Resolved
RESOLVED that Audit and Procurement Committee recommends that the Cabinet Member for Policy and Leadership approves the revised (attached as Appendix One to the report).
Audit and Procurement Committee approved this item on Monday 18 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Audit and Procurement Committee recommends that the Cabinet Member for Policy and Leadership approves the revised (attached as Appendix One to the report).
The Fraud and Corruption Strategy explains the Council’s strategic response to tackling fraud and corruption and sets out the Counter Fraud Framework, which comprises the various elements the Council uses to fight fraud and implement the Fraud and Corruption Strategy. The purpose of the report is for the Audit and Procurement Committee to consider the Fraud and Corruption Strategy, as set out in Appendix One and to recommend to the Cabinet Member (Policy and Leadership) that the Strategy be approved.
Audit and Procurement Committee is recommended to consider the revised Fraud and Corruption Strategy (attached at Appendix One) and to recommend to the Cabinet Member (Policy and Leadership) that the Strategy be approved.
The Cabinet Member (Policy and Leadership) is recommended to:
1. Consider the comments of the Audit Committee.
2. Approve the Fraud and Corruption Strategy (attached at Appendix One).
1 List of Appendices included:
Appendix One – Fraud and Corruption Strategy 2018
None
Other useful documents:
Fraud and Corruption Strategy 2012 http://internaldemocraticservices.coventry.gov.uk/ieListDocuments.aspx?CId=208&MID=9515
Has it or will it be considered by scrutiny?
No
Has it, or will it be considered by any other council committee, advisory panel or other body?
Yes – Cabinet Member for Policy and Leadership 26th July 2018
Will this report go to Council?
No
2 Report title: Fraud and Corruption Strategy
1. Context (or background)
1.1Local authorities face a significant fraud challenge with annual losses to local government estimated at £2.1 billion a year. Fraud and corruption is a drain on the public purse and takes resources away from the delivery of front line services. In addition to the scale of losses, there are further challenges arising from changes in the wider public sector landscape including budget reductions and government policy changes, which means that local authorities need to keep their arrangements for responding to the risk of fraud under review and up to date to ensure they are continuing to act effectively.
1.2The risk of fraud is acknowledged by central government through publication of “Fighting Fraud Locally” which is a counter fraud and corruption strategy for local government. This emphasises the need for local authorities to “ensure they are active in looking for and identifying fraud and embedding a counter fraud culture at the heart of their organisation”.
1.3In light of this new national counter fraud landscape, the Council’s Fraud and Corruption Strategy has been reviewed and updated to ensure our arrangements provide a rigorous framework to respond to these challenges. Given the Audit and Procurement Committee’s responsibility, as reflected in its terms of reference “to monitor Council policies on whistleblowing and the anti-fraud and corruption strategy”, this report allows the Audit and Procurement Committee to comment on the content and scope of the revised Strategy, prior to it being considered for approval by the Cabinet Member (Policy and Leadership).
2. Options considered and recommended proposal
2.1The proposed Fraud and Corruption Strategy is attached at Appendix One. The Strategy was last updated in 2012. The process of reviewing the Strategy has included the following actions / considerations:
Since 2012, updated guidance on this area has been published, including central government’s “Fighting Fraud Locally” strategy and the CIPFA Code of Practice on Managing the Risk of Fraud and Corruption, both of which have been considered in developing the new Strategy.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Fraud and Corruption StrategyReport | 116 KB | DownloadRead as text |
Follow Audit and Procurement Committee at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... | Approved | Open |
| 22 Jun 2026 | Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. | Decided | Open |
| 22 Jun 2026 | Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. | Decided | Open |
| 16 Mar 2026 | Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... | Agreed | Open |
| 16 Mar 2026 | 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.