AI summaryCrawley Audit Committee confirmed satisfaction with risk management and asked the Chief Executive to seek Home Office funding for asylum-related staff costs.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedChief Executive asked to seek Home Office support
MoneyUp to £2.8m annual cost riskMigration and asylum pressures on temporary accommodation
What happens nextLobby Home Office for fundingChief Executive and Corporate Management Team to act
Who it affectsCouncil services and residentsAsylum response, homelessness, planning, staffing
What was decided
The Committee confirmed it is satisfied with the council's risk management arrangements. Report P2
The Chief Executive and Corporate Management Team were asked to seek additional financial support from the Home Office for the cost of council staff visiting asylum hotels to support leavers before eviction. Report P20, P21
Why
The Committee has a responsibility to ensure action has been taken on risk-based issues and to provide independent assurance that the risk management framework is sound. Report 3.1, 4.2
Several strategic risks now score above the council's tolerance level of 15, including balanced budget, homelessness, climate change and migration or asylum pressures. Report 6.3, 6.4
What happens next
Lobbying for a review and extension of new burdens funding continues at Ministerial level, with no confirmation yet for the 2025/26 financial year. Report P21
A Government decision on Local Government Reorganisation proposals is expected in March 2026, after which the council is set to be abolished on 1 April 2028. Report 7.1, P26
The residual risk for recruitment, retention and succession planning will be reviewed once the staff survey results and retention data are available. Report P31
The money
£2.8m Potential annual cost risk for temporary accommodation and resource funding after new burdens funding ended in March 2025 Report P20
£0.7m Best case scenario budget surplus under Funding Review 2.0 forecasts Report 7.1
£3.5m Worst case scenario budget deficit under Funding Review 2.0 forecasts Report 7.1
£1.5m Prudent savings and cuts target for 2026/27, with any shortfall funded from reserves Report 7.1
Options considered
Chosen: Confirm satisfaction with current risk management arrangements and seek Home Office support for asylum costs. Committee viewed the framework as sound and judged Risk 3 mitigation limited without extra funding Report P2, P19
Rejected: Leave the residual risk score for Risk 3 at 16. Committee had previously judged the council's ability to mitigate was limited and Corporate Management Team later raised the score to 20 Report P19, P21
Implications
Financial: Migration and asylum pressures carry a £2.8m per year cost risk now that new burdens funding ended in March 2025. Report P20
Financial: Budget Strategy 2026/27 to 2027/28 was approved by full Council on 22 October 2025, with a reduced horizon due to Local Government Reorganisation. Report 7.1
Risk: Several strategic risks including balanced budget, homelessness, climate change and migration or asylum exceed the council's residual risk tolerance of 15. Report 6.3, 6.4
Staffing: Recruitment, retention and succession planning remains a concern in light of Local Government Reorganisation, with the residual score held at 12 pending staff survey results. Report P30, P31
Legal: Withdrawal of the Water Neutrality Position Statement on 31 October 2025 may leave planning decisions open to legal challenge on water neutrality grounds. Report P23
Other: Climate change is identified as a strategic risk and is being monitored, though the report has no direct climate or environmental implications. Report 6.4, P38, 8.4
Who and where
Asylum seekers and hotel leavers in Crawley, who may face eviction with reduced notice and officer support Report P21
The homelessness service, facing additional strain from single adult males losing accommodation entitlement Report P20
Council staff in the Chagossian Response Team and those visiting asylum hotels Report P21
Planning applicants and developers, as the council considers longer Planning Committee meetings to clear a backlog Report P24
Council employees, given uncertainty over recruitment, retention and succession during Local Government Reorganisation Report P30, P31
Timeline
2 September 2025: Previous Audit Committee meeting where risk scores for Risks 3 and 13 were discussed Report P15, P19, P30
26 September 2025: West Sussex joint reorganisation proposals and a Brighton and Hove proposal submitted to Government Report P26
22 October 2025: Full Council approved the Budget Strategy 2026/27 to 2027/28 Report 7.1
31 October 2025: Natural England withdrew its September 2021 Water Neutrality Position Statement Report P23
Late November 2025: Further information on Funding Review 2.0 expected Report 7.1
