Cabinet, Tuesday 16 December 2025 at 2.00pm

Coventry Very Light Rail

Approved Executive 3 papers

AI summaryCabinet recommended Coventry City Council approve an 800m twin track very light rail demonstrator in live traffic. CVLR has a £40.5m CRSTS allocation, but Stage Gate 3B construction needs DfT approval, with public rides planned for Autumn 2027. [D] [P2] [P14] [5.2] [5.5] [4.1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved800m live traffic route, conditional on DfT funding [P2] [P14]
Money£40.5m CRSTS allocation [5.2]£3.2m local match contribution [5.2]
What happens nextStage Gate 3B approval [5.5]Release targeted for Jan 26 [P80]
Who it affectsCity centre transport users [P115]Disabled people, older people, cyclists and pushchair users [P115]

What was decided

Cabinet recommended that Council approve installation of the CVLR slab track and a short operating period for the 800m twin track City Centre Demonstrator from Coventry Railway Station to Coventry University Technology Park in live traffic, following release of the next DfT funding phase. Report P2, P14

The recommendation also sought Council approval to delegate live traffic operation, subject to risk mitigation, and to secure approvals, legal agreements, contracts and infrastructure leases. The Director of Innovation would consult the Director of Law and Governance, Director of Finance and Resources, Director of Regeneration and Economy, and the Cabinet Member for Jobs, Regeneration and Climate Change. Report P8, P9, P10, P11

The recommendation sought authority to begin business case work for Coventry's first commercial route, subject to the necessary funding being secured. Report P12, P19

Why

The demonstrator will test whether the track can be installed quickly, within the expected cost limit, in a more complex environment, and whether the vehicle can operate in live traffic. Report 1.4, 2.1

The demonstration will provide public and stakeholder rides, test traffic signal integration, installation speed and affordability, and collect data to inform the first commercial route's business case and design. Report 1.5, P38, 2.1

CVLR could support greater use of rail based public transport, local jobs and skills, and wider commercial interest. A commercial route could eventually link the Investment Zone with the railway station and continue towards Pool Meadow, University Hospital Coventry & Warwickshire and Ansty Park. Report 1.11, 1.13, 2.9

What happens next

Stage Gate 3B construction funding can be released only after the Independent Review Panel assesses technical evidence, the case for safety, costs and risk, and the Department for Transport approves it. The table targets release for Jan 26. Report 2.6, 5.5, P80

Following funding approval, the Council can let the construction contract, procure a competent licensed operator and begin delivery. Construction is planned for 2026/2027, with public rides in Autumn 2027. Report 2.3, 4.1

The Director of Innovation is to seek statutory approvals, legal agreements, contracts and leases. A planning application is required for vehicle stabling, and business case work for the first commercial route is subject to funding being secured. Further engagement with residents, businesses and accessibility groups will continue. Report P9, P10, P11, P12, 1.7, 3.5, P115, P116

The money

  • £40.5m CRSTS allocation for CVLR Report 5.2
  • £3.2m Required local match contribution Report 5.2
  • 43,700,000 Total shown in the Stage Gate funding table Report P80
  • 40,500,000 CRSTS CVLR funding shown in the Stage Gate table Report P80
  • 3,200,000 Council match contribution shown in the Stage Gate table Report P80
  • £1m Committed sum for track and highway maintenance Report 5.11
  • circa £10m/km Target CVLR installation cost Report P1

Options considered

  • Chosen: Approve installation and operation of 800m twin track CCD. It would develop the system for live traffic, showcase the technology, collect technical data, provide greater certainty over capital costs and demonstrate the potential for autonomous operation. Report P49, P50, 2.1
  • Rejected: Do not proceed with CCD. The report discounted it because of positive On Road Test results, continued DfT and WMCA support, the need to develop commercial potential and transport benefits, and the risk of weakening the business case and existing grant funded investment. Report P57, 2.7, 2.10, 2.11

