RESOLVED that the Cabinet: 1) Authorises a procurement process to establish a set of multi-supplier term contracts for an original term of two (2) years with the option to extend by a further two (2) twelve (12) month periods for the provision of property maintenance, repairs and improvements i.e. a maximum contract length of 4 years in total. 2) Delegates authority to Director for Property Services and Development, in consultation with the Cabinet Member for Jobs and Regeneration, to agree the award of the contract(s) following the restricted tender process in conjunction with Procurement. 3) Authorises the Council to enter in to Contract(s) with the successful suppliers for up to four (4) years.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Coventry City Council’s Compliance and Surveying Team provide a property management service for Council buildings and schools as well as a number of external clients. The works mainly include repairs and maintenance with some property improvements and are undertaken on either a planned or reactive basis depending on the work required. The provision of these works has been via Term Contracts for a number of years.
As the existing term contracts are coming to an end, in order to deliver these works it is proposed to undertake a restricted tender process to set up a multi-lot, multi-supplier term contract for a period of 4 years. A term contract is an agreement whereby there is no guarantee of work. However, should there be a requirement for such work the term contractor will be approached.
The first placed supplier on each lot will be offered the work. The others will be approached if the first place is unable to undertake the work. Bringing all term contracts that are expiring at the same time under one umbrella, reduces the time taken to undertake the necessary procurement process for both the Council and relevant suppliers who may have interest in more than 1 of the contracts. Recommendations:
Cabinet is requested to:
1) Authorise a procurement process to establish a set of multi-supplier term contracts for an original term of two (2) years with the option to extend by a further two (2) twelve (12) month periods for the provision of property maintenance, repairs and improvements ie a maximum contract length of 4 years in total;
2) Delegate authority to Director for Property Services and Development in consultation with the Cabinet Member for Jobs & Regeneration, to agree the award of the contract(s) following the Restricted tender process in conjunction with Procurement; and
3) Authorise the Council to enter in to Contract(s) with the successful suppliers for up to four (4) years.
List of Appendices included:
None
Background papers
None
Other useful documents
Procurement Outline Document (POD) PROC2 – Permission to Procure – Property Asset Management (Term Contracts) Framework. This document is available by contacting the Procurement and Commissioning team on 02476 975 232 (option2) or via [email protected].
Has it been or will it be considered by Scrutiny?
No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
No
Will this report go to Council?
No Report title: Procurement for Property Asset Management (Term Contracts) Framework
1. Context (or background)
1.1Coventry City Council’s Compliance and Surveying Team delivers a property maintenance repairs and improvement programme covering Council buildings, schools and other external buildings with a predicted spend of circa £8.45m per annum. This is carried out either via our own Repairs and Maintenance workforce or through the use of term contracts.
1.2Capacity limits the ability of our own workforce to carry out all the works required. Their function is primarily reactive repairs. The school customer base requires much of the work to be carried out in school holidays which term contractors are able to undertake. This work also attracts fee income.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.