RESOLVED That the Cabinet approves: a) the installation of permanent toilet facilities at both Cherry Lane and Millpond unsupervised adventure playgrounds. b) the virement of £107,827 existing capital budget to support the delivery of the project. c) a virement of £25,000 to fund the revenue implications of the scheme from within Community Services budgets. d) that the Head of Community Services be delegated the authority to undertake all necessary processes as required for the installation of the toilets, including (and not limited to), any negotiation and approval of tenders and other documentation, subject to consultation with the Statutory Officers (Generic Delegations 2 & 3 will be used to enact this recommendation). Reasons for the Recommendations To ensure compliance with the council’s constitution and associated decision-making processes to approve the allocation of capital funds and annual revenue budget for installation of permanent toilets at Millpond and Cherry Lane unsupervised adventure playground sites. The Council is not under a legal duty to provide public conveniences. It does however have the discretionary power to provide them pursuant to section 87 of the Public Health Act 1936 (as amended)
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
a) Install permanent toilet facilities at both Cherry Lane and Millpond unsupervised adventure playgrounds.
b) Approve the virement of £107,827 existing capital budget to support the delivery of the project.
c) Approve a virement of £25,000 to fund the revenue implications of the scheme from within Community Services budgets.
d) Subject to approval to proceed, delegate to the Head of Community Services the undertaking all necessary processes as required for the installation of the toilets, including (and not limited to), any negotiation and approval of tenders and other documentation, subject to consultation with the Statutory Officers (Generic Delegations 2 & 3 will be used to enact this recommendation).
Reasons for the recommendations
3.1To ensure compliance with the council’s constitution and associated decision-making processes to approve the allocation of capital funds and annual revenue budget for installation of permanent toilets at Millpond and Cherry Lane unsupervised adventure playground sites.
3.2The Council is not under a legal duty to provide public conveniences. It does however have the discretionary power to provide them pursuant to section 87 of the Public Health Act 1936 (as amended) 4. Background
4.1Full Council on 20th October 2021 ratified the Cabinet decision to convert Cherry Lane and Millpond adventure playground sites into unsupervised adventure playground sites and to “mothball” Creasys Drive and Waterlea sites, pending a further options appraisal.
4.2A capital budget allocation of £400,000 was earmarked to undertake the necessary works. This included;
- Adaptations and / or investment in Cherry Lane and Millpond Adventure Playground to make the sites suitable for unsupervised play. - Removal of equipment / make the sites safe at Creasys Drive and Waterlea sites.
4.3The adaptations at Cherry Lane adventure playground were completed in 2022 with the site opening during Easter 2022. This was reasonably straightforward since the facility had undergone major investment in 2016/17, with the site requiring adaptations rather than wholesale refurbishment.
4.4The equipment at Creasys Drive UAP site has been removed and the site made safe. Much of the equipment had reached the end of its life.
4.5The equipment at Waterlea UAP has been removed and the site made safe. The site currently has a pre-school hiring the building during term time, no other activity takes place at the site which remains closed to the public.
4.6Millpond UAP has recently been fully re-developed into an unsupervised play area, the site opened to the public on 31st May 2023.
4.7Portaloo’s have been in place at both sites since their re-opening thus providing a temporary solution at a cost of £11,151 to date however this is funded from a temporary budget available until the 31 March 2024. However, the portaloo’s at Cherry Lane UAP site have been vandalised on numerous occasions.
4.8Work to install toilet provision at both sites was scheduled to commence in November 2023, this is currently on hold pending approval from Cabinet as outlined in this paper.
5. Description of Issue to be Resolved
5.1The Cabinet Member for Leisure and Wellbeing has requested that members of the public have access to permanent toilet provision at Cherry Lane and Millpond UAP sites.
5.2The buildings at Cherry Lane and Millpond play areas are no longer used to deliver council services and there are lease agreements in place which do not permit public use of these building including their toilet facilities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.