Resolved
The Audit Committee noted the outcome of the housing benefit subsidy certification work
Audit & Governance Committee noted this item on Thursday 21 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
The Audit Committee noted the outcome of the housing benefit subsidy certification work
Council name COTSWOLD DISTRICT COUNCIL
Name and date of AUDIT COMMITTEE – 21 JULY 2022 Committee
Report Number AGENDA ITEM 7
Subject KPMG LLP REPORTS – HOUSING BENEFIT SUBSIDY CERTIFICATION
Wards affected None
Accountable member Cllr Mike Evemy – Deputy Leader and Cabinet Member with responsibility for Finance Email: [email protected]
Accountable officer Mandy Fathers – Business Manager for Operations and Enabling Email: [email removed]
Summary/Purpose For the Audit Committee to note the outcome of the Housing Benefit Subsidy Grant Certification audit for 2020/2021
Annexes None
Recommendation(s) To note the outcome of the housing benefit subsidy certification work
Corporate priorities Delivering our services to the highest standards
Key Decision NO
Exempt NO
Consultees/ Leader and Deputy Leader, Chief Executive and Deputy Chief Executive, Consultation Monitoring Officer, Interim Head of Legal Services, Finance Business Partner, Group Manager, Director of Finance (Publica) 1. BACKGROUND
1.1In financial years prior to 2018/19, the annual housing benefit subsidy audit formed part of the procurement process for external audit services This procurement was carried out on behalf of local authorities by the Audit Commission. 1.2 Since the demise of the Audit Commission, the Council has used PSAA Ltd (a company established and owned by the Local Government Association) to procure its external audit services. 1.3 Due to changing legislation, the procurement for external audit services from 2018/19 onwards could not include the audit of the Housing Benefit Subsidy claim. Therefore, with effect from the 2018/19 financial year, the Council has been required to procure this specialist service directly and has procured the services of KPMG LLP to carry out the Housing Benefit subsidy claim audit for the 2018/19, 2019/20 and 2020/2021 financial years.
2. MAIN POINTS
2.1The Certification process aims to ensure that subsidy claims are fairly stated and provided assurance that the housing benefit scheme is being administered correctly. 2.2 During 2020/2021, the Housing Benefit Team administered approximately 21,003 changes in circumstances, and paid out £12,159,948 in Housing Benefit. The total subsidy claimed for by Cotswold District Council was £12,159,948. The team also identified £329,525 of overpaid Housing Benefit recoverable from claimants. In the year, claimants repaid a total of £110,415, including recovery of debts from previous years. 2.3 In the initial sample of Housing Benefit cases, KPMG LLP found 15 claims where subsidy had either been overstated or understated. This is broken down as follows:
Type of Number of claims Reason Subsidy Impact Subsidy Loss Claim incorrect (under/-over)
Non HRA 8 Incorrect assessment of £8,742.11 £0.00 Local Housing Allowance (LHA) rate -£8,742.11
Non HRA 1 Misclassification of Claimant -£2,249.90 £2,249.90 Error Overpayment
Non HRA 1 System migration issues £-55.84 £55.84 Rent 1 Claim misclassified as Rent £636.37 £0.00 Allowance Allowance when should be Non HRA
Rent 2 System migration issues -£1,011.03 £1,011.03 Allowance
Modified 2 Incorrect assessment of -£155.44 £155.44 Local War Widows pension Scheme
Total Subsidy Loss to Local Authority £3,472.21
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
KPMG LLP Reports: Housing Benefit Subsidy CertificationReport | 105 KB | DownloadRead as text |
Follow Audit & Governance Committee at Cotswold and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jan 2026 | Annual Capital StrategyResolved that the Committee: Noted the draft Capital Strategy (Annex A) for 2026/27 and provided feedback to the Cabi... | Noted | Open |
| 27 Jan 2026 | 2024/25 External Audit Report and Audit OpinionResolved that the Committee: Noted the report of the Senior Information Risk Owner (SIRO) on Information Governance f... | Noted | Open |
| 27 Jan 2026 | Matters exempt from publicationResolved that the Committee: Agreed to exclude the press and public for the remaining items of business in accordance... | Agreed | Open |
| 4 Dec 2025 | MinutesThe minutes of the Audit and Governance Committee on 30 September 2025 were APPROVED (2 votes for, 1 abstention.) | Approved | Open |
| 4 Dec 2025 | Audit and Governance Committee Work PlanThe Committee noted the Work Plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.