RESOLVED That the Committee confirm it is satisfied with the risk management arrangements. That the following be brought to the attention of the Chief Executive / Corporate Management Team: a) Consider factoring in questions regarding Local Government Reorganisation into the next staff survey to assess how it was affecting staff morale and wellbeing (Risks 10 and 14 on the Strategic Risk Register). b) Request that information relating to how staff wellbeing was being affected by Local Government Reorganisation be built into the HR and OD Manager’s report to the Overview and Scrutiny Commission (Risks 10 and 14 on the Strategic Risk Register). c) That the potential impact on public perception on the elected Members democratic mandate be taken into account within the narrative for Risk 10 (Local Government Reorganisation).
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
a) Is requested to consider the contents of this report and confirm it is satisfied with risk management arrangements.
b) Review the Strategic Risk Register (Appendix A) and determine whether there are any matters that it wishes to draw to the attention of the Chief Executive or to Cabinet.
Reasons for the recommendations
3.1The Committee has a responsibility to ensure that action has been taken by Corporate Management Team and relevant Managers on risk-based issues identified and provide independent assurance that our risk management framework is sound.
Background
4.1The Corporate Management Team regularly review the Strategic Risks of the Council and look at the mitigations of those risks. This is a live document and updates on risks are presented to the Audit Committee at its meetings. The internal audit service (SIAP) will give an annual report and opinion on the organisation’s framework of governance and risk management on the audit work conducted in the year. The Audit Plan looks at these Strategic Risks.
4.2The focus of effective risk management is the identification and management of risks and opportunities. It increases the probability of success, reduces the likelihood or failure and the uncertainty of achieving objectives. Risk management should be a continuous and evolving process which runs throughout the Council’s strategies and service delivery. 4.3. This enables the Audit Committee to meet its responsibilities to provide the Council with independent assurance of the adequacy of the risk management framework and associated control environment.
5. Risk Management Arrangements
5.1The Council’s approach to risk management is set out in its Risk Management Strategy. The objectives of a risk management strategy are to:
• Integrate risk management into the culture of the Council by engendering a positive attitude and understanding to risk throughout service areas. • Manage risk is accordance with best practice. • Prevent injury, damage, and financial loss to those connected with the Council’s delivery of services.
6. Strategic Risk Register
6.1A strategic risk is defined as an event or action that will affect the organisations’ overall ability to achieve its corporate objectives and execute strategies successfully. By their nature, strategic risks are generally not service or objective specific; they are areas of risk that cut across service and objective boundaries.
6.2The Strategic Risk Register (Appendix A) is a live document which is regularly reviewed by the Corporate Management Team, and it includes a summary of the current analysis of residual risk as well as detail on each Strategic Risk.
6.3The risk tolerance of the Council is the threshold above which the level of risk is not acceptable and requires further action to reduce the risk. The level has been agreed by the Corporate Management Team to be any risk with a residual score (i.e., with controls in place) of 15 or above (red risks). This is set out in the Risk Management Strategy.
6.4Risks around maintaining a balanced budget, reducing homelessness, climate change and migration / asylum pressures are exceeding this score. In these cases, there are external factors that are affecting the score. These scores are being constantly reviewed by the Corporate Management Team and updates will be provided at future Audit Committees.
7. Updates since Consideration by the Audit Committee (3 December 2024)
7.1Risk 1: Maintaining a balanced budget
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.