2025/26 Third Quarter Financial Monitoring Report (to December 2025)
ApprovedExecutive1 paper
AI summaryCoventry Cabinet approves Q3 2025/26 financial monitoring, noting a £1.6m revenue overspend and a £174m capital outturn after £11.1m of scheme rescheduling.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevenue forecast £1.6m over budget after management action
Money£174m capital; £1.6m revenue overspend£1.1m new approvals, £11.1m rescheduled to later years
What happens nextNot stated
Who it affectsNot stated
What was decided
Cabinet approved the council's third quarter revenue monitoring position, which shows net spend £1.6m over the £296.7m revenue budget after management action, an improvement of £1.7m on the second quarter. Report P5, P6, 1.2, P27
Cabinet approved a revised forecast capital outturn of £174m for 2025/26, made up of a £1.1m net increase for approved and technical changes and £11.1m of programme rescheduling into future years. Report P6, P43, P46, P47
Why
The main revenue pressures are Adult Social Care purchasing packages of care (£6.2m, partly offset by client fee income), Property Services holding costs on the City Centre South project (£1.3m), and overspends in City Services and Regeneration and Economic Development, partly offset by an £8.6m underspend in Contingency and Central Budgets. Report P2, P29, P30, P31, P33, P34, P36, P42
Capital rescheduling is driven by revised contractor cashflows for the City Centre Cultural Gateway (£6.1m into 2026/27), delays to refuse vehicle delivery (£1.4m), Pearl Hyde school phasing (£1.4m), Citizen Housing joint venture (£1.0m) and street lighting LED upgrades (£1.0m). Report P43, P140, P141
What happens next
The Audit and Procurement Committee will consider the report on 16th March 2026 and forward any recommendations to Cabinet. Report P8, P17
There is no implementation timetable because this is a monitoring report, and the Director of Finance and Resources does not currently need to take any extra-ordinary action to respond to the position. Report 4.1, P86
The money
£1.6m Net revenue forecast overspend after management action Report P1, 1.2, P27, P81
£7.0m Q3 2024/25 revenue overspend for comparison Report P1, 1.2
£174m Forecast 2025/26 capital outturn Report P6, P43, P47
£171.6m Capital Programme originally approved by Cabinet in February 2025 Report 1.1
£296.7m Revenue budget approved by Cabinet on 25th February 2025 Report 1.1, P27
£1.1m Net increase in capital spending from approved or technical changes Report P6, P43, P47, P138
£11.1m Net capital programme rescheduling into future years Report P6, P43, P47, P144
£6.2m Adult Social Care overspend on purchased packages of care Report P29, P111
£2.2m Property Services and Development forecast overspend Report P27, P31
£2.1m City Services forecast overspend Report P27, P32
£1.7m Regeneration and Economic Development forecast overspend Report P27, P36
£1.3m Finance and Resources forecast overspend Report P27, P38
£8.6m Contingency and Central Budgets forecast underspend Report P27, P42
£6.0m Asset Management Revenue Account surplus, including higher CWSDC and Birmingham Airport dividend income Report P42, P135
£2.6m Net Treasury Management underspend from interest on borrowing and cash balances Report P42, P135
£2.5m Adverse variance from underachievement of One Coventry Programme and Senior Management savings Report P42, P134
£28.8m Net long-term borrowing requirement for the 2025/26 capital programme Report P55
£86.1m Existing commercial investment commitments against a £115m combined limit for 2025/26 Report P72, P73
£30m Original pooled fund investment, now at £28.6m capital value Report P66
Options considered
Chosen: Approve the third quarter revenue monitoring position and revised £174m capital outturn. Reflects the latest forecast and rescheduling needed to keep projects within resources Report P5, P6, 2.1
Implications
Financial: Net £1.6m revenue overspend after management action, an improvement of £1.7m on Q2 but still requiring ongoing management; the council has limited reserves and should avoid relying on them. Report P1, P27, P81, P83
Financial: Capital programme is mostly externally funded: 64.2% grants, 25.1% borrowing, with £17.3m of capital receipts; legacy inflation continues to affect capital schemes. Report P3, P44, P49
Risk: Maintaining a stable balanced budget is identified as a key corporate risk, with strict financial discipline and quarterly monitoring as the main mitigations. Report 1.3, P93
Equalities: No policy changes proposed at this stage, but any future service changes would be assessed through the council's equality impact process. Report 6.4, P97
Climate: No direct climate impact at this stage, though climate and environmental impact are likely to feature more strongly in future decisions. Report 6.5, P99
Other: Treasury management activity is within prudential indicators: variable rate exposure of -£36.7m against a £102.7m limit and fixed rate exposure of £227.0m against a £513.6m limit. Report P68, P69, P70, P151, P152
Who and where
Adult Services and Housing directorate, with a £3.8m forecast overspend largely from adult social care packages Report P27, P29
Property Services and Development, with a £2.2m overspend linked to City Centre South and commercial property income Report P27, P31
City Services, with a £2.1m overspend covering environmental services, waste and highways Report P27, P33, P34, P35
Regeneration and Economic Development, with a £1.7m overspend from lower planning and cultural income Report P27, P36, P37
