RESOLVED that, the Cabinet Member for Housing and Communities: 1. Notes the current position in advancing a CIL charge for Coventry as an update and progress report as of March 2019; and 2. Endorses the continued delivery of CIL at the earliest opportunity.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
The ability for Local Authorities to charge a Community Infrastructure Levy (or CIL for short) came into force nationally in April 2010. It enables the Council to raise funds from developers undertaking new building projects in the city. The money can be used to fund a wide range of infrastructure that is needed as a result of development across the city. Examples can include new or safer road schemes, flood defences, schools, hospitals and other health and social care facilities, park improvements, green spaces and leisure centres.
The levy creates a financial charging system with the majority of building projects potentially qualifying to contribute towards additional infrastructure that is needed to support wider planned development across the city. The Levy also has far greater certainty in that it provides the basis for a charge in a manner that the planning obligations system alone could not easily achieve, enabling, for example, the mitigation of cumulative impacts from development and allowing more flexible use of CIL receipts in terms of where and how they are spent. The Council is currently developing a CIL following on from the adoption of, and to support its Local Plan. Linked to and alongside the ongoing preparatory work on CIL, the Council is also in the process of developing a separate, but linked planning tool, namely a Supplementary Planning Document (SPD) relating to s.106 developer contributions. The Council has also gathered information from other areas where Local Authorities have already established a CIL charging, including benchmarking revenues from purpose built student accommodation developments.
Recommendations
The Cabinet Member is requested to: 1. note the current position in advancing a CIL charge for Coventry as an update and progress report as of March 2019; and 2. endorse the continued delivery of CIL at the earliest opportunity.
List of Appendices included: None.
Background papers: None.
Other useful documents: None.
Has it been or will it be considered by Scrutiny? No.
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body? No
Will this report go to Council? No.
2 Report title: Community Infrastructure Levy (CIL) – update position 2019.
1. Context (or background)
1.1The first stage in establishing a CIL is something called a Preliminary Draft Charging Schedule (or PDCS for short). Existing CIL regulations set out a prescribed process which all Councils must follow to get a CIL charge in place. The key requirements for being successful in establishing a CIL charge are firstly, to have recent evidence on local development and infrastructure markets and secondly, to strike an appropriate balance between the level of CIL charge and its potential effects on economic viability. Understanding the relationship between CIL and section 106 legal obligations is also important.
1.2Consultants were commissioned to undertake a viability assessment after the adoption of the Local Plan, and this was developed during 2018 on the premise that CIL charging in Coventry could support the delivery of infrastructure by placing a financial charge (or Levy) on certain new developments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.