RESOLVED that planning permission be granted in respect of Application FMP/2021/3789 subject to conditions listed in the report and the completion of a Unilateral Undertaking (UU) to secure the Travel Plan and its monitoring. Note: Having declared interests, Councillor G Lloyd and Councillor R Simpson withdrew from the meeting during consideration of this item
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
Planning Committee Report Planning Ref: FMP/2021/3789 Site: Coundon Court School, Northbrook Road, Coventry Ward: Bablake Proposal: Demolition of six existing school buildings and erection of three new buildings for teaching and educational purposes (Use Class F1); changes to internal circulation routes, site drainage, landscaping and parking provisions together with a temporary haul road, sports and temporary classrooms for use over the construction period. Case Officer: Emma Spandley
SUMMARY The application site comprises the existing Coundon Court Secondary School, which is located off Northbrook Road, the school also has an access from Holly Fast Lane.
The site is located within the Green Belt.
The application proposes the demolition of six existing school buildings and erection of three new buildings for teaching and educational purposes (Use Class F1); changes to internal circulation routes, site drainage, landscaping and parking provisions together with a temporary haul road, temporary sports pitches and temporary classrooms for use over the construction period.
The application contains details about the road the contractors will used to enter the site, referred to as the ‘Haul’ road, and the location of the contractors’ compound.
However, the haul road has been given temporary permission under the previous consent. This application seeks to reuse the existing haul road.
The contractor’s compound does not require planning permission. It can be installed under Permitted Development.
BACKGROUND Coundon Court School is mixed secondary school, including sixth form. It is one of the largest schools of its kind in the country, with a current enrolment of 1734 pupils and capacity to increase to 2025, within five years’ time. The school currently has a mixed academic and vocational curriculum with a strong focus on community, with elements of the school site being in use out of hours.
The site extends to 15.5 ha with a series of buildings focussed within the northern portion of the site, with the associated playing fields to the south and southwestern portion of the site.
The site is located within the Green Belt and contains a number of existing buildings, including two locally listed buildings, known as Coundon Court School ‘Old House’ and Coundon Court Lodge (also known as Holly Lodge); the recently completed New Teaching Building, Performing Arts Centre, sports hall building, and Business and Information Technology block, which will remain unchanged under the current proposals.
The original school block buildings were constructed from building systems known as Intergrid and Laingspan, in the post war period, are now in a poor condition and no longer fit for purpose. As such, Coundon Court School is receiving investment through the School Rebuilding Programme (SRP) to replace and redevelop these elements, which are reaching the end of their design life and have potential structural weaknesses that mean they should not be retained beyond that.
The school will remain in operation throughout the construction of the new buildings, with a reliance on some temporary accommodation to ensure continuity in provision. As new buildings are completed and become ready for occupation, the school will decant into the new facilities and the existing buildings will be demolished. Land which is not being built on will be restored for the purposes of landscaping, outdoor play space and parking.
The proposals cater for the existing pupil numbers on the current PAN and the size of the school in terms of pupil numbers will not change because of the proposals.
Subject to planning permission being granted, a start on site is scheduled for June 2022. There will be a phased programme of completion with final handover due to occur in August 2025.
KEY FACTS Reason for report to Over 5 objections against the location of the contractor’s committee: compound Current use of site: School Proposed use of site: School
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.