CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Coventry City Council
Audit and Procurement Committee, Monday 23 March 2015 at 3.30pm

Update on action arising from the Audit 2013/14 Findings Report

Agreed Finance 1 paper

Audit and Procurement Committee agreed this item on Monday 23 March 2015. Below is the council's own wording, with the papers it was decided on.

Item63

Resolved

Resolved that the Audit and Procurement Committee agree that the progress made and current position represent an appropriate response to the issues raised.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Audit and Procurement Committee

abc Public report

Audit and Procurement Committee 23rd March 2015

Name of Cabinet Member: Cabinet Member (Strategic Finance and Resources) – Councillor Gannon

Director Approving Submission of the report: Executive Director Resources

Ward(s) affected: All

Title: Report Back on the 2013/14 Audit Findings Report

Is this a key decision? No

Executive Summary: This report identifies the progress made and current position with regard to the issues raised in the 2012/13 Audit Findings Report considered by the Audit and Procurement Committee on 15th September 2014.

Recommendations: Audit and Procurement Committee is recommended to:

(1) Agree that the progress made and current position represent an appropriate response to the issues raised, and

(2) Identify any further action that the Committee requires be undertaken by officers.

List of Appendices included: None

Other useful background papers: None

Has it been or will it be considered by Scrutiny? No

Has it been or will it be considered by any other Council Committee, Advisory Panel or other body? No

Will this report go to Council? No Report Back on the 2013/14 Annual Findings Report

1. Context (or background)

1.1This report identifies the progress made and current position with regard to the issues raised in the 2013/14 Audit Findings Report brought to the Audit and Procurement Committee by the Council’s External Auditors Grant Thornton on 15th September 2014.

2. Options considered and recommended proposal

2.1Audit and Procurement Committee is recommended to agree that the progress made and current position reflected in the table below.

2.2An additional (or alternative) recommendation is for Committee to identify any further action that the Committee requires be undertaken by officers.

3. Action Plan Recommendations and Current Position

3.1The Action Plan recommendations and current response to it are included in the table below.

Rec Recommendation Current Position No.

1 The Council should put Arrangements are in hand to as part of arrangements in place to revalue 2014/15 close-down to ensure that classes of assets simultaneously assets within the same class are valued and to make the required PPE simultaneously and that the required disclosures in its accounts on a disclosures are made. This issue has class by class basis. been part of the on-going dialogue with Grant Thornton as part of preparation for the 2014/15 audit.

2 The Council needs to maintain its On-going maintenance of tight financial sound financial position by control continues to be a key focus for the continuing to : Council through: • keep tight financial control • continued budgetary control • keep the medium term monitoring financial plan up-to-date • Rolling medium term financial and plan for a range of planning forecasts reflecting a range scenarios of potential scenarios • ensure that identified savings from the ABC programme • Delivery of the abc Programme or are delivered adjustment for identified non-delivery • try to identify realistic ways of through the Budget process. making savings in the • Identification of new areas of saving medium term in respect of programmes as part of the recent children’s social care and Budget Report incorporating early intervention services. Kickstart, the Customer Journey, City Centre First, Doing Things Differently and a wide ranging Workforce Strategy. In response to the Ofsted Inspection report on its Children’s Services the Council is focussing on ensuring that the service is resourced to meet the immediate demands of the service across Coventry. Over the medium term, it will be necessary to ensure that social care and early intervention services are delivered in a way that strikes an appropriate balance between service need and the achievement of value for money.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on action arising from the Audit 2013/14 Findings ReportReport 54 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 16 attended
PB
Phil BaggottOfficer, expected
SB
Councillor Sucha BainsDeputy Chair, present
RB
Councillor Richard BrownGuest, present
MB
Mick BurnOfficer, expected
LC
Lisa CommaneOfficer, expected
CF
Christine FordeOfficer, expected
DG
Councillor David GalliersChair, present
LH
Councillor Lindsley HarvardCommittee Member, present
PJ
Paul JenningsOfficer, in attendance
SL
Shokat LalOfficer, in attendance
SM
Stephen ManganOfficer, in attendance
RS
Councillor Richard SandyCommittee Member, absent

All 16 on the meeting page

More from Coventry Audit and Procurement Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... Approved Open
22 Jun 2026 Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. Decided Open
22 Jun 2026 Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. Decided Open
16 Mar 2026 Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... Agreed Open
16 Mar 2026 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies