RESOLVED that the Cabinet Member for Jobs and Regeneration:- (1) Approves the detail of the preferred capital scheme for the refurbishment /modernisation of St \Mary’s Guildhall set out in the £5.6m preferred option (2) Delegates to the Director of Business, Investment and Culture, following consultation with the Cabinet Member for Jobs and Regeneration and the Cabinet Member for Housing and Communities, authority to approve and submit a Stage Two funding application to the National Lottery Heritage Fund for £1.7m to support the project outlined in the report (3) Delegates to the Director of Business Investment and Culture, following consultation with the Director of Finance, authority to obtain the necessary consents, procurement, contractor appointment and contract extensions for the professional design team. (4) Delegates to the Director of Business, Investment and Culture, following consultation with the Director of Law and Governance, authority to enter into the necessary legal agreements to give effect ... view the full minutes text for item 4.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
St Mary’s Guildhall is a Grade One listed fourteenth century guildhall, located in the city’s historic Cathedral Quarter. First built in the 1340s for the merchant guild of St Mary, it was enlarged between 1394 and 1414 and extensively embellished at the end of the fifteenth century. Soon after it was built, it was also adopted as the headquarters for the Mayor and city leaders, and the corporation of Coventry remained here until the early twentieth century, when Coventry's present Council House was built. The building still occupies a central role in the civic calendar and is home to one of the rarest and most important tapestries in the country. Whilst the guildhall is one of the city’s greatest cultural assets, it is currently under-utilised in terms of public heritage value and does not reach its full potential as a visitor attraction and has not been able to cover its operating costs.
The Council has successfully raised £2.2m funding from the Department for Culture, Media and Sport to support the refurbishment of St. Mary’s Guildhall, and has achieved a Stage One award of £78,000 from the National Lottery Heritage Fund which will enable officers to develop a Stage Two application for revenue and capital funding of £1.7m. In February 2020, Cabinet approved up to £3 million capital support for the project to be funded through prudential borrowing to bridge any remaining funding gap on the basis a financial return would be achieved on this investment. This report seeks approval to submit a Stage Two National Lottery Heritage Fund application, the preferred scheme for capital works, arrangements for the closure of St. Mary’s Guildhall to enable work to take place to deliver the associated refurbishment and the delegations necessary to implement these decisions. Recommendations:
The Cabinet Member for Jobs and regeneration is requested to:
1. Approve the detail of the preferred capital scheme for the refurbishment / modernisation of St Mary’s Guildhall set out in £5.6m preferred option. 2. Delegate to the Director of Business Investment & Culture following consultation with the Cabinet Member for Jobs and Regeneration and the Cabinet Member for Housing and Communities to approve a Stage Two funding application to National Lottery Heritage Fund for £1.7m to support the project outlined in this report. 3. Delegate to the Director for Business Investment & Culture, following consultation with the Director of Finance to obtain the necessary consents, procurement, contractor appointment and contract extensions for the professional design team. 4. Delegate to the Director for Business, Investment and Culture following consultation with the Director of Law and Governance to enter into the necessary legal agreements to give effect to the above recommendations.
List of Appendices included:
Appendix One – Equalities Impact Assessment Appendix Two – Floor Plans Appendix Three – Significance of Medieval Kitchen
Background papers
None
Other useful documents
• UK City of Culture 2021 Capital Programme – Approval to receive and be accountable body for additional capital funding for the Cultural Capital Investment Fund - Cabinet Report (August 2018) • Business, Economy and Enterprise Scrutiny Board (3) – St Mary’s Guildhall (November 2018) • Budget Report 2020/21 – Cabinet Report (February 2020) • Business, Economy and Enterprise Scrutiny Board (3) – St Mary’s Guildhall Transformation Project (March 2020)
Has it been or will it be considered by Scrutiny?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicRESOLVED that approval be given to exclude the press and public under Section 100(A) 4 of the Local Government Act 19...
Exclusion of the Press and PublicRESOLVED that approval be given to exclude the press and public under Section 100(A) 4 of the Local Government Act 19...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.