Cornwall Harbours Board, Thursday 9 July 2026 at 2.00pm

Port of Truro proposal for Boatyard Services and Boat Storage at Lighterage Quay, Newham

Decided Committee 2 papers

AI summaryCornwall Harbours Board backs £0.374m Port of Truro boatyard plan at Lighterage Quay, including shed demolition and sale of Newham offices.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedWithout amendment, all parts approved
Money£0.374mFrom Port of Truro Reserve, plus building sales
What happens nextDemolish Shed 6, sell buildingsAwait Kernow Industrial Growth Fund decision
Who it affectsBoatyard and storage usersAt Lighterage Quay, Newham

What was decided

The Board supported the proposal without amendment.

A £0.374m commitment was approved from the Port of Truro Reserve, with the sale of the Newham Office and Maritime Workshop and demolition of Shed 6 also endorsed. Report 2.1

The application to the Kernow Industrial Growth Fund was endorsed, with priority to be given to the Port of Truro from the Truro Harbours General Reserve if that fund is not available.

Why

Commercial shipping at the port has declined, with only one movement in 2024 and none in 2025, reducing income. Report 1.2, 1.4, P6, 3.1

The proposal repurposes the quay for the leisure sector, which has around 1,500 moorings in the Port of Truro. Report 1.1, 1.5

The site is expected to generate a surplus that offsets the loss of regular commercial shipping income.

What happens next

Progress the application to the Kernow Industrial Growth Fund for £0.309m match funding. Report 1.11, 6.3

Demolish Shed 6 and sell the Newham Office and Maritime Workshop, with the Maritime Service relocating to Shed 7. Report 2.1, 6.2

Consult Cornwall Council under the terms of the MOU before disposing of the Newham office and Maritime Workshop. Report 7.1

The money

  • £0.374m Financial commitment from Port of Truro Reserve Report 6.1
  • £0.350m Anticipated proceeds from sale of Newham Office and Maritime Workshop Report 6.2
  • £1,033,000 Total project cost Report P23
  • £309,000 Project shortfall, pending Kernow Industrial Growth Fund grant Report P23, 6.3
  • £475,000 20t slew crane Report P23
  • £120,000 Shed 6 demolition Report P23
  • £100,000 Boat wash down facility Report P23
  • £100,000 Resurfacing and fencing at Newham Roundabout site Report P23

Options considered

  • Chosen: Support the proposal, with or without amendment, including financial commitment, building sale and grant application endorsement. Repurposes the quay for leisure use and supports port income Report P31
  • Rejected: Do not support the proposal Report P32

Implications

  • Financial: Project total £1,033,000 with £724,000 from Port of Truro sources, leaving a £309,000 shortfall pending grant funding. Report P23, 6.1, 6.3
  • Legal: Cornwall Harbours Board must consult Cornwall Council under the terms of the MOU before disposing of the Newham office and Maritime Workshop. Report 7.1
  • Risk: Without diversification, the Port may need alternative income to meet statutory obligations, possibly impacting fees at other harbours. Report 8.1
  • Risk: Lack of affordable port infrastructure could lead to more boat abandonment or failure to comply with environmental requirements.
  • Environment: Closed loop wash down facility captures marine growth and antifoul, minimising impact on the SSSI.

Who and where

  • Port of Truro commercial and leisure users Report 1.1, 1.2
  • Boating community needing storage and maintenance facilities Report 1.7
  • Truro Boat Services, Truro Boating Association, Truro Recycling, Fuel Specialist Services and Cornwall Council Maritime Service currently at the quay Report P4
  • Other harbours within the Cornwall Harbours portfolio if port income shortfalls affect the wider group Report 8.1

Timeline

  • Sept 2026: Fuel Specialist Services lease ends Report P4
  • 2024: One commercial shipping movement at Lighterage Quay Report P6
  • 2025: No commercial shipping movements at Lighterage Quay Report P6
  • Pre 2023: Port of Truro ring fenced HRO account period, final drawdown of £0.374m Report 6.1
  • Since 2023: Port of Truro surplus allocated to Cornwall Harbours General Reserve Report 6.1

Plain English for the jargon

  • HRO: Pre 2023 ring fenced account for Port of Truro funds
  • MOU: Memorandum of Understanding between Cornwall Harbours Board and Cornwall Council
  • SSSI: Site of Special Scientific Interest, an environmentally protected area
  • PoT: Port of Truro
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCHB40

