Verge Scheme Programme 2015/16

Approved Committee 1 paper

Public Services approved this item on Tuesday 16 June 2015. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED that the schemes to be undertaken in the 2015/16 verge programme detailed in Appendix A to the report be approved.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Public Services

Executive summary

On 3 March 2015 Cabinet approved the 2015/16 Transportation and Highway Maintenance Capital Programme. The basic principle of the programme was to carry out packages of complementary schemes, linking where possible works such as safety and traffic management schemes with maintenance schemes to maximise savings and efficiency.

The approval included an allocation of £125,000 for verge parking/protection schemes for which the list of schemes to be undertaken was to be subject to a separate report to the Cabinet Member (Public Services).

This report sets out the proposed programme and approval is sought from the Cabinet Member (Public Services) for its implementation in 2015/16.

Recommendations

The Cabinet Member is recommended to approve:-

The schemes to be undertaken in the 2015/16 Verge Programme as detailed in Appendix A.

List of Appendices included:

Appendix A - Proposed 2015/16 Verge Programme Appendix B - Update on 2014/15 Verge Programme Appendix C - Remaining locations, not yet programmed, with requests for verge parking/protection

Other useful background papers: Cabinet Report, copy available on moderngov.coventry.gov.uk. Date: 3 March 2015. Title: 2015/16 Transportation and Highway Maintenance Capital Programme

Cabinet Member (City Services) Report, copy available on moderngov.coventry.gov.uk. Date: 12 July 2011. Title: Revisions to Verge Parking Policy

Has it been or will it be considered by Scrutiny?

No

Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?

No

Will this report go to Council?

No

2 Report title: Report - Verge Scheme Programme 2015/16

1. Context (or background)

1.1At the Cabinet meeting on 3 March 2015 approval was granted for the 2015/16 Transportation and Highway Maintenance Capital Programme. Within the programme was an allocation of £125,000 for verge parking/protection schemes for which the list of schemes to be undertaken was to be subject to a separate report to the Cabinet Member (Public Services).

2. Options considered and recommended proposal

2.1At the Cabinet Member (City Services) meeting of 12 July 2011 the revisions to the Verge Parking Policy were approved. The revisions to the policy assist to overcome competing demands on whether to enable parking on the verge or to protect the verge, and determines the action to be undertaken, either enhanced parking facilities or legal/ physical enforcement.

2.2There are a number of verges on which measures have been requested, originating either from highways inspectors/maintenance issues, individual members of the public or petitions. The proposed 2015/16 Verge Programme, detailed in Appendix A, will utilise the approved budget of £125,000 and includes an allocation of £15,000 for ‘general' action for works at various small sites to assist in reducing on-going maintenance demands.

2.3An initial estimate is provided for each potential verge scheme (Appendix A). However, these are budget estimates only. The final cost may change as detailed designs are completed and items such as the location of utility services and whether they will be required to be diverted is confirmed.

2.4In order to allow for any slippage in the programme due to problems with buried statuary undertakers’ services, or localised objections or the final costs being lower than the estimate etc. an element of over programming has been included in the programme to accommodate this. Any schemes which are not completed will be carried forward for prioritisation in the next financial year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Verge Scheme Programme 2015/16Report 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

2 of 4 attended
AS
Councillor Abdul Salam KhanGuest, in attendance
RL
Councillor Rachel LancasterChair, present
ML
Councillor Marcus LapsaShadow Cabinet Member, present
MS
Moh ShafieOfficer, in attendance

On this subject at Coventry

Search all
  1. Verge Scheme Programme 2015/16This decision
  2. Verge Scheme Programme 2014/15Approved
  3. Verge Parking Schemes 2013-14Approved

More from Coventry Public Services

All decisions
MeetingDecisionOutcome
15 Mar 2016 Petition - Request for Traffic Lights at Junction of Longford Road and Oakmoor RoadRESOLVED that: (1) The concerns and requests of the petitioners be noted. (2) Approval be given that option 4 (southb... Noted Open
15 Mar 2016 Petitions Determined by Letter and Petitions Deferred Pending Further InvestigationsRESOLVED that: (1) Approval be given that, where appropriate, a summary of petitions received which are determined by... Approved Open
22 Feb 2016 Petition - The Management of Trees in Loudon AvenueRESOLVED that: (1) Approval be given to the reduction in the number of trees in the southern section of Loudon Avenue... Approved Open
22 Feb 2016 e-petition - Reopen Stoney Road to all TrafficIt was agreed that the bus gate would remain and monitoring would be undertaken. In July, 2013, following analysis of... Agreed Open
22 Feb 2016 Civil Parking Enforcement - Annual Report 2014 / 2015RESOLVED that the Civil Parking Enforcement Annual Report 2014/ 2015, as set out at the appendix, be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies