Resolved
Subject to the inclusion of the above amendments, the Committee agreed that the of the Audit Committee held on 21 July 2022 were an accurate record. Voting Record – For 4, Against 0, Abstentions 2, Absent 2
Audit & Governance Committee agreed this item on Thursday 29 September 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Subject to the inclusion of the above amendments, the Committee agreed that the of the Audit Committee held on 21 July 2022 were an accurate record. Voting Record – For 4, Against 0, Abstentions 2, Absent 2
Audit Committee 21/July2022
Minutes of a meeting of Audit Committee held on Thursday, 21 July 2022.
Councillors present: Nigel Robbins Nick Maunder Tony Berry Tom Stowe Patrick Coleman Ray Theodoulou
Officers present: Jenny Poole – Deputy Chief Executive & Chief Finance Officer Angela Claridge – Director of Governance Mandy Fathers – Business Manager, Environment, Welfare and Revenue Michelle Burge – Chief Accountant Lucy Cater – Assistant Director, SWAP Mike Butler – Risk and Compliance Officer Caleb Harris – Democratic Services Wayne Smith – Democratic Services
Observers: Councillor Stephen Andrews
144 Apologies
There were apologies provided from Councillor Gary Selwyn
145 Substitute Members
There were no substitute Members
146 Declarations of Interest
There were no declarations of interest from Members
There were no declarations of interest from Officers
147 Minutes
The Committee reviewed the minutes of the Audit Committee Meeting from 28 April 2022.
RESOLVED: The Committee agreed that the minutes were an accurate record of the previous meeting held on the 28 April 2022.
Voting Record - For 5, Against 0, Abstentions 0, Absent 2 Audit Committee 21/July2022
148 Public Questions
There were no public questions.
149 Member Questions
There were no Member questions
150 KPMG LLP Reports - Housing Benefit Subsidy Certification
The purpose of the report was for the Audit Committee to note the outcome of the Housing Benefit Subsidy Grant Certification audit for 2020/2021
The Committee noted that a request had been made for a year on year comparator and this had been provided at the end of the previous year. This was not available for the current year but would be included for the following year.
The Committee commented that a loss of 0.02% on Housing Benefit Subsidy was an exceptionally good achievement, especially considering the main IT system was replaced, and all data, was transferred to a new system during this period.
The Committee noted that of the £329,000 total Recoverable Overpaid Benefits, £110,000 had been recovered by the Council and the remainder would be recovered in the future (months and years) until all recoverable debt is repaid. Debts were only written off where payment recipients were declared bankrupt or abscond and could not be traced.
The Committee noted that the completion of the Housing Benefit Subsidy Grant Certification Audit 2020-21 had been delayed due to the work involved in transferring the data between two systems and Housing Benefit Subsidy Grant Certification Audit 2021-22 will be available in May 2023.
RESOLVED: The Audit Committee noted the outcome of the housing benefit subsidy certification work
151 Internal Audit Annual Opinion
The purpose of the report was to present a summary of the work undertaken by Internal Audit during 2021/22 and to give an overall opinion on levels of assurance resulting from this work. The Assistant Director, SWAP introduced the report and confirmed that due to the information contained in The Internal Audit Annual Opinion, it was deemed unnecessary to submit a separate quarterly monitoring report. In place of this, a condensed version of the usual report had been produced containing a summary of the work concluded since the last meeting of this Committee. The Committee noted that no significant risks had been identified over the previous year and the Council had been awarded a ‘High Reasonable Assurance” which was the same as the previous year.
The Committee noted that the different areas selected for audit investigation each year meant that direct year on year comparisons were not possible, however the report could still Audit Committee 21/July2022 provide reassurance that the overall audited performance and probity of the Council remained consistent.
The Council noted that five key Council areas will continue to be audited each year. These were: Business Continuity Continuous assurance Key financial audits Information governance and security Key front line services
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 86 KB | DownloadRead as text |
Follow Audit & Governance Committee at Cotswold and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jan 2026 | Annual Capital StrategyResolved that the Committee: Noted the draft Capital Strategy (Annex A) for 2026/27 and provided feedback to the Cabi... | Noted | Open |
| 27 Jan 2026 | 2024/25 External Audit Report and Audit OpinionResolved that the Committee: Noted the report of the Senior Information Risk Owner (SIRO) on Information Governance f... | Noted | Open |
| 27 Jan 2026 | Matters exempt from publicationResolved that the Committee: Agreed to exclude the press and public for the remaining items of business in accordance... | Agreed | Open |
| 4 Dec 2025 | MinutesThe minutes of the Audit and Governance Committee on 30 September 2025 were APPROVED (2 votes for, 1 abstention.) | Approved | Open |
| 4 Dec 2025 | Audit and Governance Committee Work PlanThe Committee noted the Work Plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.