Individual Decision Day, Wednesday 14 October 2026 at 10.00am

Individual Decision - Tamar Crossings - Supply of Replacement Ferry Main Chains for the Torpoint Ferries

Decided Committee 2 papers

AI summaryCornwall Council’s Individual Decision Day decided to award the Torpoint ferry chain contract to the highest scoring bidder. [D] The 10 year arrangement is intended to support reliable chain supply, with projected scrappage savings of ~£7k/year. [P14][P15]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCompetitive tender awards contract to highest scoring bidder. [D]
Money~£7k/year [P15]Projected cashable savings through the chain scrappage rebate. [P15]
What happens nextProcurement and contract management [P17]Commercial Services runs procurement; Tamar Crossings manages the contract. [P17]
Who it affectsThree Torpoint Ferries [P14]The contract secures chain supply and supports ferry service reliability. [P14][P15]

What was decided

Cornwall Council’s Individual Decision Day decided to award the contract for replacement ferry main chains to the highest scoring bidder. The award followed an open competitive tender. [D]

The contract has a 10 year term, made up of a 5 year initial term and a 5 year extension option. It covers custom made 655m studless open link chains for the three Torpoint Ferries. [P14] Report P14

Chains are to be replaced every three years under the maintenance schedule. Delivery must use DDP Incoterms, and used chains must be collected and disposed of, with any scrappage value returned to Tamar Crossings. [P14] Report P14

Why

The contract is intended to secure a reliable, long term supply of marine grade chains. It should support safety, operational continuity and ferry service reliability. [P14][P15] Report P14, P15

A multi year arrangement should reduce procurement time and resource. It is also intended to provide cost stability during volatile steel and freight markets. [P14] Report P14

The tender seeks best value and compliance with the Procurement Act 2023. It evaluates supplier capability, lead times, risk mitigation and innovation, with social value weighted at 15%. Research and consultation were not applicable because the work was business as usual. [P14][P22][P23] Report P14, P22, P23

What happens next

Cornwall Council Commercial Services will run the procurement. Tamar Crossings will manage the contract. [P17] Report P17

The supplier must deliver under DDP Incoterms to the Torpoint Ferry site. Chains must have flaked out presentation and preservation for tidal storage. [P14] Report P14

Used chains must be collected and disposed of, with scrappage value returned to Tamar Crossings. All chains must be Lloyd’s Register certified and accompanied by Certificates of Conformity. [P14][P15] Report P14, P15

The money

  • ~£7k/year Projected cashable savings through the scrappage rebate Report P15

Options considered

  • Chosen: Award the contract to the highest scoring bidder. The award followed an open competitive tender.
  • Chosen: Use a 10 year contract with a 5 year extension option. Long term supply and cost stability with less procurement resource. Report P14

Implications

  • Financial: Projected cashable savings are ~£7k/year from the scrappage rebate. The arrangement is intended to provide budget certainty and reduced procurement cycles. [P15] Report P15
  • Legal: The procurement must comply with the Procurement Act 2023. [P14] Report P14
  • Legal: All chains must be Lloyd’s Register certified and accompanied by Certificates of Conformity, as part of compliance with maritime legislation. [P14][P15] Report P14, P15
  • Equalities: The age impact assessment records no change. The mitigation response also records no change. [P24][P25][P26][P27] Report P24, P25, P26, P27
  • Climate: Sustainability considerations are to be embedded where applicable. The market engagement aim includes potential innovations in chain design or sustainability. [P14][P15] Report P14, P15
  • Risk: Multi year contracting is intended to reduce procurement time and resource. Overseas sourcing risks and freight cost volatility are to be addressed through contractual mechanisms. [P14][P15] Report P14, P15
  • Risk: Supplier capability, lead times, risk mitigation and innovation potential are tender evaluation considerations. [P14] Report P14
  • Other: The project is recorded against the council priorities of a resilient economy with good growth and jobs, and connected, safe and reliable roads and transport. The project has no impact on the Convention on the Rights of the Child. [P3][P4][P5][P6] Report P3, P4, P5, P6

Who and where

  • The three Torpoint Ferries Report P14
  • Torpoint ferry service Report P15
  • Tamar Crossings Report P14, P17
  • Cornwall Council Commercial Services Report P17

Timeline

  • 12/11/2025: Date recorded for the assessment. Report P11, P12
  • 10 year contract: Overall contract term. Report P14
  • 5 year initial term: The first contract period. Report P14
  • 5 year extension option: The optional extension period. Report P14
  • Every three years: Scheduled replacement of ferry chains. Report P14

Plain English for the jargon

  • DDP Incoterms: Delivery terms for supply to the Torpoint Ferry site. [P14]
  • Lloyd’s Register certification: Required for all chains, with Certificates of Conformity. [P14][P15]
  • Social value: A supplier evaluation consideration with a 15% weighting. [P14]
  • Contract extension option: A possible 5 year extension after the initial term. [P14]
  • Scrappage rebate: Projected savings of ~£7k/year, with value returned to Tamar Crossings. [P14][P15]
  • Procurement Act 2023: The legislation with which the tender must comply. [P14]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemIDD-L103

Resolved

Following an open competitive tender procedure, that the award of the Supply of Replacement Ferry Main Chains for the Torpoint Ferries Contract be awarded to the highest scoring bidder.
Word for word from the decision Cornwall published for this meeting. Source: democracy.cornwall.gov.uk

Follow this further

Built from Cornwall's papers

What the report saysPro

Report to Individual Decision Day

Information Classification: PUBLIC

Supply of Replacement Ferry Chains for the Three Torpoint Ferries Which of the six council priorities does your decision/project impact?

