Resolved
RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back to the Cabinet through the Commission’s Comment sheet.
Overview and Scrutiny Commission noted this item on Monday 22 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back to the Cabinet through the Commission’s Comment sheet.
2.1To the Overview and Scrutiny Commission:
That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.
2.2To the Cabinet:
The Cabinet is recommended to:
a) Agree to note the projected outturn for the year 2021/2022 as summarised in this report. b) Note the updated proposed spend of Contained Outbreak Management Fund (COMF) grant funding as outlined in section 10.
3.1To report to Members on the projected outturn for the year compared to the approved budget.
4.1As part of the Budget Strategy, the Council has in place robust budget monitoring systems to ensure that unapproved overspends are avoided. The Council also manages and analyses underspending to identify potential savings that could help meet current and future years’ priorities.
4.2Budget monitoring is undertaken on a monthly basis with budget holders. There are quarterly budget monitoring reports to Cabinet with the Corporate Management Team receiving monthly update reports on key areas and any other areas of concern. The Overview and Scrutiny Commission also have the opportunity to scrutinise expenditure. Quarterly monitoring information is also included in the Councillors’ Information Bulletin. 4.3 This report outlines the projected outturn for 2021/2022 as at the end of September 2021.
4.4As discussed in the budget report and Budget Strategy, due to the pandemic it is very difficult to accurately forecast our financial position for the year.
5. Budget Monitoring Variations
5.1General Fund The table below summarises the projected variances in the relevant Portfolio at Quarter 2.
[F indicates that the variation is favourable, U that it is unfavourable]
Variance Variance Projected at Projected at Quarter 2 Quarter 1 £'000's £'000's Cabinet 344 U 331 Public Protection & Community Engagement (17) F (15) Environmental Services & Sustainability 324 U 318 Housing (6) F 18 Wellbeing 930 U 911 Planning & Economic Development (56) F 17 Resources (24) F (3)
Sub Total 1,495 U 1,577
Investment Interest (258) F (48) Sales, Fees and Charges Grant Q1 (316) F (250) Use of Approved Coronavirus Budgets (934) F (1,008)
(SURPLUS)/DEFICIT (13) 271
This will require a transfer from reserves of £142,000 in order to balance the budget.
Further details of these projected variances are provided in Appendix 1(i & ii) attached to this report.
Significant Quarter 2 variances over £20,000
5.2Cabinet
There are no significant variations to report this quarter.
5.3Public Protection & Community Engagement
There are no significant variations to report this quarter.
5.4Environmental Services & Sustainability Services
There are no significant variations to report this quarter. 5.5 Housing Services
There are no significant variations to report this quarter.
5.6Wellbeing
There are no significant variations to report this quarter.
5.7Planning & Economic Development
Additional income has been recognised following the improved offer for the surrender of the lease on Kingsgate car park. The total projected underspend within the asset management team is now £109,000.
5.8Resources
There are no significant variations to report this quarter.
5.9Investment Income
Additional income of £209,800 is being recognised from interest on deferred receipts from shared equity properties due to sale of additional shared equity homes and a larger movement in the house price index than forecast.
5.10Additional Funding – Sales, fees and charges Quarter 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2021/2022 Budget Monitoring: Quarter 2Report | 726 KB | DownloadRead as text |
Follow Overview and Scrutiny Commission at Crawley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... | Noted | Open |
| 7 Sep 2026 | Treasury Management Outturn 2025 – 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate were fed back ... | Noted | Open |
| 7 Sep 2026 | 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... | Noted | Open |
| 7 Sep 2026 | Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... | Noted | Open |
| 7 Sep 2026 | Crawley Homes Asset StrategyRESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.