Capital scheme sponsors affected by rescheduling, including City Centre Cultural Gateway, refuse vehicle replacement, Pearl Hyde school, Citizen Housing joint venture and street lighting LED upgrade Report P140, P141
Timeline
25th February 2025: Cabinet approved the £296.7m revenue budget and £171.6m capital programme Report 1.1, P56
31st December 2025: End of Q3 monitoring period for the 2025/26 report Report P1, P17
10th February 2026: Cabinet decision approving Q3 monitoring position and £174m capital outturn Report P6
16th March 2026: Audit and Procurement Committee to consider the report and forward recommendations to Cabinet Report P8, P17
Plain English for the jargon
Outturn: The actual or forecast final spending position for a financial year
Rescheduling: Moving planned capital spending from this financial year into a later one
Prudential Indicators: CIPFA-set measures that show whether a council's borrowing and investments are affordable and sustainable
PWLB: Public Works Loan Board, a government body that lends to local authorities
DSG: Dedicated Schools Grant, ringfenced funding for schools
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item60
Resolved
RESOLVED that Cabinet: 1) Approves the Council’s third quarter revenue monitoring position. 2) Approves the revised forecast capital outturn position for the year of £174m incorporating: £1.1m net increase in spending relating to approved/technical changes and £11.1m of net programme rescheduling of expenditure to future years.
Word for word from the decision Coventry published for this meeting.Source: edemocracy.coventry.gov.uk
The purpose of this report is to advise Cabinet of the forecast outturn position for revenue and capital expenditure and the Council’s treasury management activity as at the end of December 2025. The net revenue forecast position after management action is for spend in 2025/26 of £1.6m over budget. Whilst not a wholly comparable position, at the same point in 2024/25, there was a projected overspend of £7.0m.
The Council continues to face budget pressures within Adults Social Care, Property Services & Development, City Services and Regeneration & Economic Development. These financial pressures are being caused by a combination of continued service demand, complexity & market conditions in social care, legacy inflation impacts, and income shortfalls due largely to the economic climate.
The Council’s capital spending is projected to be £174m and includes major schemes progressing across the city. The size of the programme and the nature of the projects within it continue to be fundamental to the Council’s role within the city. Although prevailing inflation rates look to be stabilising, legacy inflationary pressures continue to affect capital projects. We will continue to monitor this position and ensure projects are delivered within available resources. Recommendations:
The Cabinet is requested to:
1) Approve the Council’s third quarter revenue monitoring position.
2) Approve the revised forecast capital outturn position for the year of £174m incorporating: £1.1m net increase in spending relating to approved/technical changes and £11.1m of net programme rescheduling of expenditure to future years.
Audit and Procurement Committee is requested to:
1) Consider the proposals in the report and forward any recommendations to Cabinet.
List of Appendices included:
Appendix 1 - Revenue Position: Detailed Service breakdown of forecast outturn position Appendix 2 - Capital Programme: Analysis of Budget/Technical Changes Appendix 3 - Capital Programme: Analysis of Programme Acceleration/(Rescheduling) Appendix 4 - Prudential Indicators
Background papers
None
Other useful documents
None
Has it been or will it be considered by Scrutiny?
No
Has it been or will it be considered by any other Council Committee, Advisory Panel or other body?
Yes - Audit and Procurement Committee, 16th March 2026
Will this report go to Council?
No Report title: 2025/26 Third Quarter Financial Monitoring Report (to December 2025)
1. Context (or background)
1.1Cabinet approved the City Council's revenue budget of £296.7m on 25th February 2025 and a Capital Programme of £171.6m. This is the third quarterly monitoring report for 2025/26. The purpose is to advise Cabinet of the forecast outturn position for revenue and capital expenditure, recommending any action required, and to also report on the Council’s treasury management activity.
1.2The current 2025/26 revenue forecast is for net expenditure to be £1.6m over budget (after management action). The reported forecast at the same point in 2024/25 was an overspend of £7.0m which reflected pressures relating primarily to social care activity and price. Capital spend in 2025/26 is projected to be £174m.
1.3Whilst it is not unusual to experience a forecast overspend at this point, it is essential that the Council maintains strict financial discipline to operate within approved budgets.
2. Options considered and recommended proposal.
2.1This is a budget monitoring report and as such there are no options.
Table1: Revenue Position - The revenue budgets and forecast positions are shown below analysed by service area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue and Capital Outturn 2025/26RESOLVED that Council be recommended to approve the contribution to reserves of £3.2m for the purposes described in S...
Transport Capital Programme 2026/27RESOLVED that, the Cabinet: 1. Approve delivery of the 2026/27 programmes of Local Network Improvement schemes and Hi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.