Crawley Borough Council
Cabinet, Wednesday 26 November 2025 at 7.00pm

2025-2026 Budget Monitoring - Quarter 2

Approved Executive 1 paper

AI summaryCrawley Cabinet notes a £232,000 projected service overspend at Q2 2025/26, approves £26,000 of new Goffs Park path works, and accepts £5.735m of decarbonisation grant for council housing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNotes outturn; adds Goffs Park paths and HRA decarbonisation grant
Money£26,000 new, £5.735m grant, £232,000 overspendCapital addition, HRA grant, projected net service deficit
What happens nextQ3 budget monitoring report dueCar parking income and savings updates promised at Q3
Who it affectsCouncil tenants, residents, Crawley HomesCouncil housing stock and parks users affected

What was decided

Cabinet noted the projected outturn for 2025/26 and the virements approved under delegation, as set out in sections 6 and 9 of report FIN/714. Report P5

Cabinet approved adding £26,000 to the capital programme for path improvements in Goffs Park, funded from the Parks Investment Reserve. Report 9.14, P74

Cabinet approved using confirmed grant of £5.735m for the Social Housing Decarbonisation Fund Wave 3 within the HRA capital programme. Report 9.21, P82

Why

To report to members on the outturn for the financial year compared to the approved budget, as part of the Council's regular budget monitoring. Report 3.1, 4.1, 4.2

The report identifies investment interest income of £1.130m above budget, homelessness temporary accommodation cost pressure of £484k above budget, and an HRA overspend of £1.076m driven mainly by urgent repairs identified through stock condition surveys. Report 5.2, 5.7, P25, 8.2

What happens next

Q3 monitoring will report progress on the £388,000 car parking charges saving, patch working savings, and Create Building occupancy. Report P36, P19

Government reimbursement of £3.06m in 2023/24 and 2024/25 New Burdens claims for Chagos arrivals is still awaited; full repayment is still considered likely. Report P25, P26

The money

  • £26,000 New capital addition for Goffs Park path improvements, from Parks Investment Reserve Report 9.14, P74
  • £5.735m Confirmed SHDF Housing Decarbonisation Wave 3 grant for HRA capital programme Report 9.21, P82
  • £232,000 Projected net service adverse variation for 2025/26 at Q2 Report 5.2, P122
  • £1.130m Additional investment interest forecast for the year above budget Report 5.9, P13, P121
  • £1.076m HRA forecast overspend for 2025/26 Report 8.2, P166
  • £484k Temporary accommodation cost forecast to exceed budget in 2025/26 Report 5.7, P25
  • £785,000 Forecast overspend on Ashdown House empty property costs at Q2 Report 5.5, P19
  • £920,000 HRA responsive repairs overspend driven by stock condition surveys Report P171
  • £121,000 Forecast overspend on parades due to four vacant units Report 5.8, P29, P119
  • £1.732m Full-year budgeted savings for 2025/26; £803,000 achieved at Q2 Report 5.10, P34
  • £3.06m Outstanding Home Office New Burdens claim for 2023/24 and 2024/25 Report 5.7, P25
  • £56,100 Virement approved under delegation for Inspire heating management systems, pay back within 12 months Report 6.2
  • £67,000 Capital virement for two K2 Crawley gas burner replacements funded from additional contract income Report 6.3, 9.11
  • £50,000 Virement for urgent fire compliance works at community centres and sports pavilions Report 9.13
  • £20,000 Virement for Simpler Recycling depot works from grant Report 9.12

Options considered

  • Chosen: Note Q2 outturn and approve £26,000 Goffs Park path capital addition. Reflects spend-to-date, additional grant income and reserves use Report P5, 9.14
  • Chosen: Approve use of £5.735m SHDF Wave 3 grant for HRA capital programme. Confirmed government grant received for housing decarbonisation Report 9.21
  • Chosen: Continue to use contingency budget to underwrite unachieved 2025/26 savings. Contingency was set aside for phasing and set-up costs of savings Report P38

Implications

  • Financial: General Fund balance forecast at £4.183m at 31 March 2026, remaining above the £3m recommended minimum. Report 10.1, P87
  • Financial: HRA working balance held at £5m, with the £1.076m overspend reducing revenue funding available for the HRA capital programme. Report 8.5, 10.3, 10.4
  • Financial: Investment interest is expected to fall in 2026/27 because of forecast interest rate cuts and capital spend, making future surpluses harder to repeat. Report P32
  • Legal: Legal, staffing, climate change, crime and disorder, and customer implications were considered and deemed not to have a direct bearing on the decision. Report 12.2, 12.3, 12.4, 12.5, 12.6
  • Equalities: Equality duty under section 149 Equality Act 2010 considered; equality impact assessments are undertaken on individual projects listed in the report. Report 12.7, 12.8
  • Risk: Risk noted that £3.06m of Home Office New Burdens reimbursement for 2023/24 and 2024/25 has not yet been received, although full repayment is still considered likely. Report 5.7, P25

Who and where

  • Crawley Homes tenants, through additional repairs work and HRA capital investment Report P171
  • Households in temporary accommodation, with continued cost pressure on homelessness budgets Report 5.7, P25
  • Users of community centres, sports pavilions and parks including Goffs Park Report 9.14, 6.2
  • Council staff, with continuing vacancy management and unmet vacancy provision of £185,000 flagged for the 2026/27 budget Report 5.3

Timeline

  • 1 October 2025: Car parking strategy changes implemented following statutory consultation Report P36
  • 2025-11-24: Overview and Scrutiny Commission considered the report before Cabinet Report 2.1, P2
  • 2025-11-26: Cabinet decision taken on Q2 budget monitoring
  • Q3 2025/26: Next monitoring report due, with updates on car parking income, Create Building and patch working Report P36, P19
  • 31 March 2026: End of 2025/26 financial year; forecast General Fund balance £4.183m Report P87