Implications

  • Financial: The 800m section will use the current approved CRSTS budget. Stage Gate 3B construction funding is conditional on DfT approval following Independent Review Panel scrutiny. Report 2.4, 2.6, 5.5
  • Financial: The grant agreements provide a 10% cost and programme tolerance. Spend or slippage above that limit goes through Change Control. Report 5.6
  • Legal: Planning permission is required for vehicle stabling, platforms and track outside adopted highway, while track in adopted highway is permitted development. A Transport and Works Act Order is required for a fare paying passenger service, and the Council intends to apply for one after a commercial route has been funded and agreed. Report 5.15, 5.16
  • Risk: Live traffic operation depends on a case for safety, Independent Review Panel scrutiny, Department for Transport approval, road safety audits and a letter of no objection from the Independent Competent Person. Report 2.6, 5.21, 5.22
  • Risk: The Council will work with utility companies to leave most equipment in place and provide ducting where appropriate. Trials showed access could usually be gained without lifting the track. Report 1.9
  • Equalities: Installing track on the carriageway may affect disabled people, older people and people using bikes or pushchairs. Proposed mitigation includes audio and visual warnings, signage, lighting and anti slip materials. No adverse impact on protected characteristic groups is anticipated. Report P115, P118
  • Climate: CVLR is zero emission at point of use and is intended to encourage more people to use rail based public transport. Report P121
  • Staffing: Delivery will use existing Council resources where possible and external contractors. The operator will hold the relevant licences and be responsible for infrastructure management and the transport undertaking under the 2006 safety regulations. Report 6.3, 2.3

Who and where

  • Coventry residents and visitors Report P2, 2.2
  • Disabled people, older people, cyclists and pushchair users Report P115
  • Nearby residents and businesses Report 3.2, 3.4
  • People seeking access to jobs, healthcare, leisure and study Report P107
  • People working at the West Midlands Investment Zone Report 1.10, 2.9
  • Coventry University Report 1.7
  • Utility companies whose equipment lies beneath the route Report 1.9, 2.8
  • Local manufacturers and the wider transport supply chain Report 1.11, 1.13, 6.6

Timeline

  • June 2025: Controlled city centre On Road Test Report P3, 1.2
  • Summer 2025: City centre CVLR demonstration Report P1
  • 13th January 2026: Council consideration of the report Report P31
  • Jan 26: Target for release of Stage Gate 3B construction funding Report P80
  • 2026/2027: Construction of the route Report 4.1
  • Autumn 2027: Public operation and rides for the demonstrator Report 4.1
  • 1 April 2027: The Transport for City Region fund replaces CRSTS, and further funding will be sought from it Report P4
  • October 2027: ITS World Congress at the NEC, with an opportunity to showcase CVLR Report P5

Plain English for the jargon

  • CCD: An 800m twin track demonstration from Coventry Railway Station to Coventry University Technology Park, intended as part of the proposed first commercial route [P2] [P4]
  • CVLR: Coventry Very Light Rail, a research and development project using a prototype vehicle and slab track [1.1] [1.3]
  • CRSTS: City Region Sustainable Transport Settlement, the programme providing CVLR's grant funding [1.1] [5.2]
  • DfT: Department for Transport [1.1]
  • WMCA: West Midlands Combined Authority [1.1]
  • IRP: Independent Review Panel, which assesses technical evidence, safety, costs and risk before funding release [2.6] [5.5]
  • ICP: Independent Competent Person, whose letter of no objection is required before operation [2.6] [5.22]
  • TWAO: Transport and Works Act Order, required for a fare paying passenger service [5.16]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item46

Resolved

RESOLVED that Cabinet recommends that Council approves: 1) The installation of the CVLR slab track and a short period of operation, of the City Centre Demonstrator (CCD) from Coventry Railway Station to Coventry University Technology Park in a live traffic environment will follow the ... view the full minutes text for item 46.
Word for word from the decision Coventry published for this meeting. Source: edemocracy.coventry.gov.uk

Follow this further

Built from Coventry's papers

What the report saysPro

Report to Cabinet, 17 pages

Executive summary

The Coventry Very Light Rail (CVLR) demonstration in the city centre during Summer 2025 was a major success. Our mission is to create a tram system that can be installed quickly and at less than half the cost of conventional tram systems: our ground-breaking track was installed in just over eight weeks and proved that we are on target to achieve our target installation cost of circa £10m/km.

