outturn: The actual income and expenditure for a financial year, compared to the budget set
  • Annual Governance Statement: A statement setting out the governance framework and how it is reviewed and maintained
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemTBTF/131

Resolved

RESOLVED that 1. The 2025/26 outturn report is approved, subject to audit. 2. The draft Annual Governance Statement is approved.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Tamar Bridge and Torpoint Ferry Joint Committee, 11 pages

Executive summary

1.1The report presents the Joint Committee’s revenue and capital outturn against budget for 2025/26 financial year, subject to audit. 1.2 The outturn report included in Appendix 1, follows the normal format for presentation to the Joint Committee. It emphasises management account information such as detailed analysis of revenue and capital, income and expenditure and a comparison of actuals against the revised budget (and original budget). 1.3 The revenue position currently shows an overall surplus of £0.498m, an unfavourable variance of £0.078m compared to the revised budget. In relation to capital, the position shows expenditure of £4.316m against the revised budget for the year of £6.765m. 1.4 The reserve position as at 31 March 2026 is £1.414m, compared to the forecast reserve position of £1.573m.

1.5Since the introduction of the Accounts and Audit Regulations of 2015, there is no longer a requirement for the accounts to be signed off by the Joint Committee or for the provision of an Annual Governance Statement.

1.6Whilst there is no statutory obligation in place for the Joint Committee to commission a review of their financial statements by an appointed auditor, there is still an obligation for constituent authorities to ensure that an effective financial and governance framework is maintained for their Joint Committees and the funds that they control.

1.7In order to provide the required assurance Cornwall Council’s Audit Services will be undertaking a review of the Joint Committee’s governance framework and financial statements for the year ended 31 March 2026. An Annual Governance Statement supports this framework.

2 Purpose of Report and key information

Summary Revenue and Capital Outturn

2.1The Joint Committee’s revenue account for the financial year 2025/26 has been finalised, subject to audit. This report sets out the actual spending for the year, compares this with the revised budget and explains the main variations. Information Classification: PUBLIC

2.2The summary table on page 1 of Appendix 1 shows the Joint Committee’s revenue spending compared with the revised budget for 2025/26. The outturn for 2025/26, subject to audit, shows that the actual surplus for the year is £0.498m, which is £0.078m less than the revised estimate.

Summary of variation from revised estimates

2.3The net variation of £0.078m is accounted for as follows:

Operational Income and Expenditure £'000 Income (page 2 of appendix 1)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Outturn Report 2025-2026Report 11 pages DownloadRead as text
PDF
TBTFJC: 2025-26 Budget Outturn: Appendix 1 /131Appendix 7 pages Download
PDF
TBTFJC: 2025-26 Budget Outturn: Appendix 2 /131Appendix 6 pages Download

At this meeting

Whole meeting

On this subject at Cornwall

Search all
  1. Budget Outturn Report 2025-2026This decision
  2. Cornwall Harbours Board Budget Outturn April 2025 - March 2026Noted
  3. Budget Outturn Report April 2025 to March 2026Noted

More from Cornwall Tamar Bridge and Torpoint Ferry Joint Committee

All decisions
MeetingDecisionOutcome
25 Sep 2026 Minutes of the Meeting held on 26 June 2026RESOLVED hat the Minutes of the meeting of the Tamar Bridge and Torpoint Ferry Joint Committee held on 26 June 2026 w... Decided Open
25 Sep 2026 Internal Audit ReportRESOLVED that the Joint Committee notes the outcome of the 2025/26 internal audit review of Tamar Bridge & Torpoint F... Decided Open
25 Sep 2026 Statement of Accounts and Audit Findings 2025/26RESOLVED that 1. The Joint Committee note the Audit Findings 2. The Joint Committee endorse the draft Statement of Ac... Noted Open
26 Jun 2026 Election of Joint Chair (Cornwall)RESOLVED that Councillor Long be elected as Joint Chairman (Cornwall) for the Tamar Bridge and Torpoint Ferry Joint C... Decided Open
26 Jun 2026 Election of Joint Chair (Plymouth)RESOLVED that Councillor Stephens be elected Joint Chairman (Plymouth) for the Tamar Bridge and Torpoint Ferry Joint ... Decided Open