RESOLVED That the Cabinet approves to the projected outturn for the year 2022/2023 as summarised in this report FIN/607 . Reasons for the Recommendations To report to Members on the projected outturn for the year compared to the approved budget.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.
2.2To the Cabinet:
The Cabinet is recommended to agree to note the projected outturn for the year 2022/2023 as summarised in this report.
Reasons for the recommendations
3.1To report to Members on the projected outturn for the year compared to the approved budget.
Background
4.1As part of the Budget Strategy, the Council has in place robust budget monitoring systems to ensure that unapproved overspends are avoided. The Council also manages and analyses underspending to identify potential savings that could help meet current and future years’ priorities.
4.2Budget monitoring is undertaken on a monthly basis with budget holders. There are quarterly budget monitoring reports to Cabinet with the Corporate Management Team receiving monthly update reports on key areas and any other areas of concern. The Overview and Scrutiny Commission also has the opportunity to scrutinise expenditure. 4.3 This report outlines the projected outturn for 2022/2023 as at the end of December 2022.
4.4As discussed in the budget report and Budget Strategy, due to the pandemic it is very difficult to accurately forecast our financial position for the year.
5. Budget Monitoring Variations
5.1General Fund The table below summarises the projected variances in the relevant Portfolio at Quarter 3.
[F indicates that the variation is favourable, U that it is unfavourable]
Variance Variance Projected at Projected at Quarter 3 Quarter 2
£'000's £'000's
Cabinet 327 378 U Public Protection & Community Engagement (56) (25) F Environmental Services & Sustainability 152 134 U Housing 1,365 1,164 U Wellbeing (98) (193) F Planning & Economic Development 30 (46) U Resources 38 58 U
TOTAL (SURPLUS)/DEFICIT 1,758 1,470 U
Investment Interest (636) (646) F Lower Tier Services Grant 76 76 U
ADJUSTED (SURPLUS)/DEFICIT 1,198 900 U
Budgeted transfer from reserves 452 452 Total transfer from reserves 1,650 1,352
Further details of these projected variances are provided in Appendix 1(i & ii) attached to this report.
Significant Quarter 3 variances over £20,000
5.1.1 Cabinet
The Audit Committee received EY’s Audit Results Report (FIN/600) in November 2022 which contained their proposed fee for the 2020/21 audit. The provision for audit fees for 2020/21 to 2022/23 have been updated based on this proposal and it has resulted in additional expenditure of £127,000. Rent reviews and back rent for Investment & Operational Properties have resulted in projected additional income of £183,000.
Additional costs of postage and printing for Crawley Live have resulted in a projected overspend of £23,000. The annual cost to print and distribute is now expected to be over £65,000. Mitigations will be sought in the next financial year, or a growth bid will be required if costs persist at this level.
5.1.2 Public Protection & Community Engagement
Vacancies within the Nuisance and Anti-Social Behaviour team have resulted in a projected underspend of £29,000.
Difficulty in recruiting to vacancies in the Community Warden team have resulted in a projected underspend of £65,000.
The total number of consignments the Port Health team have seen through Gatwick Airport is starting to increase but overall is still 73% lower than 2019 before covid. Therefore, further lost income of £23,000 is expected.
5.1.4 Housing Services
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.