AI summaryCoventry City Council approves building an 800m twin-track Very Light Rail demonstrator from the railway station to the university technology park, with construction by March 2027 and public rides in Autumn 2027.
Written from the decision and the officer reportPDF Pro
OutcomeApproved800m route from station to technology park
MoneyNot stated
What happens nextConstruction in 2026/2027, rides Autumn 2027Subject to DfT Stage Gate 3B funding release
Who it affectsCity centre road users, residents, businessesPlus ITS World Congress delegates in October 2027
What was decided
The Council approved installing the CVLR slab track and a short period of operation of the 800m City Centre Demonstrator, subject to the next phase of DfT funding being released. Report P7, P14
Delegated authority was given to the Director of Innovation, following consultation with named directors and the Cabinet Member for Jobs, Regeneration and Climate Change, to operate CVLR in live traffic, secure statutory approvals, enter legal agreements, award contracts and initiate business case work for a commercial route. Report P8, P9, P10, P11, P12, P15, P16, P17, P18, P19
Why
The 2025 On Road Test on Queen Victoria Road and Greyfriars Road, which carried around 3,000 passengers, showed the track can be installed in just over eight weeks and supports a target installation cost of circa £10m per km. Report P1, 1.2, 1.3
The Council wants to demonstrate the CVLR system in a live traffic environment, gather further safety and operating data, and showcase it to a global audience at the ITS World Congress at the NEC in October 2027. Report P5, P38, 1.5, 1.14
Officers concluded that not proceeding would compromise existing grant-funded investment, lose learning for the first commercial route, and forfeit support from the DfT and West Midlands Combined Authority. Report P57, 2.7, 2.10, 2.11
What happens next
The Independent Review Panel will assess Stage Gate 2 and partial Stage Gate 3A evidence before the DfT's Roads Investment Committee considers releasing Stage Gate 3B construction funding, targeted for January 2026. Report 1.15, P80, 2.6, 5.5
Subject to funding release, a construction contract will be let, an operator will be procured, stabling planning permission will be sought, and lease agreements for associated infrastructure will be completed. Report P9, P11, P19, 1.7, 4.1
Further public engagement and drop-in sessions will continue over coming months, with road safety audits and a Transport and Works Act Order application planned once a commercial route is funded. Report 3.5, 5.16, P98
The money
£40.5m CRSTS grant allocation for the CVLR programme Report 1.1, 5.2, P80
£3.2m Local match contribution previously approved by Cabinet on 12 October 2021 Report 5.2, P80
40,500,000 CRSTS CVLR funding line in the stage gate table Report P80
3,200,000 CCC match contribution line in the stage gate table Report P80
43,700,000 Total CRSTS plus match funding line in the stage gate table Report P80
circa £10m/km Target installation cost for CVLR track Report P1
£1m Commuted sum agreed for track and highway maintenance Report 5.11
Options considered
Chosen: Approve the 800m twin-track City Centre Demonstrator, its operation, statutory approvals, legal agreements, contracts, leases and business case work (Recommended). Builds on successful 2025 On Road Test, secures DfT and WMCA support, supports ITS Congress showcase and feeds into first commercial route business case. Report P50, 2.1, 2.2, 2.3, 2.4, 2.6
Rejected: Do not proceed with the City Centre Demonstrator (Not Recommended). Would compromise existing grant investment, lose commercial route learning, and miss opportunity to engage utilities and stakeholders ahead of a wider network. Report P57, 2.7, 2.8, 2.9, 2.10, 2.11
Implications
Financial: Construction is funded from the existing £40.5m CRSTS allocation with £3.2m match; a 10% cost and programme tolerance applies before change control is triggered, and there is a low financial risk of unlimited utility indemnity claims, covered by insurance and the CVLR budget. Report 5.6, 5.7, 5.9, 5.11
Legal: The Council will apply to itself as highway authority for consents, obtain planning permission for stabling, platforms and non-adopted track, and follow safety verification under ROGS 2006 with a Transport and Works Act Order to follow for any fare-paying service. Report 5.14, 5.15, 5.16, 5.18, 5.21, 5.22
Risk: Top risks include technical issues with vehicle, track or infrastructure, vehicle build delays, utility consent, personal injury or third-party property damage, and delays procuring an operator; these are mitigated by the Independent Review Panel, Independent Competent Person, road safety audits and an established risk register. Report P95, P96, P97, P98, 5.19, 5.20, 5.21, 5.22, 5.23
Equalities: An Equalities Impact Assessment has been produced; potential impacts on disabled people, older people, cyclists and pushchair users will be mitigated through engagement, audio and visual warnings, signage, lighting and anti-slip materials. Report P115, P116, P117, P118, P119
Climate: CVLR is zero emission at point of use and is intended to encourage modal shift, supporting the council's net zero transport target. Report P121, P106, P107
Staffing: The programme will be delivered using existing Coventry City Council officer resources with professional services and external contractors procured as needed. Report 6.3, P110, P123
Who and where
City centre road users, pedestrians and cyclists during construction on the demonstrator route Report 1.8, 3.2, 3.4
Friargate Resident Liaison Group and Stoney Road Area Residents consulted in July 2025 Report 3.1
Park Road residents and businesses offered drop-ins in November 2025 Report 3.4
Accessibility and equalities groups invited to trial and feed back on the demonstrator Report P115, P116, P119
Visitors and delegates attending the ITS World Congress at the NEC in October 2027 Report P5, 2.2
Utility companies whose apparatus will largely remain in situ under the track Report 1.9, 2.8
Transport for West Midlands, West Midlands Combined Authority and the Department for Transport as funders and partners Report 1.1, 1.10, 5.2, 6.6, P123
Colas Rail Ltd as appointed contractor and the future operator to be procured Report 1.10, 2.3, 4.1, P123
Timeline
19 May 2025: DfT approved change control for Stage Gate 3A prepare-to-construct element Report 2.4, P76
July 2025 to August 2025: On Road Test ran on Queen Victoria Road and Greyfriars Road with around 3,000 passengers Report 1.2, 2.8
10 July 2025: Engagement with Friargate Resident Liaison Group and Stoney Road Area Residents at the Council House Report 3.1
Week commencing 28 July 2025: Letter and leaflet about the City Centre Demonstrator delivered to nearby residents and businesses Report 3.2
November 2025: Drop-in sessions offered to Park Road businesses and residents Report 3.4
January 2026 (target): DfT Stage Gate 3B construction funding release subject to Independent Review Panel recommendation Report P80, 2.6
13 January 2026: Council approval of City Centre Demonstrator recommendations Report P31
2026/2027: Construction of the 800m City Centre Demonstrator route Report P4, 4.1
By March 2027: City Centre Demonstrator scheduled to be constructed using CRSTS funding Report P4
Autumn 2027: City Centre Demonstrator operational for public rides, including new Gen1 vehicle Report 1.6, 2.2, 4.1, P98
31 March 2027: End of current five-year CRSTS funding programme Report 4.1
1 April 2027: Transport for City Region fund replaces CRSTS Report P4
October 2027: ITS World Congress held at the NEC, with CVLR rides showcased Report P5, 2.2
Plain English for the jargon
CVLR: Coventry Very Light Rail, a research and development tram system intended to be quicker and cheaper to install than conventional light rail.
CCD: City Centre Demonstrator, the proposed 800m twin-track CVLR section from Coventry Railway Station to Coventry University Technology Park.
CRSTS: City Region Sustainable Transport Settlement, the funding programme providing the £40.5m CVLR allocation, running to 31 March 2027.
ORT: On Road Test, the summer 2025 trial of CVLR on Queen Victoria Road and Greyfriars Road.
DfT: Department for Transport, the UK government department providing CRSTS funding and approving stage gate releases.
WMCA: West Midlands Combined Authority, the accountable body for CRSTS funding.
TCR: Transport for City Region fund, which replaces CRSTS from 1 April 2027.
IRP: Independent Review Panel of industry experts providing independent scrutiny of CVLR test results.
ICP: Independent Competent Person appointed under ROGS 2006, who must issue a letter of no objection before operation.
