RESOLVED That Cabinet: a) agrees to note the projected outturn for the year 2023/2024 as summarised in report FIN/643 . b) approves the addition to the Capital Programme of £53,635 for artificial cricket wickets and net bays funded by £43,635 contribution from England Cricket Board and £10,000 from Sussex Cricket. (paragraph 8.8 report FIN/643 ) c) approves the addition to the Capital Programme of £115,680 to deliver the final elements of the HRA Database funded from the Housing Revenue Account (HRA). (para 8.10 report FIN/643 ) Reasons for the Recommendations To report to Members on the projected outturn for the year compared to the approved budget.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.
2.2To the Cabinet:
The Cabinet is recommended to:
a) Agree to note the projected outturn for the year 2023/2024 as summarised in this report.
b) Approve the addition to the Capital Programme of £53,635 for artificial cricket wickets and net bays funded by £43,635 contribution from England Cricket Board and £10,000 from Sussex Cricket. (para 8.8)
c) Approve the addition to the Capital Programme of £115,680 to deliver the final elements of the HRA Database funded from the Housing Revenue Account (HRA). (para 8.10)
Reasons for the recommendations
3.1To report to Members on the projected outturn for the year compared to the approved budget.
Background
4.1As part of the Budget Strategy, the Council has in place robust budget monitoring systems to ensure that unapproved overspends are avoided. The Council also manages and analyses underspending to identify potential savings that could help meet current and future years’ priorities. 4.2 Since the budget was set in February 2023 the Council’s financial situation has deteriorated significantly as reported in the 2023/24 Budget Monitoring Report – Quarter 1 (FIN/633) and The 2023/24 Budget Monitoring Report – Quarter 2 (FIN/635). The reasons for the projected overspend include pay inflation and other cost pressures, which are largely offset by the increased return on investments. However, the biggest cost pressure is the increase in the cost of homelessness. The situation with regard to Homelessness (temporary accommodation) has deteriorated further (as explained in paragraph 5.3)
4.3Budget monitoring is undertaken with budget holders. There are quarterly budget monitoring reports to Cabinet with the Corporate Management Team receiving monthly update reports on key areas and any other areas of concern. The Overview and Scrutiny Commission has the opportunity to scrutinise expenditure. Quarterly monitoring information is also included in the Councillors’ Information Bulletin.
4.4This report outlines the forecast outturn for 2023/2024 as projected at the end of December 2023.
5. Budget Monitoring Variations
5.1General Fund The table below summarises the projected variance for the financial year ending 31 March 2024 and the forecast draw on reserves. Quarter 3 Quarter 2 Projection Projection £’000 £’000 Forecast Service Overspend 5,201 3,772 Investment Interest (1,298) (1,256) Sub Total 3,903 2,516 MRP Adjustment (778) (778) Delay to Renewals Transfers (350) 0 Forecast Net Overspend 2,775 1,738 Budgeted Transfer from Reserves 262 262 Total Forecast Transfer from Reserves 3,037 2,000
General Fund Balance 01/04/2023 6,000 6,000 Use of General Fund Balance 23/24 (3,037) (2,000) Transfer in from Earmarked Reserves (As Per 365 365 Budget Strategy) Closing Balance 31/03/2024 3,328 4,365
General Fund Recommended Minimum balance 3,000 3,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.