Resolved
RESOLVED that, the Audit and Procurement Committee note the progress made against the actions planned in 2019/20 to address the governance issues highlighted in the Annual Governance Statement for 2018/19.
Audit and Procurement Committee noted this item on Monday 27 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that, the Audit and Procurement Committee note the progress made against the actions planned in 2019/20 to address the governance issues highlighted in the Annual Governance Statement for 2018/19.
The purpose of this report is to provide the Audit and Procurement Committee with an update on the actions planned in 2019-20 to address the governance issues highlighted in the Annual Governance Statement for 2018-19.
The Audit and Procurement Committee is recommended to note and consider the progress made against the actions planned in 2019-20 to address the governance issues highlighted in the Annual Governance Statement for 2018-19.
1 List of Appendices included:
Appendix One - Update on the 2018-19 Annual Governance Statement action plan
None
Other useful documents:
Annual Governance Statement 2018-19 https://edemocracy.coventry.gov.uk/ieListDocuments.aspx?CId=553&MId=12088&Ver=4
Has it or will it be considered by scrutiny?
No other scrutiny consideration other than the Audit and Procurement Committee
Has it, or will it be considered by any other council committee, advisory panel or other body?
No
Will this report go to Council?
No
2 Report title: Annual Governance Statement 2018-19 – Update on planned actions
1. Context (or background)
1.1Coventry City Council is responsible for ensuring that its business is conducted in accordance with the law and proper standards, and that public money is safeguarded and properly accounted for, and used economically, efficiently and effectively. In discharging this responsibility, the City Council is responsible for putting in place proper arrangements for the governance of its affairs and facilitating the effective exercise of its functions, including arrangements for the management of risk.
1.2To demonstrate such arrangements, the City Council had adopted a Code of Corporate Governance, which is consistent with the principles reflected in the CIPFA / SOLACE framework and guidance ‘Delivering Good Governance in Local Government’ (2016).
1.3The Annual Governance Statement (‘AGS’) explains how Coventry City Council has complied with the Code and in doing so, reflects the requirements of the Accounts and Audit Regulations 2015, which requires all relevant bodies to prepare an Annual Governance Statement. The AGS also details key governance / control issues identified through the assessment that the Council faces in the coming year.
1.4The Audit and Procurement Committee approved the AGS for 2018-19 at its meeting on the 24th June 2019. As part of this, the Committee requested that they receive an update report during the year on the actions planned to be undertaken by the Council in 2019-20 to address the governance issues highlighted.
2. Options considered and recommended proposal
2.1Disclosures made in the 2018-19 Annual Governance Statement
Part of the function of the AGS is to highlight areas that the Council considers require internal control / governance improvements. The 2018-19 statement set out the following issues (disclosures) which were identified in the development of the AGS:
Seeking sustainable improvement in Children’s Services Ensuring delivery of the Council’s vision and corporate objectives, in line with the Medium-Term Financial Strategy. Raising Educational standards Implementation of the Information Management Strategy Delivery of the Workforce Strategy Delivery of the ICT Strategy Management of increasing demand in relation to homelessness and the associated costs of housing families in temporary accommodation. Producing a corporate data access standard Governance over relationships with partners and outside bodies Governance over the programme of capital projects
2.2Improvement actions
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Governance Statement 2018-19: Update on Planned ActionsReport | 158 KB | DownloadRead as text |
Follow Audit and Procurement Committee at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... | Approved | Open |
| 22 Jun 2026 | Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. | Decided | Open |
| 22 Jun 2026 | Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. | Decided | Open |
| 16 Mar 2026 | Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... | Agreed | Open |
| 16 Mar 2026 | 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.