RESOLVED that the Cabinet:- 1. Approve the expansion of Plas Dol -y- Moch , at a cost of £750,000, providing conditions are met as indicated within the report submitted. 2. Approve a capital investment of £500,000 to be funded via the Council’s capital programme and repaid by the service to the Council over 10 years with interest. 3. Note that the Friends of Dol -y- Moch , in collaboration with the Cabinet Member for Education and the Head of Centre, launch and support a community-led fundraising exercise and support bids for external grants to raise £250,000 towards the project by September 2017 in line with the Connecting Communities approach. 4. Subject to regular monitoring of the funds being raised by the Outdoor Education Committee, authorise officers to undertake works at Plas Dol -y- Moch and to include tis as part of the Council’s capital programme on the assumption that the £250,000 gap can be raised by September 2017. 5. Approve in principle that the Council will be guarantor for any external grant funding up to a combined total of £250,000 and delegate responsibility to the Executive Director of Resources in consultation with the relevant Cabinet Member in relation to details of any such guarantor agreement.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Name of Cabinet Members: Cabinet Member for Education – Councillor Kershaw
Directors Approving Submission of the report: Executive Director of People Director of Education, Libraries and Adult Learning
Ward(s) affected: None
Title: Plas Dol-y-Moch: Investing in Outdoor Education for Coventry’s Children and Young People
Is this a key decision? No
Executive Summary: Plas Dol-y-Moch is Coventry’s outdoor education centre. For the past 50 years it has provided Coventry children with memorable experiences and effective learning in a natural outdoor setting. As its 50th anniversary approaches, this report sets out the strategic case for investing £750,000 into improving the facilities at Plas Dol–y–Moch to meet the needs of the city’s growing and changing pupil population. It pledges the Council to lend two thirds of this (£500,000) and outlines a community-led fundraising drive co-ordinated by the Friends of Dol-y-Moch, in partnership with the Cabinet Member for Education and the Head of Centre to raise the remainder (£250,000) in the next year. This will help secure the centre for the next generation and is in line with the Council’s Connecting Communities approach.
Recommendations: Cabinet is requested to:
1. Approve the expansion of Plas Dol-y-Moch, at a cost of £750,000, providing conditions are met as outlined below.
2. Approve a capital investment of £500,000 to be funded via the Council’s capital programme and repaid by the service to the Council over 10 years with interest.
3. Note that the Friends of Dol-y-Moch, in collaboration with the Cabinet Member for Education and Head of Centre, launch and support a community-led fundraising exercise and support bids for external grants to raise £250,000 towards the project by September 2017 in line with the Connecting Communities approach.
4. Subject to regular monitoring of the funds being raised by the Outdoor Education Committee, authorise officers to undertake works at Plas Dol-y-Moch and to include this as part of the Council’s capital programme on the assumption that the £250,000 gap can be raised by September 2017.
5. Approve in principle that the Council will be guarantor for any external grant funding received up to a combined total of £250,000 and delegate responsibility to the Executive Director of Resources in consultation with the relevant Cabinet Member in relation to details of any such guarantor agreement.
List of Appendices included: Appendix 1: Financial projections Appendix 2: Evidence base for the expansion of Plas Dol-y-Moch Appendix 3: Fundraising and programme of activities
Background papers: None
Other useful documents: Developing social enterprises, mutuals and other forms of public service delivery including Key principles for Council spin-outs (Cabinet, 2 December 2014)
Strategic direction for the future of outdoor education provision / Plas Dol-y-Moch, Briefing note to Cabinet Member for Education, 2 March 2015
Has it been or will it be considered by Scrutiny? No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body? No
Will this report go to Council? No
-2- Report title: Plas Dol-y-Moch: investing in outdoor education for Coventry’s children and young people
1 Background / context
1.1Plas Dol-y-Moch (PDyM) is Coventry’s outdoor education centre. Since 1966, it has provided Coventry children with memorable experiences and effective learning in a natural outdoor setting. It is part of Coventry’s wider portfolio of outdoor education: People Directorate Place Directorate
Outdoor Education Service (traded service funded by schools through a Coombe Education Service (countryside, heritage, environmental studies and education centre) at Coombe Country Park Educational visits guidance and advice Plas Dol-y-Moch (through a Coventry-based advisor)
Duke of Edinburgh Award operating authority (Award Officer in Youth Services with responsibility for all DoE programmes in Coventry)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.