Crawley Growth Programme – Next Phase Projects and Update to S106 Allocation, Funding and Governance

Approved Executive 1 paper

Cabinet approved this item on Wednesday 26 June 2019. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED That the Cabinet approves 1. going out to public consultation on the concept designs, as set out in Appendices A-C of report PES/316 for the next tranche of Crawley Growth Programme schemes : a) Manor Royal to Three Bridges cycle route; b) Town Centre cycle route improvements; c) Bus shelter “super hubs”. 2. expenditure of up to £783,000 from the existing CBC capital programme – Crawley Growth programme budget on the detailed design phase for the three schemes listed in the previous resolution, subject to consultation. 3. the allocation of £327,570 of received S106 developer contributions to West Sussex County Council, to be used for one of the Crawley Growth Programme schemes for which they are the Lead Authority 4. the transfer of Lead Authority for the Town Centre Commercial Space development project from West Sussex County Council to Crawley Borough Council. That Full Council be recommended to approve 1. a further £600,842 of received S106 developer contributions is allocated to the CBC capital programme Crawley Growth programme budget and commit these funds to the specific projects as detailed in 7.2.2 of report PES/316 2. from within the existing Crawley Growth Programme budget, the allocation of £327,637 of received S106 developer contributions to the project schemes set out in section 7.2.2 of report PES/316 3. an increase to the overall Crawley Growth programme capital programme allocation of £6 million for the Town Centre Commercial Office Space project within the Crawley Growth programme, to be funded from contributions from existing funding commitments to the Crawley Growth Programme, subject to formal agreement with WSCC of a revised funding protocol. Reasons for the Recommendations The recommendations will allow Crawley BC to progress the referenced projects to the next phase. The report to Cabinet of 4 October 2017 informed Members that the Crawley Growth programme will be part financed by an allocation of £2,481,000 of S106 funding. To date Crawley BC has received from developers £1,946,958 of the intended S106 monies. Of this amount Crawley BC has already allocated £1,018,547 to the Crawley Growth Programme. The purpose of the Full Council recommendations 1 and 2, was therefore to allocate received S106 funds to the Crawley Growth programme budget within the CBC capital programme so these funds can in turn be allocated to specific projects. The ... view the full minutes text for item 8.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1To the Overview and Scrutiny Commission:

2.1.1. That the Commission consider the report and decide what comments, if any, it wishes to make to the Cabinet.

2.2The Cabinet is recommended to:

a) Approve going out to public consultation on the concept designs for the next tranche of Crawley Growth Programme schemes: I) Manor Royal to Three Bridges cycle route; II) Town Centre cycle route improvements; III) Bus shelter “super hubs”. (Appendices A to C) b) Approve expenditure of up to £783,000 from the existing CBC capital programme - Crawley Growth programme budget on the detailed design phase for the above 3 schemes, subject to consultation. c) Approve the allocation of £327,570 of received S106 developer contributions to West Sussex County Council, to be used for one of the Crawley Growth Programme schemes for which they are the lead authority (Appendix G). d) Approve the transfer of lead authority for the Town Centre Commercial Space development project from West Sussex County Council to Crawley Borough Council.

2.3Request Full Council to:

e) Approve that a further £600,842 of received S106 developer contributions is allocated to the CBC capital programme Crawley Growth programme budget and commit these funds to the specific projects as detailed in 7.2.2. f) Approve from within the existing Crawley Growth Programme budget, the allocation of £327,637 of received S106 developer contributions to the project schemes set out in section 7.2.2. g) Approve an increase to the overall Crawley Growth programme capital programme allocation of £6 million for the Town Centre Commercial Office Space project within the Crawley Growth programme, to be funded from contributions from existing funding commitments to the Crawley Growth Programme, subject to formal agreement with WSCC of a revised funding protocol. 3. Reasons for Recommendations

3.1The recommendations as set out in a, b, d and g, will allow Crawley BC to progress the above projects mentioned to the next phase.

3.2The report to Cabinet of 4 October 2017 informed Members that the Crawley Growth programme will be part financed by an allocation of £2,481,000 of S106 funding. To date Crawley BC has received from developers £1,946,958 of the intended S106 monies. Of this amount Crawley BC has already allocated £1,018,547 to the Crawley Growth Programme. The purpose of the recommendation e and f, is therefore to allocate received S106 funds to the Crawley Growth programme budget within the CBC capital programme so these funds can in turn be allocated to specific projects.

3.3Recommendation c as described above will enable West Sussex County Council to allocate S106 monies to the delivery of the Manor Royal Highways improvements scheme, which is part of the Crawley Growth programme.

Background

4.1In September 2017, Crawley BC and WSCC were awarded LEP funding for the Crawley Growth Programme. Significant progress has been made, both in terms of governance arrangements / protocols and individual scheme delivery.

4.2On 4 October 2017, Cabinet were informed that the total cost of the Crawley Growth Programme is anticipated to be £60.4 million and that it will be funded from multiple sources including £29.081m to be funded from a number of private sector sources including Metrobus, Manor Royal BID, Gatwick Airport Ltd (GAL) and developer contributions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Crawley Growth Programme: Next Phase Projects and Update to S106 Allocation, Funding and GovernanceReport 4.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 13 attended
PL
Councillor Peter Lamb Leader of the CouncilChair, present
II
Councillor Ian IrvineCommittee Member, present
CM
Councillor Chris Mullins Cabinet Member for WellbeingCommittee Member, present
BS
Councillor Brenda Smith Cabinet Member for Public Protection and Community EngagementCommittee Member, present
PS
Councillor Peter Smith Cabinet Member for Planning and Economic Development and Deputy LeaderCommittee Member, present
GT
Councillor Geraint Thomas Cabinet Member for Environmental Services and SustainabilityCommittee Member, present
NB
Natalie Brahma-PearlOfficer, in attendance
AB
Ann-Maria BrownOfficer, in attendance
ID
Ian DukeOfficer, expected
KH
Karen HayesOfficer, in attendance
CP
Chris PedlowOfficer, in attendance
HG
Heather GirlingOfficer, expected

All 13 on the meeting page

On this subject at Crawley

Search all
  1. Crawley Growth Programme – Next Phase Projects and Update to S106 Allocation, Funding and GovernanceThis decision
  2. Crawley Growth Deal RefreshApproved
  3. Recommendation 6 – Western Boulevard Scheme - Crawley Growth ProgrammeApproved
  4. Western Boulevard Scheme - Crawley Growth ProgrammeAgreed
  5. Western Boulevard Scheme - Crawley Growth ProgrammeNoted
  6. Crawley Growth Programme - Next Phase Projects and Update to S106 Allocation, Funding and Governance - Cabinet, 26 June 2019 (Recommendation 2)Approved

More from Crawley Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a... Approved Open
9 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual... Approved Open
9 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ... Approved Open
9 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Cabinet: a) approves the Crawley Homes Annual Complaints Performance and Service Improvement Plan R... Approved Open
9 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Cabinet: a) approves the Crawley Homes Asset Management Strategy ( appendix A of report CH/222 ) fo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies