Reserve request for contribution to capital projects

Decided Committee 3 papers

AI summaryCornwall Harbours Board approved £90,500 from its general reserve for structural repairs at St Ives and Portreath Harbours, supplementing the council's 2026/27 capital programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved£90,500 from general reserve to capital programme
Money£90,500From Harbours General Reserve to capital projects
What happens next9 July 2026Work can proceed on the funded repairs
Who it affectsSt Ives and Portreath HarboursUsers, residents and visitors

What was decided

The Board approved using £90,500 of the Cornwall Harbours General Reserve to part fund structural repairs at St Ives and Portreath Harbours. Report P17

Why

An £800,000 allocation was made in the Environment Capital Programme 2026/27 for essential maintenance at St Ives, Portreath and Penzance Harbours, and the reserve contribution enables these projects to be completed. Report 1.1, 2.1

Match funding lets the Board meet its statutory duty to keep harbours safe and open for users, residents and visitors. Report 3.1

What happens next

The £90,500 will be transferred to the Cornwall Council Capital Programme, with repairs including breakwater capping stones at Portreath and Sloop Slipway and wharf works at St Ives to be taken forward from 9 July 2026. Report P11, 2.1, P21, P23, P24

The money

  • £90,500 Requested transfer from Cornwall Harbours General Reserve to the capital programme Report P17, 2.1, 6.1
  • £271,500 Combined cost of the St Ives and Portreath projects covered by this report Report 2.1
  • £181,000 Funded from the Cornwall Council Capital projects budget for St Ives and Portreath Report 2.1
  • £528,500 Allocated to Penzance Harbour works Report 2.1
  • £800,000 Total Environment Capital Programme 2026/27 allocation for the three harbours Report 1.1
  • £913,919 Balance of the Cornwall Harbours General Reserve as at March 2026 Report 6.1

Options considered

  • Chosen: Approve the £90,500 transfer from the Cornwall Harbours General Reserve to the capital programme. Enables the St Ives and Portreath projects to be completed and supports statutory duty to keep harbours safe and open. Report 10.1, 3.1
  • Rejected: Do not approve the £90,500 transfer. A reduction in project scope would be required. Report 10.1, 8.1

Implications

  • Financial: £90,500 will leave the Cornwall Harbours General Reserve, which had a balance of £913,919 at March 2026. Report 6.1, P17
  • Legal: No legal or governance implications identified. Report 7.1
  • Risk: If the Board had refused the transfer, the project scope would have needed to be reduced. Report 8.1

Who and where

  • Users, local residents and visitors of St Ives and Portreath Harbours Report 3.1, P6
  • Portreath Harbour User Association Report 5.2
  • St Ives Harbour Stakeholder Group Report 5.3
  • Penzance Harbour Stakeholder Group Report 5.4

Timeline

  • March 2026: Balance of Cornwall Harbours General Reserve recorded at £913,919 Report 6.1
  • 9 July 2026: Cornwall Harbours Board decision and next steps can be taken Report P3, P11

Plain English for the jargon

  • Cornwall Harbours General Reserve: Reserve fund held by the Cornwall Harbours Board, used here to top up the council's capital programme for harbour repairs.
  • Environment Capital Programme 2026/27: Cornwall Council's capital funding stream from which £800,000 has been allocated to harbour works.
  • Sloop Slipway: A slipway at St Ives Harbour where repairs to four bays are planned.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCHB39

Resolved

RESOLVED that £90,500 of the Cornwall Harbours General Reserve would be used to fund part of structural repairs needed for St Ives and Portreath Harbours.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Cornwall Harbours Board, 4 pages

Information Classification: CONTROLLED

Report to: Cornwall Harbours Board

Date: 9 July 2026

Title: Reserve request for contribution to capital projects

Portfolio Area: N/A

Divisions Affected: Primarily those around the municipal ports and harbours at St Ives, Portreath & Penzance Harbours

Local Member(s) No briefed:

Relevant Scrutiny Committee: Harbour Management Committee

Authors, Vicky Fraser - Service Director for Environment and Connectivity Roles and [email protected] Contact Details: Chris Jones – Maritime Manager [email protected]

Approval and clearance obtained: Y

Date next steps can be taken 9 July 2026

For Cabinet and delegated executive decisions only

Key decision? (≥£500k in value or significant effect on N/A communities in two or more electoral divisions)

Published in advance on Cabinet Work Programme? N/A

Urgency Procedure(s) used if ‘N’ to Work Programme?] N/A

Recommendation(s):

To use £90,500 of the Cornwall Harbours General Reserve to fund part of structural repairs needed for St Ives, Portreath and Penzance Harbours.