A resilient economy creating good growth and jobs

Connected‚ safe‚ reliable roads and transport

Does this project have an impact (positive or negative) on the Convention on the Rights of the Child

No

Directorate

150001 - Sustainable Growth & Place

Name of Officer(s) completing the Assessment

Robert Powell & Andy Trout

Date

12/11/2025

What are the aims‚ objectives‚ outcomes?

Aims of the Contract: To secure a reliable, long-term supply of marine-grade ferry chains for the three Torpoint Ferries. To ensure safety and operational continuity by replacing chains every three years in line with maintenance schedules. To reduce procurement time and resource through a multi-year contract arrangement. To achieve cost stability amid global steel and freight market volatility. To comply with maritime legislation, including Lloyd’s Register certification. Objectives: Procure a 10 - year contract (5-year initial term + 5-year extension option) for the supply of custom- made 655m studless open link chains. Ensure delivery under DDP Incoterms to the Torpoint Ferry site, including flaked-out presentation and preservation for tidal storage. Include collection and disposal of used chains, with scrappage value returned to Tamar Crossings. Conduct a competitive tender to secure best value and ensure compliance with the Procurement Act 2023. Evaluate supplier capability, lead times, risk mitigation, and innovation potential. Embed social value (15% weighting) and sustainability considerations where applicable. Expected Outcomes: Operational Assurance: Chains delivered on time and to specification, maintaining ferry service Information Classification: PUBLIC

reliability. Financial Predictability: Budget certainty with a projected spend of approx. over 5 years plus option for additional 5 years Efficiency Gains: Cashable savings via scrappage rebate (~£7k/year). Non-cashable benefits such as reduced procurement cycles and resource savings. Market Engagement: Identification of capable suppliers and potential innovations in chain design or sustainability. Risk Mitigation: Addressing overseas sourcing risks and freight cost volatility through contractual mechanisms. Compliance and Quality: All chains to be Lloyd’s Register certified and accompanied by Certificates of Conformity.

Who implements or delivers the above?

Cornwall Council Commercial Services will run the procurement and the contract will be managed by Tamar Crossings Information Classification: PUBLIC

Environmental and Social

Legend Long lasting or severe negative impact Short term or limited negative impact No or neutral impact Short term or limited positive impact Long lasting or extensive positive impact Information Classification: PUBLIC

Equality and Inclusion

Legend Long lasting or severe negative impact Short term or limited negative impact No or neutral impact Short term or limited positive impact Long lasting or extensive positive impact

Please give details of the research‚ consultation and any other evidence you have used to assess and inform the design‚ delivery‚ ownership and impact of your project.

Business As Usual (BAU) therefore not applicable

Age (particular age or range of ages) Please describe the likely differential impact on people with different ages‚ whether positive or negative.

no change

What mitigations will be put in place to minimise disproportionate adverse impacts on this group? Information Classification: PUBLIC

No change

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Individual Decision: Tamar Crossings: Supply of Replacement Ferry Main Chains for the Torpoint Ferries: Appendix 2 -L103Decisions 515 KB DownloadRead as text
PDF
Individual Decision: Tamar Crossings: Supply of Replacement Ferry Main Chains for the Torpoint FerriesDecisions 285 KB Download

At this meeting

Whole meeting

Who was there

0 of 9 attended
AP
Adam PaynterCommittee Member, expected
TD
Tim DwellyCommittee Member, expected
HF
Hilary FrankCommittee Member, expected
PL
Peter La BroyCommittee Member, expected
TM
Thalia MarringtonCommittee Member, expected
JM
Jim McKennaCommittee Member, expected
SP
Sarah PreeceCommittee Member, expected
LR
Loic RichCommittee Member, expected
DR
Dan RogersonCommittee Member, expected

On this subject at Cornwall

Search all
  1. Individual Decision - Tamar Crossings - Supply of Replacement Ferry Main Chains for the Torpoint FerriesThis decision
  2. Individual Decision - Direct Contract Award to Provider AApproved
  3. Individual Decision - National Jobs Guarantee – Cornwall and DevonAgreed
  4. Individual Decision - Local Transport Consolidated FundingDecided
  5. Individual Decision - Environment Service Licensing SchemesDecided
  6. Individual Decision - Visit Cornwall Asset LicensingApproved

More from Cornwall Individual Decision Day

All decisions
MeetingDecisionOutcome
14 Oct 2026 Individual Decision - Direct Contract Award to Provider AThat the direct contract award for Provider A set out in the report and exempt appendix be approved with a contract s... Approved Open
14 Oct 2026 Individual Decision - National Jobs Guarantee – Cornwall and DevonThat, subject to a positive funding decision from the Department for Work and Pensions (DWP), Cornwall Council accept... Agreed Open
14 Oct 2026 Individual Decision - Local Transport Consolidated FundingThat Cornwall’s refined Local Transport Delivery Plan, as set out in Appendix?1 to the report, be endorsed to enable ... Decided Open
2 Sep 2026 Individual Decision - Environment Service Licensing SchemesThat authority be delegated to the Service Director for Environment & Connectivity to procure suppliers for the follo... Decided Open