RESOLVED that the Cabinet:- (1) Note the progress made in respect of the delivery of the Priority Schools Building Programme. (2) Note the update on progress of procurement for the President Kennedy School as part of the Midlands Privately Financed Batch of Schools. (3) Approve capital expenditure within the Education Capital Programme of:- (a) £95,000 in respect of Section 278 Highway Works and other off site works, as a result of the new school buildings; and (b) £60,000 in respect of costs associated with the required temporary decant of the Children’s Centre at Richard Lee School and the installation of new fibre optic works required at Richard Lee School Site. (4) Authorise officers to continue supporting schools and the Education Funding Agency in delivering the six capital grant funded schemes and the procurement of President Kennedy School. (5) Agree to receive further monitoring reports in July and November 2014 on the progress of construction and handover of the capital grant funded schools in the Coventry Priority Schools Building Programme and the procurement of President Kennedy School, to be replaced through a new form of Private Finance Initiative known as PF2.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
On 24 May 2012 the Department for Education (DfE) announced the outcome of applications submitted under the Government's Priority School Building Programme (PSBP) for the rebuild of schools in the worst condition. Coventry has secured funding for all seven schemes it submitted:
Primary Secondary Special Richard Lee President Kennedy Alice Stevens Wyken Croft Ernesford Grange St. Thomas More Catholic Whitmore Park
With the exception of President Kennedy, all schemes are to be funded through capital grant. President Kennedy will be delivered through a private finance initiative. The Coventry Programme will be delivered as a single batch and procured centrally by the Education Funding Agency (EFA) using the national Contractors' Framework. It is expected that the first Capital Grant Funded school (Whitmore Park Primary School) will be delivered by April 2014 with the President Kennedy School (Privately Financed) delivered by 2017
Recommendations
Cabinet is requested to approve the following recommendations: 1. Note the progress made in respect of the delivery of Coventry’s PSBP.
2. Note the update on progress of procurement for the President Kennedy School as part of the Midlands Privately Financed Batch of Schools;
3. Approve capital expenditure within the Education Capital Programme of:
• £95,000 in respect of S278 (Highways Works) and other off site works, as a result of the new school buildings; and • £60,000 in respect of costs associated with the required temporary decant of the Children’s Centre at Richard Lee School and the installation of new fibre optic works required at Richard Lee School Site.
4. Authorise officers to continue supporting schools and the Education Funding Agency (EFA) in delivering the six capital grant funded schemes and the procurement of the President Kennedy School
5. Agree to receive further monitoring reports in July and November 2014 on the progress of construction and handover of the capital grant funded schools in the Coventry PSBP Programme and the procurement of President Kennedy School. President Kennedy School is to be replaced through a new form of Private Finance Initiative known as PF2.
List of Appendices included: None
Background papers: None
Other useful documents: Education Capital: Priority Schools Building Programme: Cabinet Member (Education) 4th October 2011
Education Capital: Priority Schools Building Programme: Cabinet Member (Education) 14th August 2012
Education Capital: Priority Schools Building Programme: Cabinet 5th March 2013
Education Capital: Priority Schools Building Programme: Cabinet 9th July 2013
All of the above documents are available on the Council’s website: http://moderngov.coventry.gov.uk/mgListCommittees.aspx?bcr=1
Has it been or will it be considered by Scrutiny? No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body? No
Will this report go to Council? No Report Title: Education Capital - Priority Schools Building Programme
1. Context (or background)
1.1The Secretary of State announced on 19 July 2011, the launch of the Priority School Building Programme (PSBP) for the rebuilding of schools, originally a privately financed (PFI) national programme, with a value of capital investment estimated at £2billion nationally.
1.2In May 2012, the Council was successful in securing capital grant funding for the following six schemes:
Alice Stevens Ernesford Grange Secondary Richard Lee St. Thomas More Roman Catholic Whitmore Park Wyken Croft
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.