RESOLVED That the Cabinet: 1. approves the adoption and publication of the proposed Local List of Planning Requirements (Appendix 1 to report PES/306), with effect from 22 November 2018; 2. delegates authority to the Cabinet Member for Planning and Economic Development to approve subsequent updates to the Local List of Planning Requirements tokeep it up to date and compliant with national policy. Reasons for the Recommendations The most recent review of the Local List of Planning Requirements was in 2010 and it is now out of date. A revised Local List is needed in order to apply local validation requirements, which have themselves changed with the adoption of the 2015 Local Plan. The revised Local List has been subject to a four-week public consultation and the proposed version takes account of responses received. Officers consider that it represents an appropriate set of requirements for planning applications in Crawley. The Town and Country Planning (Development Management Procedure) (England) Order 2015 (known as the ‘Development Management Procedure Order’) provides that Local Lists must be reviewed every two years in order to remain in force. The proposed delegation is considered appropriate in light of this.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
a) Approve the adoption and publication of the proposed Local List of Planning Requirements (Appendix 1), with effect from 22 November 2018;
b) Delegate authority to the Cabinet Member for Planning and Economic Development to approve subsequent updates to the Local List of Planning Requirements to keep it up to date and compliant with national policy.
Reasons for the recommendations
3.1The most recent review of the Local List of Planning Requirements was in 2010 and it is now out of date. A revised Local List is needed in order to apply local validation requirements, which have themselves changed with the adoption of the 2015 Local Plan.
3.2The revised Local List has been subject to a four-week public consultation and the proposed version takes account of responses received. Officers consider that it represents an appropriate set of requirements for planning applications in Crawley.
3.3The Town and Country Planning (Development Management Procedure) (England) Order 2015 (known as the ‘Development Management Procedure Order’) provides that Local Lists must be reviewed every two years in order to remain in force. The proposed delegation is considered appropriate in light of this.
Background
4.1Planning applications must be accompanied by certain documents before they can be registered and assessed. Certain national requirements for submitting an application are set out in the Development Management Procedure Order. Article 11 of the Order (see weblink at end of report) also allows a Local Planning Authority to publish a ‘Local List’ of requirements, setting out additional documents to be provided before an application is registered. Para. 44 of the National Planning Policy Framework (see weblink at end of report) further states that Local Planning Authorities ‘should publish a list of their local information requirements’ arising from the local development plan, which ‘should be reviewed at least every two years.’
5. Description of Issue to be resolved
5.1In the absence of an up-to-date Local List, planning officers are often obliged to register applications which are not considered to be sufficiently detailed. The council can still request additional documentation after registration and refuse permission where it is not forthcoming. This can, however, increase the risk of not determining the application within the statutory period. In addition, an updated Local List will enhance the ability for the Local Planning Authority to implement the policy requirements set out in the 2015 Local Plan.
5.2The revised Local List will be published and will be used to screen all applications made to the Local Planning Authority before they are registered. Where applications are not compliant further information will be requested, and applications will be counted as invalid until it has been provided. Only then will the statutory determination period commence.
5.3The revised Local List will affect all stakeholders in the planning process. Applicants such as developers (including the council) and their agents will have a clear and up to date list of information requirements. Council officers, consultees, and members of the public will have greater assurance that the information provided with planning applications will be sufficient to enable them to be assessed and meet the requirements set out in the policies of the Crawley Borough Local Plan 2015-2030.
6. Information & Analysis Supporting Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.