St Mary's Guildhall Capital Project

Approved Committee 6 papers

Jobs and Regeneration approved this item on Wednesday 3 June 2020. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED that the Cabinet Member for Jobs and Regeneration:- (1) Approves the detail of the preferred capital scheme for the refurbishment /modernisation of St \Mary’s Guildhall set out in the £5.6m preferred option (2) Delegates to the Director of Business, Investment and Culture, following consultation with the Cabinet Member for Jobs and Regeneration and the Cabinet Member for Housing and Communities, authority to approve and submit a Stage Two funding application to the National Lottery Heritage Fund for £1.7m to support the project outlined in the report (3) Delegates to the Director of Business Investment and Culture, following consultation with the Director of Finance, authority to obtain the necessary consents, procurement, contractor appointment and contract extensions for the professional design team. (4) Delegates to the Director of Business, Investment and Culture, following consultation with the Director of Law and Governance, authority to enter into the necessary legal agreements to give effect ... view the full minutes text for item 4.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Jobs and Regeneration

Executive summary

St Mary’s Guildhall is a Grade One listed fourteenth century guildhall, located in the city’s historic Cathedral Quarter. First built in the 1340s for the merchant guild of St Mary, it was enlarged between 1394 and 1414 and extensively embellished at the end of the fifteenth century. Soon after it was built, it was also adopted as the headquarters for the Mayor and city leaders, and the corporation of Coventry remained here until the early twentieth century, when Coventry's present Council House was built. The building still occupies a central role in the civic calendar and is home to one of the rarest and most important tapestries in the country. Whilst the guildhall is one of the city’s greatest cultural assets, it is currently under-utilised in terms of public heritage value and does not reach its full potential as a visitor attraction and has not been able to cover its operating costs.

The Council has successfully raised £2.2m funding from the Department for Culture, Media and Sport to support the refurbishment of St. Mary’s Guildhall, and has achieved a Stage One award of £78,000 from the National Lottery Heritage Fund which will enable officers to develop a Stage Two application for revenue and capital funding of £1.7m. In February 2020, Cabinet approved up to £3 million capital support for the project to be funded through prudential borrowing to bridge any remaining funding gap on the basis a financial return would be achieved on this investment. This report seeks approval to submit a Stage Two National Lottery Heritage Fund application, the preferred scheme for capital works, arrangements for the closure of St. Mary’s Guildhall to enable work to take place to deliver the associated refurbishment and the delegations necessary to implement these decisions. Recommendations:

The Cabinet Member for Jobs and regeneration is requested to:

1. Approve the detail of the preferred capital scheme for the refurbishment / modernisation of St Mary’s Guildhall set out in £5.6m preferred option. 2. Delegate to the Director of Business Investment & Culture following consultation with the Cabinet Member for Jobs and Regeneration and the Cabinet Member for Housing and Communities to approve a Stage Two funding application to National Lottery Heritage Fund for £1.7m to support the project outlined in this report. 3. Delegate to the Director for Business Investment & Culture, following consultation with the Director of Finance to obtain the necessary consents, procurement, contractor appointment and contract extensions for the professional design team. 4. Delegate to the Director for Business, Investment and Culture following consultation with the Director of Law and Governance to enter into the necessary legal agreements to give effect to the above recommendations.

List of Appendices included:

Appendix One – Equalities Impact Assessment Appendix Two – Floor Plans Appendix Three – Significance of Medieval Kitchen

Background papers

None

Other useful documents

• UK City of Culture 2021 Capital Programme – Approval to receive and be accountable body for additional capital funding for the Cultural Capital Investment Fund - Cabinet Report (August 2018) • Business, Economy and Enterprise Scrutiny Board (3) – St Mary’s Guildhall (November 2018) • Budget Report 2020/21 – Cabinet Report (February 2020) • Business, Economy and Enterprise Scrutiny Board (3) – St Mary’s Guildhall Transformation Project (March 2020)

Has it been or will it be considered by Scrutiny?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EIAAppendix 1 284 KB Download
PDF
1917-200F Proposed Ground Floor PlanAppendix 2 254 KB Download
PDF
1917-201B Proposed First Floor PlanAppendix 2 206 KB Download
PDF
1917-202B Proposed Second Floor PlanAppendix 2 161 KB Download
PDF
Appendix 3Appendix 3 1.8 MB Download
PDF
St Mary's Guildhall Capital ProjectReport 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 4 attended
RB
Councillor Roger BaileyBy Invitation, in attendance
PM
Councillor Peter MaleShadow Cabinet Member, present
JO
Councillor Jim O'BoyleCabinet Member, present
DS
Councillor David Stuart WelshDeputy Cabinet Member, present

On this subject at Coventry

Search all
  1. St Mary's Guildhall Capital ProjectThis decision
  2. Acceptance of Grant Funding from the National Lottery Heritage Fund towards the project to transform St. Marys GuildhallDecided
  3. Application LB/2020/0909 - St Mary's Guildhall, Bayley LaneDecided

More from Coventry Jobs and Regeneration

All decisions
MeetingDecisionOutcome
14 Jul 2020 Whitley Depot Rebuild - Additional Capital AllocationRESOLVED that the Cabinet Member for Jobs and Regeneration approves the allocation of an additional £0.48m of capital... Approved Open
3 Jun 2020 Exclusion of the Press and PublicRESOLVED that approval be given to exclude the press and public under Section 100(A) 4 of the Local Government Act 19... Approved Open
3 Jun 2020 Land Disposal at Parkside, Paradise Street and Re-provision of Newgate Court Industrial EstateRESOLVED that the Cabinet Member for Jobs and Regeneration:- 1. Declares the part of the land at Parkside, Paradise S... Approved Open
4 Mar 2020 Exclusion of the Press and PublicRESOLVED that approval be given to exclude the press and public under Section 100(A) 4 of the Local Government Act 19... Approved Open
4 Mar 2020 8-12 Ironmonger Row, 17-21 Cross Cheaping Coventry - 250 Year LeaseRESOLVED that the Cabinet Member for Jobs and Regeneration:- 1) Grants a new 250 year lease, at the sum identified in... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies