Tamar Bridge and Torpoint Ferry Joint Committee, Friday 26 June 2026 at 10.00am

Budget Monitoring Report 2026-27

Noted Committee 2 papers

AI summaryTamar Bridge and Torpoint Ferry Joint Committee noted the 2026/27 revenue forecast and capital programme at its 26 June 2026 meeting.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevenue forecast and capital programme for 2026/27
MoneyNot stated
What happens nextNot stated
Who it affectsNot stated

What was decided

The committee resolved that the revenue forecast and capital programme for 2026/27 be noted.

Why

The papers supplied contain no reasoning beyond the report clearance process. Report 12.1, P2, P3, P4

What happens next

No further steps are set out in the papers provided. Report 12.1, P2, P3, P4

Timeline

  • 11/06/2026: Report cleared by Governance/Legal Manager and Finance Manager Report P4
  • 15/06/2026: Report cleared by Service Director Report P4
  • 18/06/26: Report cleared by Strategic Director Report P4
  • 2026-06-26: Joint Committee meeting
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemTBTF/132

Resolved

RESOLVED that the revenue forecast and capital programme for 2026/27 be noted.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Tamar Bridge and Torpoint Ferry Joint Committee, 6 pages

Information Classification: PUBLIC

Report to: Tamar Bridge & Torpoint Ferry Joint Committee Date: 26 June 2026

Title: 2026 - 2027 Budget Monitoring

Portfolio Area: Cornwall Council: Transport

Plymouth City Council: Strategic Planning & Transport

Divisions Affected: All

Local Member(s) N/A briefed:

Relevant Scrutiny Committee:

Cornwall Council: Sustainable Growth and Place

Plymouth City Council: Natural Infrastructure & Growth

Authors, Geraldine Baker, Finance Analyst Manager Roles and Contact 01872 322222 [email protected] Details: Andrew Vallance, Governance and Finance Manager 01752 361577 [email removed]

Approval and clearance obtained: Y/N

Date next steps can be taken 26 June 2026

For Cabinet and delegated executive decisions only

Key decision? (≥£500k in value or significant effect on N/A communities in two or more electoral divisions)

Published in advance on Cabinet Work Programme? N/A

Urgency Procedure(s) used if ‘N’ to Work Programme? N/A

Recommendation(s):

1. That the revenue forecast and capital programme for 2026/27 be noted.

1 Executive Summary Information Classification: PUBLIC

1.1The report contains the budget monitoring statement and forecast outturn position based on actual information available at the end of May 2026.

1.2The statement shows the current expenditure and income for 2026/27 and compares this with the forecast. It also contains an update on the capital programme for the same period. 1.3 The revenue position currently shows an overall surplus of £0.730m, an adverse variance of £0.077m year to date compared to the forecast. The position at the end of March 2027 is forecast to be an overall deficit of £0.128m. 1.4 Within Capital, the position shows expenditure of £0.212m against the budget for the year of £5.483m. 1.5 The forecast reserve position (taking into account the draft outturn) based on our current estimate is a surplus of £1.286m as at 31 March 2027.

2 Purpose of Report and key information

2.1The Joint Committee receives a quarterly update on its financial position in order to provide assurance that the finances of the undertaking are being managed appropriately and that any significant issues are highlighted, and necessary actions taken to address them.

2.2The revenue statement in Appendix 1 shows the position for the period covering 1 April 2026 to 31 May 2026 and the forecast for the financial year to 31 March 2027. The forecast highlights the continuing volatility and suppression of the cash (full price) toll income. 2.3 Within the Bridge cost centre, the current favourable variance is £0.127m compared to the budget to date. The main variances that cumulatively contribute to this are within the following areas: 2.4 Bridge painting – although the main focus has been on a capital recoating scheme, a contingency provision was made in the budget for reactive tasks which has not yet been used, this lack of reactive activity results in a favourable variance of £0.072m. 2.5 Toll equipment - required updates are currently being scoped and priced and expected to be implemented later in the year, this was included in the budget but is causing the favourable variance of £0.029m to date due to the timing issue. Information Classification: PUBLIC

2.6The Ferry cost centre currently shows an adverse variance of £0.030m compared to the budget. The main variances are detailed in subsequent paragraphs:

2.7Employee costs - shows a favourable variance of £0.049m, which is a reflection of the number of open vacancies not filled but currently being recruited.

2.8Ferry and Vehicle Maintenance – significant maintenance work associated with service delivery challenges at the start of the financial year which are reported in the Chief Officers report leading to the current adverse variance to date of £0.061m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Monitoring Report 2026-27Report 6 pages DownloadRead as text
PDF
TBTFJC: 2026-27 Budget Monitor: Appendices 1 & 2 /132Report 2 pages Download

At this meeting

Whole meeting

On this subject at Cornwall

Search all
  1. Budget Monitoring Report 2026-27This decision
  2. Budget Monitoring Report April 2026 – August 2026Noted
  3. Budget Monitoring Report April 2025 - Jan 2026Noted
  4. 2025-26 Budget Monitoring ReportNoted

More from Cornwall Tamar Bridge and Torpoint Ferry Joint Committee

All decisions
MeetingDecisionOutcome
25 Sep 2026 Minutes of the Meeting held on 26 June 2026RESOLVED hat the Minutes of the meeting of the Tamar Bridge and Torpoint Ferry Joint Committee held on 26 June 2026 w... Decided Open
25 Sep 2026 Internal Audit ReportRESOLVED that the Joint Committee notes the outcome of the 2025/26 internal audit review of Tamar Bridge & Torpoint F... Decided Open
25 Sep 2026 Statement of Accounts and Audit Findings 2025/26RESOLVED that 1. The Joint Committee note the Audit Findings 2. The Joint Committee endorse the draft Statement of Ac... Noted Open
26 Jun 2026 Election of Joint Chair (Cornwall)RESOLVED that Councillor Long be elected as Joint Chairman (Cornwall) for the Tamar Bridge and Torpoint Ferry Joint C... Decided Open
26 Jun 2026 Election of Joint Chair (Plymouth)RESOLVED that Councillor Stephens be elected Joint Chairman (Plymouth) for the Tamar Bridge and Torpoint Ferry Joint ... Decided Open