RESOLVED that the Cabinet: 1. Authorise a procurement process to set up a multi-supplier framework for 4 years for a Civil Engineering Support Framework to support the Council’s Direct Labour Organisation delivery. 2. Delegate authority to the Executive Director of Place to agree the award of contract(s) following a restricted tender process. 3. Authorise the City Council to enter into contract(s) with the successful suppliers for the 4 year period.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Coventry City Councils Highways Direct Labour Organisation (DLO) delivers circa £4.5m of work per year to the City’s roads and pavements funded from a number of sources including the Integrated Transport Block, the Highs Maintenance Capital Investment Programme and external grant funding. In order to deliver these works, a multi supplier Minor Civils Engineering Works Framework was established in 2013 for the engagement of the services of suitably experienced Contractors to undertake minor civil engineering maintenance works - typically minor highway maintenance/enhancement schemes. The Framework was set up to support the DLO in the delivery of highways services, to supplement the DLO's own in-house resources and act as a top-up, flexible resource where required through the peaks and troughs of the Highways maintenance season. This allows the DLO to deliver a flexible service without having to recruit additional direct staff.
The current Framework was set up in November 2013 and expected to run for a 4 year period. Due to the additional monies received by the Council from the European Regional Development Fund (ERDF), the framework has been much more heavily used than anticipated. As a result, spend through the framework has reached the value it was procured for before the end of the life of the framework. Continuing use of the current framework until its natural expiry in 2017, could put the Council at risk of procurement challenge.
It is proposed to undertake a restricted tender process to set up a replacement multi-supplier framework for a period of 4 years for a new Civil Engineering Support Framework for the value of £6m. Subject to approval of this report, a tender process will be commenced immediately to ensure that a new contract is in place for the 1st August 2016. Recommendations:
Cabinet is requested to:
1. Authorise a procurement process to set up a multi-supplier framework for 4 years for a Civil Engineering Support Framework to support the Councils DLO delivery. 2. Delegate authority to the Executive Director Place to agree the award of contract(s) following a Restricted tender process. 3. Authorise the City Council to enter into Contract(s) with the successful suppliers for the 4 year period.
List of Appendices included:
None
Other useful background papers:
Proc 2 (Gate 2 – Approval to Procure) – Civil Engineering Support Framework. Available by contacting Procurement and Commissioning team on 02476 833537
Has it been or will it be considered by Scrutiny? No
Has it been or will it be considered by any other Council Committee, Advisory Panel or there body? No
Will this report go to Council? No
2 Page 3 onwards Report title: Civil Engineering Support Framework
1. Context (or background)
1.1Coventry City Council’s Highways Direct Labour Organisation (DLO) delivers circa £4.5m of work per year. The Framework ensures the DLO can compliantly engage the services of suitably experienced Contractors to carry out the provision of highways and civil engineering minor construction works for transport related schemes, typically minor highways maintenance / enhancement scheme. The works will be packaged into four lots:
Lot 1 - The adjustment and replacement of carriageway ironwork in association with resurfacing; Lot 2 - Reactive and programmed pothole patching/repair maintenance; Lot 3 - Civil engineering and traffic safety schemes between the value of £0-250,000; Lot 4 - Civil engineering and traffic safety schemes above the value of £250,000;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.