Coventry City Council
Audit and Procurement Committee, Monday 16 March 2026 at 2.30pm

2025/26 Third Quarter Financial Monitoring Report (to December 2025)

Noted Finance 1 paper

AI summaryAudit and Procurement Committee noted the third quarter financial monitoring report for 2025/26 and made no recommendations to Cabinet. The report forecasts a £1.6m revenue overspend and £174m of capital spending.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee reviewed report with no additions
Money£1.6m revenue overspend forecastCapital outturn forecast of £174m for 2025/26
What happens nextNo implementation timetableCabinet to consider report separately
Who it affectsCouncil budget and servicesAdult social care, property, waste, planning

What was decided

The committee noted the content of the third quarter financial monitoring report covering revenue, capital and treasury management activity to December 2025. Report P1, P7, P8

The committee confirmed it had no recommendations to forward to Cabinet.

The committee considered the proposals in the report as set out in the recommendations to it. Report P8

Why

The committee's role under the report is to consider monitoring proposals and forward any recommendations to Cabinet. Report P7, P8

The report is a monitoring update with no decision options, as officers set out in section 2.1. Report 2.1

The revenue overspend position has improved by £1.7m since the second quarter report, while pressures remain in adult social care, property, city services and regeneration. Report P2, P27

What happens next

There is no implementation timetable as this is a financial monitoring report. Report 4.1

Cabinet will be asked to approve the third quarter revenue monitoring position and the revised capital outturn of £174m, including £1.1m of new approved or technical changes and £11.1m of programme rescheduling. Report P5, P6, P47

The Director of Finance and Resources will continue to monitor the position and ensure projects are delivered within available resources. Report P3, P86

The money

  • £1.6m Net revenue forecast overspend for 2025/26 after management action Report P1, 1.2
  • £174m Capital spending outturn forecast for 2025/26 at third quarter Report P3, P43, P47
  • £7.0m Overspend at the same point in 2024/25 for comparison Report P1, 1.2
  • £296.7m Approved revenue budget for 2025/26 set by Cabinet on 25th February 2025 Report 1.1, P27
  • £1.1m Net increase in capital spending from approved or technical changes Report P6, P47, P138
  • £11.1m Net programme rescheduling of capital expenditure to future years Report P6, P47, P144
  • £184m Capital outturn forecast reported at second quarter Report P43, P46
  • £28.8m Net long-term borrowing requirement for the 2025/26 capital programme Report P55

Options considered

  • Chosen: No options. This is a budget monitoring report and as such there are no options. Report 2.1

Implications

  • Financial: Net revenue overspend forecast of £1.6m after management action, an improvement of £1.7m on the second quarter position. Report P1, P27, P81
  • Financial: Capital programme revised to £174m with £11.1m of expenditure rescheduled into future years, mainly on City Centre Cultural Gateway, vehicle replacements and Pearl Hyde school. Report P43, P47, P140
  • Financial: Treasury management shows an average short term investment return of 4.48% in the third quarter and a £2.6m net underspend on treasury management activities. Report P42, P62
  • Risk: The need to deliver a stable and balanced financial position is a key corporate risk and is reflected in the corporate risk register. Report P93
  • Staffing: Recruitment controls continue as part of management action to mitigate pressures and a centralised salaries underspend of £7.7m reflects unfilled vacancies. Report P85, P108
  • Equalities: No current policy changes are proposed, but the council's equality impact process will be used if service changes are needed later in the year. Report P97
  • Climate: No impact at this stage, although climate change and environmental impact of decisions are likely to feature more strongly in future reports. Report P99
  • Legal: The council has a statutory obligation to maintain a balanced budget and the monitoring process supports awareness of issues and actions. Report P89

Who and where

  • Adult social care service users facing continued demand, complexity and cost pressures in purchased care packages. Report P2, P29
  • Council taxpayers in Coventry, given the overall revenue and capital position. Report 6.1
  • Cabinet members who will be asked to approve the revenue monitoring position and revised capital outturn. Report P4, P5, P6
  • Council staff subject to ongoing recruitment controls and vacancy management across services. Report P85, P108

Timeline

  • 25th February 2025: Cabinet approved the revenue budget of £296.7m and capital programme of £171.6m Report 1.1
  • 31st December 2025: End of the third quarter reporting period for 2025/26 Report P1
  • 16th March 2026: Audit and Procurement Committee considered the third quarter financial monitoring report Report P17

Plain English for the jargon

  • PWLB: Public Works Loan Board, the main source of loan finance for local authority capital investment.
  • DSG: Dedicated Schools Grant, ringfenced funding for schools.
  • CWSDC: Coventry and Solihull Waste Disposal Company, a council owned waste disposal body.
  • One Coventry Plan: The council's strategic plan setting out its corporate priorities and objectives.
  • Prudential Indicators: Borrowing and investment limits set under the CIPFA Prudential Code to keep capital finance affordable and sustainable.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59

Resolved

RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recommendations for the Cabinet.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Audit and Procurement Committee

Executive summary

The purpose of this report is to advise Cabinet of the forecast outturn position for revenue and capital expenditure and the Council’s treasury management activity as at the end of December 2025. The net revenue forecast position after management action is for spend in 2025/26 of £1.6m over budget. Whilst not a wholly comparable position, at the same point in 2024/25, there was a projected overspend of £7.0m.