Plain English for the jargon

  • HRA: Housing Revenue Account, a ring-fenced account for income and spend on the council's own housing stock
  • SHDF: Social Housing Decarbonisation Fund, a government grant programme for energy efficiency upgrades
  • RTB: Right to Buy, the statutory scheme allowing council tenants to buy their home
  • MRR: Major Repairs Reserve, a ring-fenced HRA reserve used to fund capital works on housing stock
  • EPR: Extended Producer Responsibility grant, paid to councils to cover the cost of recycling packaging waste
  • New Burdens: Central government funding to reimburse councils for new statutory duties, here for Chagos arrivals temporary accommodation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED That the Cabinet: a) notes the projected outturn for the financial year 2025/26 and the virements approved under delegation as detailed in section 6 and section 9 of report FIN/714 . b) approves the addition to the capital programme of £26,000 for improvements to paths within Goffs Park to be funded from the Parks Investment Reserve as detailed in section 9.14 of report FIN/714 . c) approves the use of confirmed grant funding of £5.735m for SHDF Housing Decarbonisation Wave 3 for the HRA capital programme as detailed in section 9.21 of report FIN/714 . Reasons for the Recommendations To report to Members on the outturn for the financial year compared to the approved budget.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1To the Overview and Scrutiny Commission:

That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.

2.2To the Cabinet:

That the Cabinet is recommended to:

a) Note the projected outturn for the financial year 2025/26 and the virements approved under delegation as detailed in section 6 and section 9 of report FIN/714. b) Approve the addition to the capital programme of £26,000 for improvements to paths within Goffs Park to be funded from the Parks Investment Reserve as detailed in section 9.14 of report FIN/714. c) Approve the use of confirmed grant funding of £5.735m for SHDF Housing Decarbonisation Wave 3 for the HRA capital programme as detailed in section 9.21 of report FIN/714.

Reasons for the recommendations

3.1To report to Members on the outturn for the financial year compared to the approved budget. 4. Background

4.1As part of the Budget Strategy, the Council has in place regular budget monitoring systems to ensure that unapproved overspends are avoided. The Council also manages and analyses underspending to identify potential savings that could help meet current and future years’ priorities.

4.2Budget monitoring is undertaken regularly with Budget Holders. There are quarterly budget monitoring reports to Cabinet with the Corporate Management Team receiving monthly update reports on key areas and any other areas of concern. The Overview and Scrutiny Commission has the opportunity to scrutinise income and expenditure.

5. Budget Monitoring Variations

5.1General Fund

The table below summarises the projected variances at Quarter 2 (Q2) grouped in portfolios for the financial year ending 31 March 2026 compared to approved budget.

Variance Variance Projected at Projected at Quarter 1 Quarter 2 £'000 £'000 Cabinet 562 1,018 Community Engagement & Culture (5) (29) Environment, Sustainability & Climate Change 27 (28) Housing 55 93 Leisure & Wellbeing 79 75 Planning & Economic Development 20 17 Public Protection 0 25 Resources 38 191 TOTAL (SURPLUS)/DEFICIT 776 1,362

Investment Interest (300) (1,130)

ADJUSTED (SURPLUS)/DEFICIT 476 232

Significant Quarter 1 variances +/- £100k

5.2The projected net outturn variation for service expenditure at Q2 for 2025/26 is a deficit of £232,000. This is partly offset with additional grant funding of (£150,000) as detailed in 5.11 resulting in an adverse variance of £82,000. It should be noted that there are fluctuations within service areas. The reasons for major variations in excess of +/- £100,000 are detailed from paragraph 5.5 below, with a more detailed summary at Appendix A. Favourable variations are shown in brackets.

5.3The adverse variations in Appendix A contain £185,000 for the unmet vacancy allowance. This is being monitored closely and will be reflected in the budget assumptions for 2026/27. 5.4. Section 5.10 summarises the savings to date of £803,000 against a full year budget of £1.732m. It should be noted that there is a contingency budget set aside for set up costs and the time to implement changes.

5.5Cabinet

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025-2026 Budget Monitoring: Quarter 2Report 317 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 20 attended
MJ
Councillor Michael JonesChair, present
NH
Councillor Nick HiltonCommittee Member, present
II
Councillor Ian IrvineCommittee Member, present
YK
Councillor Yasmin KhanCommittee Member, present
CM
Councillor Chris MullinsCommittee Member, present
SM
Councillor Sue MullinsCommittee Member, present
AN
Councillor Atif NawazCommittee Member, present
BN
Councillor Bob NoyceCommittee Member, present
DC
Councillor Duncan CrowObserving, in attendance
JR
Councillor Justin RussellObserving, in attendance
GB
Georgina BouetteOfficer, in attendance
DC
Dan CarberryOfficer, in attendance

All 20 on the meeting page

On this subject at Crawley

Search all
  1. 2025-2026 Budget Monitoring - Quarter 2This decision
  2. 2026-2027 Budget Monitoring - Quarter 1Approved
  3. 2026-2027 Budget Monitoring - Quarter 1Noted
  4. 2025-2026 Budget Monitoring - Quarter 3Approved
  5. 2025-2026 Budget Monitoring - Quarter 1Approved
  6. 2025-2026 Budget Monitoring - Quarter 1Noted

More from Crawley Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a... Approved Open
9 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual... Approved Open
9 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ... Approved Open
9 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Cabinet: a) approves the Crawley Homes Annual Complaints Performance and Service Improvement Plan R... Approved Open
9 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Cabinet: a) approves the Crawley Homes Asset Management Strategy ( appendix A of report CH/222 ) fo... Approved Open