The purpose of this report is to seek approval for the construction of an 800m twin track City Centre Demonstrator (CCD) that will operate in a live traffic environment from Coventry railway station to Coventry University Technology Park (see Appendix 1 to the report for the route plan). This demonstration phase builds on everything learned in the summer and will help to lay the foundations for the first commercial route by:

1. Operating the CVLR vehicle with live traffic – including the installation of an autonomous ready vehicle control system integrated with the city’s traffic signal control system. 2. Providing rides for the public and stakeholders to demonstrate how the vehicle has evolved since the On Road Test (ORT) in June 2025 and to take feedback on the system 3. Demonstrating at scale, using the learnings from the ORT, the speed of installation and affordability of the CVLR track 4. Expediting the design and delivery process 5. Utilising learning to inform the business case and design of Coventry’s first commercial route and, more widely, to continue to stimulate national and global commercial interest

The 800m route is intended to form part of the proposed first commercial route (subject to business case approval) running from the railway station to the West Midlands Investment Zone (Greenpower Park), with potential to extend northwards from the railway station through the city centre to connect to Pool Meadow, University Hospital Coventry & Warwickshire (UHCW) and to a Park and Ride at Ansty Park. The 800 m demonstrator section will be delivered using allocated grant funding from the City Region Sustainable Transport Funding (CRSTS) and is scheduled to be constructed by March 2027. Further funding will be sought from the Transport for City Region (TCR) fund, which replaces CRSTS from 1 April 2027.

As an added benefit in October 2027 the Intelligent Transport Systems (ITS) World Congress is being staged at the NEC. This provides an excellent opportunity to showcase, to a global audience the benefits of CVLR using it to carry delegates to the National Transport Design Centre (on the Technology Park) to showcase Coventry’s ground- breaking transport innovations.

Recommendations

Cabinet is requested to recommend that the Council approve:

1) The installation of the CVLR slab track and a short period of operation, of the City Centre Demonstrator (CCD) from Coventry Railway Station to Coventry University Technology Park in a live traffic environment will follow the release of the next phase of approved funding by the DfT.

2) Delegated authority to the Director of Innovation, following consultation with the Director of Law and Governance, the Director of Finance and Resources, the Director of Regeneration and Economy, and Cabinet Member for Jobs, Regeneration and Climate Change, to operate CVLR in a live traffic environment subject to risks being appropriately mitigated.

3) Delegated authority to the Director of Innovation to secure the necessary Statutory approvals to construct CCD.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Coventry Very Light Rail: Appendix 1: CVLR CDD route MapAppendix 1 pages Download
PDF
Coventry Very Light Rail: Appendix 2: Equality Impact Assessment: VLR City Centre DemonstratorAppendix 8 pages Download
PDF
Coventry Very Light RailReport 17 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Coventry

Search all
  1. Coventry Very Light RailThis decision
  2. Coventry Very Light RailApproved
  3. Coventry Protocol for Addressing Adult Modern SlaveryDecided
  4. Coventry Protocol for Addressing Adult Modern SlaveryAgreed
  5. Coventry Very Light RailApproved
  6. Coventry Very Light Rail (VLR)Approved

More from Coventry Cabinet

All decisions
MeetingDecisionOutcome
7 Jul 2026 Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S... Approved Open
7 Jul 2026 Acceptance of the Music Hub Revenue Grant for the Strategic Area of Coventry, Warwickshire and SolihullRESOLVED that, the Cabinet: 1. Approve acceptance of the revenue grant for the academic year 2026/27 from ACE of £1,7... Approved Open
17 Mar 2026 Private Sector Housing Enforcement Policy 2026-31RESOLVED that the Cabinet recommend that the policy be reviewed by full Council for approval. Approved Open
17 Mar 2026 Coventry: City of Movement Strategy 2026-2031RESOLVED that, the Cabinet: 1. Note and accept the additional recommendation from the Scrutiny Co-ordination Committe... Approved Open