RESOLVED That the Cabinet approves the Council’s continuation in the LASER Framework Contract for energy procurement for the period from 1 October 2020 to 30 September 2024. Reasons for the Recommendations LASER benchmarks their purchasing performance each year and shares this information with its customers. This benchmarking exercise indicates that LASER has been able to deliver prices to customers at 4.6% below the market average over the last 4 years. Based on current consumption this level of performance would equate to a total saving in energy costs over the next 4 year contract period of £98,000 assuming similar performance levels. Given the estimated savings achieved through a flexible procurement strategy, it is recommended that the Council continue its arrangement with LASER and participate in the framework contract for the 4 year period from 1st October 2020 to 30 th September 2024. The Pan Government Energy project recommended that to spread market risk, and avoid buying during periods of peak market pricing, “all public sector organisations adopt aggregated, flexible and risk-managed energy procurement” as provided under the LASER framework.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
Approve the Council’s continuation in the LASER Framework Contract for energy procurement for the period from 1st October 2020 to 30th September 2024.
Reasons for the recommendations
3.1LASER benchmarks their purchasing performance each year and shares this information with its customers. This benchmarking exercise indicates that LASER has been able to deliver prices to customers at 4.6% below the market average over the last 4 years. Based on current consumption this level of performance would equate to a total saving in energy costs over the next 4 year contract period of £98,000 assuming similar performance levels.
3.2Given the estimated savings achieved through a flexible procurement strategy, it is recommended that the Council continue its arrangement with LASER and participate in the framework contract for the 4 year period from 1st October 2020 to 30th September 2024.
3.3The Pan Government Energy project recommended that to spread market risk, and avoid buying during periods of peak market pricing, “all public sector organisations adopt aggregated, flexible and risk-managed energy procurement” as provided under the LASER framework. 4. Background
4.1The Council has had a long standing arrangement with LASER (Local Authority Energy Buying Group) who purchase energy on the Council’s behalf under a framework agreement. LASER currently manages the energy procurement for 160 local authorities including West Sussex, Horsham and Mid Sussex; with a total annual spend of £450 million.
4.2Historically these energy contracts were tendered under fixed price arrangements which, in a relatively stable market, secured best value for the Council. However, wholesale energy price volatility over short periods in recent years made this an increasingly high risk strategy and in common with most LASER Members in 2008 the Council switched to a system of flexible energy procurement.
4.3A wholesale flexible procurement arrangement enables the buyer to purchase blocks of energy at varying times both before and within the contracted supply period. The arrangement removes the risk of settling a LASER Members requirement on a single day. Aggregating the volumes of members within the arrangement enables effective market hedging.
5. Description of Issue to be resolved
5.1LASER has now completed the tender process for the next flexible energy framework contract which will run from 1st October 2020 to 30th September 2024 and requires confirmation from its Member authorities that they wish to participate in the new contract. The successful suppliers under this contract are:-
Electricity - Npower Gas - Total Gas & Power
5.2The framework contract covers electricity and gas supplies to the Council’s operational sites with an estimated value over the 4 year contract term of £2,140,000 i.e. £1,600,000 (Electricity) and £540,000 (Gas).
5.3An early commitment is required by LASER from authorities wishing to participate in the new contract due to its nature which may involve energy purchasing on the wholesale market 12 months or more prior to the contract start date. LASER cannot commence forward purchase on behalf of Council sites until a commitment to join the framework contract has been received.
6. Information & Analysis Supporting Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.