Town Centre District Heat Network (DHN) Phase 2

Approved Executive 1 paper

Cabinet approved this item on Wednesday 24 November 2021. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

RESOLVED That the Cabinet a) approves proceeding with the first phase of the study (feasibility) and reallocating £25,000 match funding from the existing £435,000 Town Centre capital budget. b) agrees to a new Capital programme scheme for the DHN phase 2 of £94,950 with the balance of £69,950 being funded from Heat Network Development Unit (HDNU) grant. c) delegates authority to the Head of Major Projects and Commercial Services in consultation with the Cabinet Member for Environment and Sustainability to review findings of the feasibility study and decide whether to proceed with the second phase of the study (full business case) and earmark a further £55,000 match funding from the Town Centre capital budget for this purpose. (Generic Delegation 7 will be used to enact this recommendation). Reasons for the Recommendations a) In October 2018, Cabinet approved the business case for the Town Centre DHN phase 1 (HPS 15) which is currently under construction. b) With the approval of the business case for phase 1, Cabinet also approved the recommendation to: “Note the projected financial implications for phase 2 of the DHN and that future expansion will be subject to a further report to Cabinet once the capital costs and customer and commercial negotiations have progressed” c) With a number of developments in the Town Centre progressing that are potential connections to the DHN phase 2, a prompt examination of the phase 2 feasibility and business case is required. This will allow a decision on possible future construction to be made. d) The Council has also committed to carbon reductions of at least 45% by 2030 and to zero by 2050. It is therefore timely to examine the technical options and financial implications of switching the DHN from gas to a low carbon heat source.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1To the Cabinet

The Cabinet is recommended to:

a) Approve proceeding with the first phase of the study (feasibility) and reallocating £25,000 match funding from the existing £435,000 Town Centre capital budget.

b) Agree to a new Capital programme scheme for the DHN phase 2 of £94,950 with the balance of £69,950 being funded from Heat Network Development Unit (HDNU) grant.

c) Delegate authority to the Head of Major Projects and Commercial Services in consultation with the Cabinet Member for Environment and Sustainability to review findings of the feasibility study and decide whether to proceed with the second phase of the study (full business case) and earmark a further £55,000 match funding from the Town Centre capital budget for this purpose. (Generic Delegation 7 will be used to enact this recommendation).

Reasons for the recommendations

3.1In October 2018, Cabinet approved the business case for the Town Centre DHN phase 1 (HPS 15) which is currently under construction.

3.2With the approval of the business case for phase 1, Cabinet also approved the recommendation to: “Note the projected financial implications for phase 2 of the DHN and that future expansion will be subject to a further report to Cabinet once the capital costs and customer and commercial negotiations have progressed” 3.3. With a number of developments in the Town Centre progressing that are potential connections to the DHN phase 2, a prompt examination of the phase 2 feasibility and business case is required. This will allow a decision on possible future construction to be made.

3.4The Council has also committed to carbon reductions of at least 45% by 2030 and to zero by 2050. It is therefore timely to examine the technical options and financial implications of switching the DHN from gas to a low carbon heat source.

Background

4.1Phase 1 of the town centre DHN is currently under construction and scheduled for completion in February 2022. Once operational, phase 1 will provide heat and hot water to  The New Town Hall and commercial offices (The Create Building)  Geraint Thomas House (91 residential units)  John Brackpool Court (37 residential units)

4.2DHN Phase 1 will subsequently provide heat and hot water to the second phase of residential development on the town hall site (182 residential units) anticipated completion mid-2024. The DHN will also provide electricity to the Town Hall Multi Storey Car Park and to the energy centre itself. Any excess electricity not consumed on site will be sold back to the grid.

4.3An operations, maintenance, metering and billing contract for the DHN was tendered in 2020/2021 with Pinnacle Power being appointed for a 10 year term to undertake these functions on behalf of the Council. This work is scheduled to commence in July 2021 with metering and billing services for the tenants of Geraint Thomas House.

4.4In October 2018, Cabinet approved the business case for the DHN Phase 1 (HPS 15) agreeing expenditure (excluding the energy centre building) towards the Phase 1 capital works. This budget included a contribution from the Heat Network Investment Programme (HNIP) with the balance from the Council’s capital sources. The capital budget was subsequently revised in March 2020 to accommodate the provision of a new electricity sub-station.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Town Centre District Heat Network (DHN) Phase 2Report 363 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 18 attended
PL
Councillor Peter LambChair, present
II
Councillor Ian IrvineCommittee Member, present
GS
Councillor Gurinder S JhansCommittee Member, present
MJ
Councillor Michael JonesCommittee Member, present
CM
Councillor Chris MullinsCommittee Member, present
PS
Councillor Peter SmithCommittee Member, present
NB
Natalie Brahma-PearlOfficer, in attendance
SC
Siraj ChoudhuryOfficer, expected
ID
Ian DukeOfficer, expected
KH
Karen HayesOfficer, in attendance
CP
Chris PedlowOfficer, in attendance
HG
Heather GirlingOfficer, expected

All 18 on the meeting page

On this subject at Crawley

Search all
  1. Town Centre District Heat Network (DHN) Phase 2This decision
  2. Crawley Town Centre Business Improvement District (BID) RenewalAgreed
  3. Recommendation 7 – Crawley Innovation Centre - Additional Towns Fund Monies – PART BApproved
  4. Town Centre Regeneration Programme Third EditionApproved
  5. Crawley Innovation Centre - Draft Towns Fund Business Case - PART B (Recommendation 4)Approved
  6. Council's Nomination to Crawley Town Centre BID BoardDecided

More from Crawley Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a... Approved Open
9 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual... Approved Open
9 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ... Approved Open
9 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Cabinet: a) approves the Crawley Homes Annual Complaints Performance and Service Improvement Plan R... Approved Open
9 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Cabinet: a) approves the Crawley Homes Asset Management Strategy ( appendix A of report CH/222 ) fo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies