RESOLVED that the Cabinet:- (1) Delegate authority to the Executive Director, Resources to enter into a Project Delivery Agreement with the scheme Partners, which confirms funding and provides for any costs overruns to be met in equal shares between Coventry City Council and Warwickshire County Council. (2) Delegate authority to the S151 Officer to approve the submission of a joint ‘Full Approval’ Major Scheme Funding submission by Coventry City Council on behalf of the City ... view the full minutes text for item 147.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
The NUCKLE 1 project will provide platform extensions at Bedworth station, new stations at Coventry (Ricoh) Arena and Bermuda Park (Nuneaton) and an increased train frequency to two trains per hour. This report seeks the necessary approvals to enable the new stations to be built and operational by May 2015.
The delivery of the second train per hour is not possible in the same timescale because of a national shortage of diesel rolling stock. This is partly due to delays in electrification schemes and it is expected that suitable rolling stock will not be available until December 2017. There is also a significant amount of signalling and track work required to enable the extra train to run and tenders for this work came in at three times the budgeted cost. The reason for this is due to the large amount of signalling work across the network and the limited number of contractors capable of undertaking it.
It was therefore decided that the only practical option was to deliver the Scheme as two distinct packages: • Package 1: Delivery of the new stations at Ricoh Arena and Bermuda Park together with platform lengthening at Bedworth – to be opened by May 2015; • Package 2: Delivery of second train per hour, the new bay platform at Coventry Station and associated signalling and trackwork.
This 2 stage approach has been agreed with the DfT. The submission for ‘Full Approval’ to the DfT will be for package 1 only and will be for approximately half of the originally agreed funding. The balance will be held for package 2.
Following a successful tendering exercise, Buckingham Contracting Group has been selected as the preferred bidder for Package 1. This report seeks approval to enter into a binding Project Delivery Agreement with Warwickshire County Council and Centro (the funding partners) – this has to happen before we can make the ‘Full Approval’ submission to the Department for Transport (DfT) and then appoint Buckingham as the principal contractor to build the new stations and lengthen the platforms at Bedworth.
The City Council’s Partners, Warwickshire County Council and Centro, remain committed to the scheme, Centro confirmed their contribution to the scheme at a meeting of the Independent Transport Authority on 6th January 2014 and Warwickshire County Council on 13th February 2014.
Recommendations
The Cabinet is recommended to:
1. Delegate authority to Executive Director Resources to enter into a Project Delivery Agreement with the scheme Partners, which confirms funding and provides for any costs overruns to be met in equal shares between Coventry City Council and Warwickshire County Council,
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.