Resolved
RESOLVED that the Cabinet Member for Jobs and Regeneration approves the allocation of an additional £0.48m of capital money from corporate resources to the rebuild of the Whitley Depot welfare and administration building.
Jobs and Regeneration approved this item on Tuesday 14 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Cabinet Member for Jobs and Regeneration approves the allocation of an additional £0.48m of capital money from corporate resources to the rebuild of the Whitley Depot welfare and administration building.
Cabinet resolved to provide a new welfare and administration building at the City Council’s operational depot in Whitley at their meeting on 10th April 2018.
Following detailed design work, a submission for planning permission and tendering of the building construction contract the project costs have risen to £5.07m compared to the original estimated costs of £4.35m, leaving a funding gap of £0.72m.
This report seeks to provide the Cabinet Member for Jobs and Regeneration with the proposals to reduce the above funding gap and also to seek his approval to allocate a further £0.48m of capital resources to the project.
The Cabinet Member for Jobs and Regeneration is recommended to:
1. Approve the allocation of an additional £0.48m of capital money from corporate resources to the rebuild of the Whitley Depot welfare and administration building. List of Appendices included:
None
The original Cabinet report approving the rebuild of the Whitley Depot welfare and administration building can be found at the following link:
Replacement of Administration Building at Whitley Depot and ICT Data Centre at Jackson Road.pdf
Other useful documents
None
Has it been or will it be considered by Scrutiny?
No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
No
Will this report go to Council?
No Whitley Depot Rebuild – Additional Capital Allocation
1. Context (or background)
1.1The City Council’s primary operational depot is located in Whitley and houses the following functions: waste management, vehicle workshops, highways, building services, and passenger transport.
1.2Approximately 500 frontline employees are deployed from Whitley on daily basis to carry out the above functions. The site also provides a waste transfer station and is home to the majority or the City Council’s fleet of vehicles.
1.3Apart from the existing vehicle workshops the welfare and administration facilities at Whitley Depot are made up porta cabins (installed in 2004/05) and a post war former workshop building converted into office space.
1.4Both of the existing buildings are thermally inefficient and are heated from oil fired heating. Neither building is accessible as defined in 2010 equalities act, and the welfare facilities for 500 are inadequate.
1.5In 2018 Cabinet resolved to fund a project to replace the welfare and administration building at Whitley by combining the existing provision at Whitley Depot and the provision at the City Council’s 24 hour communications centre at Jackson Road (Holbrooks). The replacement building would be provided at Whitley Depot, leaving the Jackson Road available for alternative uses.
1.6Following a detailed design exercise, planning consultation and tendering for the construction of a new welfare and administration building at Whitley Depot there remains a shortfall in capital. This report therefore seeks the allocation of an additional £0.48m of capital resource to the project.
2. Options considered and recommended proposal
2.1The tendered price for the replacement welfare and administration building at Whitley Depot is £0.72m higher than the allocated budget for the project.
2.2In order to close the above funding gap, the project team have reduced the overall size of the building by 10%, predominantly removing administrative office space. In addition, and in consultation with colleagues in the planning and highways teams several the external finishes to the proposed building have been downgraded. This has reduced the funding gap to £0.48m.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Whitley Depot Rebuild: Additional Capital AllocationReport | 84 KB | DownloadRead as text |
Follow Jobs and Regeneration at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Jun 2020 | Exclusion of the Press and PublicRESOLVED that approval be given to exclude the press and public under Section 100(A) 4 of the Local Government Act 19... | Approved | Open |
| 3 Jun 2020 | St Mary's Guildhall Capital ProjectRESOLVED that the Cabinet Member for Jobs and Regeneration:- (1) Approves the detail of the preferred capital scheme ... | Approved | Open |
| 3 Jun 2020 | Land Disposal at Parkside, Paradise Street and Re-provision of Newgate Court Industrial EstateRESOLVED that the Cabinet Member for Jobs and Regeneration:- 1. Declares the part of the land at Parkside, Paradise S... | Approved | Open |
| 4 Mar 2020 | Exclusion of the Press and PublicRESOLVED that approval be given to exclude the press and public under Section 100(A) 4 of the Local Government Act 19... | Approved | Open |
| 4 Mar 2020 | 8-12 Ironmonger Row, 17-21 Cross Cheaping Coventry - 250 Year LeaseRESOLVED that the Cabinet Member for Jobs and Regeneration:- 1) Grants a new 250 year lease, at the sum identified in... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.