Resolved

RESOLVED that: The Board supported the proposal, without amendment, included as follows; a) a financial commitment from the Port of Truro Reserve, to a value of £0.374m, b) sale of the Newham Office and Maritime Workshop, c) demolition of Shed 6 and d) endorsed the application to the Kernow Industrial Growth Fund e) in the event the Kernow Industrial Growth Fund was not available, priority is given to the Port of Truro from the Truro Harbours General Reserve.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Cornwall Harbours Board, 6 pages

Executive summary

1.1The Port of Truro is 2,500 acres in size and has a significant number of leisure moorings together with visitor’s pontoons and quays. The entire Fal estuary holds approximately 4,500 moorings, 1500 of which are located within the Port of Truro.

1.2Lighterage Quay has served as the commercial shipping hub of the Port of Truro since the 1960’s. Increasing ship sizes have restricted the use of the quay in recent years, this trend is common across many upper estuary ports.

1.3Lighterage Quay is an important asset to the port and wider area, it is home to:-

• Truro Boat Services • Truro Boating Association (TBOA) • Truro Recycling • Fuel Specialist Services *Until Sept 2026 • Cornwall Council Maritime Service

1.4Recent commercial shipping movements have been in support of National Grid with the handling of Transformers for Indian Queens Power Station, a trade that is expected to continue, and vessels to be scrapped at Truro Recycling.

Truro - Lighterage Quay Commercial Shipping 18 16 14 12 10 8 6 4 2 0 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Truro 11 11 12 13 10 7 9 10 6 3 5 9 5 11 10 5 10 17 13 13 10 8 4 0 1 0

1.5With changing commercial shipping demands at the Port, we have developed a proposal to repurpose the Quay’s activity and focus more on the buoyant leisure sector in the area. Already approved by Cornwall Harbours Board is the development of the roundabout site to provide open storage in a secure compound. This proposal will supplement and enhance usability of the storage area. Information Classification: CONTROLLED

1.6The proposal for Lighterage Quay will be the development of a Marine Services/Boatyard facility. The scope of proposed works are:-

• Shed 6 Demolition • Surfacing and fencing at Roundabout site (CHB approved) • Environmentally friendly Boat Wash Down • 20t Slew Crane • Hydraulic Boat Trailer & Tractor

1.7The footprint of Shed 6 would be used to provide seasonal boat storage for 30 boats. A further 10 spaces for short term use by boats requiring underwater works would be available to encourage other supporting businesses. 1.8 Boats would be moved within the yard via a hydraulic trailer and tractor. The Tractor could also be used to locate boats on road legal trailers to the upper storage facility at the roundabout site. 1.9 A slew crane would be installed adjacent to the quayside and able to lift boats of up to 20 tons. This crane is most suited the site requiring no works protruding over the side and minimising impact on the SSSI. 1.10 Adjacent to the crane would be a wash down facility to capture marine growth (including invasive species) and antifoul. The system would be closed loop preventing run off.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20260709: Harbours Board: Port of Truro proposal for Boatyard Services and Boat Storage at Lighterage Quay: Appendix: PUBLICAppendix 11 pages Download
PDF
Port of Truro proposal for Boatyard Services and Boat Storage at Lighterage Quay, NewhamReport 6 pages DownloadRead as text

More from Cornwall Cornwall Harbours Board

All decisions
MeetingDecisionOutcome
9 Jul 2026 Election of ChairmanRESOLVED that Councillor Rogers be elected Chairman. Councillor Rogers thereupon took the Chair and thanked Members f... Noted Open
9 Jul 2026 Election of Vice-ChairmanRESOLVED that Councillor Alvey be elected Vice-Chairman. To note: Drystan Jones was not present and left the room dur... Noted Open
9 Jul 2026 Minutes of the Meeting Held on 19 March 2026RESOLVED that the minutes of the meeting of the Cornwall Harbours Board held on 19 March 2026 were correctly recorded... Decided Open
9 Jul 2026 Cornwall Harbours Board Budget Outturn April 2025 - March 2026RESOLVED that the Board noted and approved the Harbour’s performance against budget and subsequent reserve movements. Noted Open
9 Jul 2026 Cornwall Harbours Board Budget Monitor April 2026 - May 2026RESOLVED that the Board noted and approved the Harbour’s performance against budget and subsequent reserve movements. Noted Open