The Council continues to face budget pressures within Adults Social Care, Property Services & Development, City Services and Regeneration & Economic Development. These financial pressures are being caused by a combination of continued service demand, complexity & market conditions in social care, legacy inflation impacts, and income shortfalls due largely to the economic climate.

The Council’s capital spending is projected to be £174m and includes major schemes progressing across the city. The size of the programme and the nature of the projects within it continue to be fundamental to the Council’s role within the city. Although prevailing inflation rates look to be stabilising, legacy inflationary pressures continue to affect capital projects. We will continue to monitor this position and ensure projects are delivered within available resources. Recommendations:

The Cabinet is requested to:

1) Approve the Council’s third quarter revenue monitoring position.

2) Approve the revised forecast capital outturn position for the year of £174m incorporating: £1.1m net increase in spending relating to approved/technical changes and £11.1m of net programme rescheduling of expenditure to future years.

Audit and Procurement Committee is requested to:

1) Consider the proposals in the report and forward any recommendations to Cabinet.

List of Appendices included:

Appendix 1 - Revenue Position: Detailed Service breakdown of forecast outturn position Appendix 2 - Capital Programme: Analysis of Budget/Technical Changes Appendix 3 - Capital Programme: Analysis of Programme Acceleration/(Rescheduling) Appendix 4 - Prudential Indicators

Background papers

None

Other useful documents

None

Has it been or will it be considered by Scrutiny?

No

Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?

Yes - Audit and Procurement Committee, 16th March 2026

Will this report go to Council?

No Report title: 2025/26 Third Quarter Financial Monitoring Report (to December 2025)

1. Context (or background)

1.1Cabinet approved the City Council's revenue budget of £296.7m on 25th February 2025 and a Capital Programme of £171.6m. This is the third quarterly monitoring report for 2025/26. The purpose is to advise Cabinet of the forecast outturn position for revenue and capital expenditure, recommending any action required, and to also report on the Council’s treasury management activity.

1.2The current 2025/26 revenue forecast is for net expenditure to be £1.6m over budget (after management action). The reported forecast at the same point in 2024/25 was an overspend of £7.0m which reflected pressures relating primarily to social care activity and price. Capital spend in 2025/26 is projected to be £174m.

1.3Whilst it is not unusual to experience a forecast overspend at this point, it is essential that the Council maintains strict financial discipline to operate within approved budgets.

2. Options considered and recommended proposal.

2.1This is a budget monitoring report and as such there are no options.

Table1: Revenue Position - The revenue budgets and forecast positions are shown below analysed by service area.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Third Quarter Financial Monitoring Report (to December 2025)Report 761 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
MA
Councillor Maya AliCommittee Member, absent
JB
Councillor John BlundellCommittee Member, apologies, sent representative
RB
Councillor Richard BrownBy Invitation, expected
AH
Councillor Angela HopkinsCommittee Member, present
AJ
Councillor Abdul JobbarCommittee Member, present
RP
Councillor Ram Parkash Lakha OBEChair, present
JE
Councillor Julia Elizabeth LepoidevinReserve, present as substitute
PM
Councillor Peter MaleCommittee Member, present
BS
Councillor Bally SinghDeputy Chair, present

On this subject at Coventry

Search all
  1. 2025/26 Third Quarter Financial Monitoring Report (to December 2025)This decision
  2. 2025/26 Third Quarter Financial Monitoring Report (to December 2025)Approved
  3. 2024/25 Third Quarter Financial Monitoring Report (to December 2024)Noted
  4. 2024-25 Third Quarter Financial Monitoring Report (to December 2024)Approved
  5. 2023-24 Third Quarter Financial Monitoring Report (to December 2023)Noted
  6. 2023/24 Third Quarter Financial Monitoring Report (to December 2023)Approved

More from Coventry Audit and Procurement Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... Approved Open
22 Jun 2026 Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. Decided Open
22 Jun 2026 Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. Decided Open
16 Mar 2026 Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... Agreed Open
16 Mar 2026 Quarter Three Internal Audit Progress Report 2025/2026RESOLVED that the Audit and Procurement Committee: 1. Notes the performance as at quarter three against the Internal ... Decided Open