RESOLVED That Cabinet notes 1. the projected outturn for the year 2018/2019 as summarised in report FIN/456. 2. the Section 106 contributions identified to fund the Memorial Gardens Play Improvement Project as identified in Paragraph 9.1 of the report FIN/456. Reasons for the Recommendations To report to Councillors on the projected outturn for the year compared to the approved budget.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
a) Note the projected outturn for the year 2018/2019 as summarised in this report.
b) Note the Section 106 contributions identified to fund the Memorial Gardens Play Improvement Project as identified in Paragraph 9.1 of the report.
Reasons for the recommendations
To report to Members on the projected outturn for the year compared to the approved budget.
Background
4.1As part of the Budget Strategy, the Council has in place robust budget monitoring systems to ensure that unapproved overspends are avoided. The Council also manages and analyses underspending to identify potential savings that could help meet current and future years’ priorities.
4.2Budget monitoring is undertaken on a monthly basis with budget holders. There are quarterly budget monitoring reports to Cabinet with the Corporate Management Team receiving monthly update reports on key areas and any other areas of concern. The Overview and Scrutiny Commission also have the opportunity to scrutinise expenditure. Quarterly monitoring information is also included in the Councillors’ Information Bulletin.
4.3This report outlines the projected outturn for 2018/2019 as at the end of September 2018. 5. Budget Monitoring Variations
5.1General Fund
The table below summarises the projected variances in the relevant Portfolio at Quarter 2.
[F indicates that the variation is favourable, U that it is unfavourable]
Variance at Variance at Quarter 2 Quarter 1 £’000 £'000
Cabinet (36) F (14) Public Protection & Community Engagement (22) F (10) Resources (48) F (66) Environmental Services & Sustainability (10) F (46) Housing (99) F (11) Wellbeing (20) F (58) Planning & Economic Development 21 U 66
Investment Interest (200) F (170)
TOTAL SURPLUS (414) F (309)
Further details of these projected variances are provided in Appendix 1(i & ii) attached to this report.
5.2Significant variances variations over £20,000
5.2.1 Cabinet
There is a vacant post in the transformation team resulting in a saving of £21,000. This post will be needed to support the Transformation Programme in providing specific project management skills once the plan is developed – the intention is to recruit in Quarter 3.
5.2.2 Public Protection & Community Engagement
There are no significant variations to report this quarter.
5.2.3 Resources
There are no significant variations to report this quarter.
Quarter 1 reported an underspend of £21,000 in the Community Wardens service. However, a secondment to cover maternity and one-off costs were incurred for Travellers prevention measures which have resulted in this service now reporting a £4,000 overspend. Temporary measure had to be hired until the permanent measures (in the capital programme) were installed.
The expected saving reported in Quarter 1 in Environmental Health did not take into account the standby allowance for Noise; this has reduced the underspend by £47,000. With other variations, the underspend of £69,000 reported at Quarter 1 for this service has been reduced to £15,000.
5.2.5 Housing Services
Grant has been received from the DWP for implementation of Universal Credit: the additional works has been absorbed within the benefits team. In addition, further data matching on behalf of HMRC has resulted in additional income to the service.
5.2.6 Wellbeing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.