Mid-December 2025: Provisional Local Government Finance Settlement expected Report 7.1
End of January 2026: Expected completion of the Station change procedure for Three Bridges Station Report P28
March 2026: Government decision expected on Local Government Reorganisation proposals Report P26
1 April 2028: Crawley Borough Council set to be abolished under Local Government Reorganisation Report 7.1
Plain English for the jargon
LGR: Local Government Reorganisation, the planned restructuring of councils in West Sussex
CMT: Corporate Management Team, the council's senior officer group
LEP: Local Enterprise Partnership, involved in the Crawley Growth Programme
EIA: Equality Impact Assessment, not required for this report
Residual risk: Risk score after controls and mitigations are taken into account
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
RESOLVED That the Committee confirm it is satisfied with the risk management arrangements. That, in regard to Risk 3 (Migration / Asylum Pressures), the Chief Executive / Corporate Management Team seek additional financial support from the Home Office to assist with the additional financial burden incurred due to the increased number of Council staff visits to asylum hotels to support leavers in advance of their eviction would be funded.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
a) Is requested to consider the contents of this report and confirm it is satisfied with risk management arrangements.
b) Review the Strategic Risk Register (Appendix A) and determine whether there are any matters that it wishes to draw to the attention of the Chief Executive or to Cabinet.
Reasons for the recommendations
3.1The Committee has a responsibility to ensure that action has been taken by Corporate Management Team and relevant Managers on risk-based issues identified and provide independent assurance that our risk management framework is sound.
Background
4.1The Corporate Management Team regularly review the Strategic Risks of the Council and look at the mitigations of those risks. This is a live document and updates on risks are presented to the Audit Committee at its meetings. The internal audit service (SIAP) will give an annual report and opinion on the organisation’s framework of governance and risk management on the audit work conducted in the year. The Audit Plan looks at these Strategic Risks.
4.2The focus of effective risk management is the identification and management of risks and opportunities. It increases the probability of success, reduces the likelihood or failure and the uncertainty of achieving objectives. Risk management should be a continuous and evolving process which runs throughout the Council’s strategies and service delivery. 4.3. This enables the Audit Committee to meet its responsibilities to provide the Council with independent assurance of the adequacy of the risk management framework and associated control environment.
5. Risk Management Arrangements
5.1The Council’s approach to risk management is set out in its Risk Management Strategy. The objectives of a risk management strategy are to:
• Integrate risk management into the culture of the Council by engendering a positive attitude and understanding to risk throughout service areas. • Manage risk is accordance with best practice. • Prevent injury, damage, and financial loss to those connected with the Council’s delivery of services.
6. Strategic Risk Register
6.1A strategic risk is defined as an event or action that will affect the organisations’ overall ability to achieve its corporate objectives and execute strategies successfully. By their nature, strategic risks are generally not service or objective specific; they are areas of risk that cut across service and objective boundaries.
6.2The Strategic Risk Register (Appendix A) is a live document which is regularly reviewed by the Corporate Management Team, and it includes a summary of the current analysis of residual risk as well as detail on each Strategic Risk.
6.3The risk tolerance of the Council is the threshold above which the level of risk is not acceptable and requires further action to reduce the risk. The level has been agreed by the Corporate Management Team to be any risk with a residual score (i.e., with controls in place) of 15 or above (red risks). This is set out in the Risk Management Strategy.
6.4Risks around maintaining a balanced budget, reducing homelessness, climate change and migration / asylum pressures are exceeding this score. In these cases, there are external factors that are affecting the score. These scores are being constantly reviewed by the Corporate Management Team and updates will be provided at future Audit Committees.
7. Updates since the last Audit Committee (2 September 2025)
7.1Risk 1: Maintaining a balanced budget
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.