1 Executive Summary Information Classification: CONTROLLED

1.1To supplement the Harbours repairs and maintenance budget a request for additional capital funding was made to fund essential maintenance work at St Ives Harbour, Portreath and Penzance Harbours. An allocation of £800,000 has been granted in the Environment Capital Program 26/27. The following projects will be undertaken:

Portreath Harbour

• Remove, repair of make good capping stones on breakwater, in consultation with Cornwall Council’s Catchment & Coastal Lead. Please see Appendix 1.

St Ives Harbour

• Repairs to Sloop Slipway (4 bays). Please see Appendix 2

• Void filling of the wharf and re-pointing

Penzance Harbour

• Void filling and pointing of Lighthouse Pier

2 Purpose of Report and key information

2.1The purpose of this report is to seek a financial contribution from Cornwall Harbours Board to the Cornwall Council Capital Program (Environment Service). A contribution of £90,500 is requested for projects at St Ives and Portreath Harbours. The combined cost of these projects totals £271,500 of which £181,000 is being funded from Cornwall Council Capital projects budget. At Penzance a total of £528,500 has been allocated. 3 Benefits for Customers/Residents

3.1Match funding the Capital Program with Cornwall Harbours Board General Reserve enables these projects to be completed. This ensures we meet our statutory obligation to provide safe and open harbours for harbour users, local residents and visitors. 4 Relevant Previous Decisions

4.1None 5 Consultation and Engagement

5.1Cornwall Harbours Board

5.2Portreath Harbour User Association Information Classification: CONTROLLED

5.3St Ives Harbour Stakeholder Group

5.4Penzance Harbour Stakeholder Group

6 Financial Implications of the proposed course of action/decision

6.1This report seeks a financial contribution of £90,500 from the Cornwall Harbours General Reserve fund. The balance of this fund as at 31 st March 2026 was £913,919. 7 Legal/Governance Implications of the proposed course of action/decision

7.1None

8 Risk Implications of the proposed course of action/decision

8.1If Cornwall Harbours Board do not agree with supporting the capital program a reduction of project scope will be required.

9 Cornwall Development and Decision Wheel

9.1A Cornwall Development and Decision Wheel has not been completed and it is not appropriate for this report.

10 Options available

10.1Cornwall Harbours Board approve or not the transfer of £90,500 to the capital programme.

11 Supporting Information (Appendices)

11.1Appendix 1 Contribution to CC Capital Programme

11.2Appendix 2 Contribution to CC Capital Programme 12 Background Papers

12.1Our budget proposals

13 Approval and clearance Information Classification: CONTROLLED

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20260709: Harbours Board: Reserve request for contribution to capital projects: Appendix 1: PUBLICAppendix 1 pages Download
PDF
20260709: Harbours Board: Reserve request for contribution to capital projects: Appendix 2: PUBLICAppendix 1 pages Download
PDF
Reserve request for contribution to capital projectsReport 4 pages DownloadRead as text

More from Cornwall Cornwall Harbours Board

All decisions
MeetingDecisionOutcome
9 Jul 2026 Election of ChairmanRESOLVED that Councillor Rogers be elected Chairman. Councillor Rogers thereupon took the Chair and thanked Members f... Noted Open
9 Jul 2026 Election of Vice-ChairmanRESOLVED that Councillor Alvey be elected Vice-Chairman. To note: Drystan Jones was not present and left the room dur... Noted Open
9 Jul 2026 Minutes of the Meeting Held on 19 March 2026RESOLVED that the minutes of the meeting of the Cornwall Harbours Board held on 19 March 2026 were correctly recorded... Decided Open
9 Jul 2026 Cornwall Harbours Board Budget Outturn April 2025 - March 2026RESOLVED that the Board noted and approved the Harbour’s performance against budget and subsequent reserve movements. Noted Open
9 Jul 2026 Cornwall Harbours Board Budget Monitor April 2026 - May 2026RESOLVED that the Board noted and approved the Harbour’s performance against budget and subsequent reserve movements. Noted Open