ROGS 2006: Railways and Other Guided Transport Systems (Safety) Regulations 2006, governing safety verification for the system.
TWAO: Transport and Works Act Order, a form of statutory authorisation that will be needed for any fare-paying CVLR passenger service.
VLRNIC: Very Light Rail National Innovation Centre in Dudley, where the CVLR vehicle underwent over 1,000km of testing.
UHCW: University Hospital Coventry and Warwickshire, a potential destination on a future commercial CVLR route.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item71
Resolved
RESOLVED that the City Council approves: 1) The installation of the CVLR slab track and a short period of operation, of the City Centre Demonstrator (CCD) from Coventry Railway Station to Coventry University Technology Park in a live traffic environment will follow the release of the next phase of approved funding by the DfT. 2) To delegate authority to the Director of Innovation, following consultation with the Director of Law and Governance, the Director of Finance and Resources, the Director of Regeneration and Economy, and Cabinet Member for Jobs, Regeneration and Climate Change and the Main Opposition Group Shadow Cabinet Member for Jobs, Regeneration and Climate ... view the full minutes text for item 71.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
The Coventry Very Light Rail (CVLR) demonstration in the city centre during Summer 2025 was a major success. Our mission is to create a tram system that can be installed quickly and at less than half the cost of conventional tram systems: our ground-breaking track was installed in just over eight weeks and proved that we are on target to achieve our target installation cost of circa £10m/km.
The purpose of this report is to seek approval for the construction of an 800m twin track City Centre Demonstrator (CCD) that will operate in a live traffic environment from Coventry railway station to Coventry University Technology Park (see Appendix 1 to the report for the route plan). This demonstration phase builds on everything learned in the summer and will help to lay the foundations for the first commercial route by:
1. Operating the CVLR vehicle with live traffic – including the installation of an autonomous ready vehicle control system integrated with the city’s traffic signal control system. 2. Providing rides for the public and stakeholders to demonstrate how the vehicle has evolved since the On Road Test (ORT) in June 2025 and to take feedback on the system 3. Demonstrating at scale, using the learnings from the ORT, the speed of installation and affordability of the CVLR track 4. Expediting the design and delivery process 5. Utilising learning to inform the business case and design of Coventry’s first commercial route and, more widely, to continue to stimulate national and global commercial interest
The 800m route is intended to form part of the proposed first commercial route (subject to business case approval) running from the railway station to the West Midlands Investment Zone (Greenpower Park), with potential to extend northwards from the railway station through the city centre to connect to Pool Meadow, University Hospital Coventry & Warwickshire (UHCW) and to a Park and Ride at Ansty Park. The 800 m demonstrator section will be delivered using allocated grant funding from the City Region Sustainable Transport Funding (CRSTS) and is scheduled to be constructed by March 2027. Further funding will be sought from the Transport for City Region (TCR) fund, which replaces CRSTS from 1 April 2027.
As an added benefit in October 2027 the Intelligent Transport Systems (ITS) World Congress is being staged at the NEC. This provides an excellent opportunity to showcase, to a global audience the benefits of CVLR using it to carry delegates to the National Transport Design Centre (on the Technology Park) to showcase Coventry’s ground- breaking transport innovations.
Recommendations
Cabinet is requested to recommend that the Council approve:
1) The installation of the CVLR slab track and a short period of operation, of the City Centre Demonstrator (CCD) from Coventry Railway Station to Coventry University Technology Park in a live traffic environment will follow the release of the next phase of approved funding by the DfT.
2) Delegated authority to the Director of Innovation, following consultation with the Director of Law and Governance, the Director of Finance and Resources, the Director of Regeneration and Economy, and Cabinet Member for Jobs, Regeneration and Climate Change, to operate CVLR in a live traffic environment subject to risks being appropriately mitigated.
3) Delegated authority to the Director of Innovation to secure the necessary Statutory approvals to construct CCD.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Election of the Leader of the CouncilRESOLVED that Councillor George Duggins be duly elected as Leader of the Council. Note 1): In accordance with Council...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.