Forward Programme of Key Procurements (January - June 2026)
ApprovedExecutive1 paper
AI summaryCrawley Borough Council Cabinet approved the procurement forward programme for January to June 2026, covering projects from a £750k car park façade to a £27m housing development, and delegated contract award decisions to the Leader of the Council.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement forward programme January to June 2026
MoneyMulti-projectRange from £750k to £27m
What happens nextDelegated awardThree Bridges scheme to separate Cabinet report in early 2026
Who it affectsSuppliers and council staffFuture procurement and contract delivery
What was decided
The Cabinet approved the procurement forward programme for January to June 2026, listed at Appendix A of report FIN/713. Report P2, 2.1
The Cabinet delegated authority to the Leader of the Council, in consultation with the relevant Cabinet Member, Head of Service, and Head of Governance, People and Performance or Head of Law and Governance, to approve contract awards following a procurement process, except for the Three Bridges Station Improvement Scheme which will go to a separate Cabinet report in early 2026. Report P3
The Cabinet delegated negotiation, approval and completion of all relevant legal documentation to the relevant Head of Service, Head of Governance, People and Performance or Head of Law and Governance, and Head of Corporate Finance, in consultation with the appropriate Cabinet Member, using Generic Delegations 2 and 3. Report P4
Why
Approval gives greater transparency of future procurement processes and lets internal stakeholders input earlier into how contracts are delivered. Report 3.1, 6.1
It creates a key decision so individual procurements can be awarded under delegated authority once tenders conclude, shortening the procurement process. Report 3.2, 5.2
The forward programme is a snapshot of high value procurements above the Cabinet approval threshold of £500k over the contract duration that the Council expects to tender in the next six months. Report 4.1, 4.2
What happens next
Individual procurements on the forward programme will be awarded under delegated authority once the tender process concludes. Report 3.2, P3
A separate Cabinet report will be brought in early 2026 on the Three Bridges Station Improvement Scheme, once railway authorities have concluded their procedure. Report P3, P26
Monitoring arrangements will be agreed between contract managers and contractors, with financial and procurement processes followed for each individual project, and equality and sustainability assessments carried out where appropriate.
The money
£500k Threshold above which contracts must be approved by Cabinet under the Procurement Code Report 4.1
£750k Estimated contract value for Former Town Hall Multi Storey Car Park façade design, supply and installation Report P26
£1.5m Estimated contract value for Tilgate Youth Centre redevelopment, design and build of six flats Report P26
£1.3m New total estimated contract value for Ashdown House support structures, insurance reinstatement and energy performance works Report P27
£26.8m Estimated contract value for Breezehurst Drive (Phase 2) remaining site development Report P27
£2.17m Estimated contract value for Little Trees Cemetery remaining site clearance, groundworks and landscaping Report P27
£27m Estimated contract value for Longley House site development Report P27
£850k Estimated contract value for reconfiguration and refurbishment of 5 Perryfield Road Report P27
£8.5m Estimated contract value for supply and maintenance of bus shelters and free standing advertising units Report P27
Options considered
Chosen: Approve the procurement forward programme and delegate award decisions to the Leader of the Council. Gives transparency, allows earlier stakeholder input and shortens tender timelines Report P2, 3.1, 3.2
Rejected: Bring every individual procurement to a full Cabinet report. Lengthens the procurement process; forward programme approval is the preferred approach Report 3.2, 7.1
Implications
Legal: Procurement processes must comply with the Procurement Act 2023, the Public Contracts Regulations 2015 where frameworks are used, and the Council's Procurement Code, which forms part of the Constitution. Report 4.1
Staffing: Each project and programme carries legal and procurement staffing implications, and monitoring arrangements are to be agreed between the contract manager and the contractor.
Financial: Financial and procurement processes will be followed for each individual project; financial and reporting considerations are set out in the report.
Equalities: Equality impact assessments are undertaken where and when appropriate for each listed project, and the report supports inclusive procurement reflecting Crawley's communities.
Climate: No direct material climate change or environmental implications from this report; assessments are done per project under the Sustainable Procurement Charter.
Risk: Not all procurements may be captured on the forward programme; where this happens, an individual Cabinet report will be taken instead. Report 7.1, 4.3
Other: No direct material crime and disorder implications, and no direct material customer implications, from this report and decision.
Who and where
Internal council stakeholders involved in shaping future contract delivery Report 3.1, 6.1
Suppliers and tenderers for the listed high value procurements Report 4.2, P26, P27
Crawley's communities, through inclusive procurement practices and equality assessments
Contract managers and council procurement and legal staff
Timeline
January 2026: Contractor procurement commences for Tilgate Youth Centre redevelopment, subject to planning approval Report P26
Early 2026: Contractor procurement commences for Ashdown House re-let works Report P27
Early 2026: Separate Cabinet report on Three Bridges Station Improvement Scheme, following conclusion of railway authorities' procedure Report P3, P26
March 2026: Contract award expected for Bus Shelters and Free Standing Advertising Units; contractor procurement commences for 5 Perryfield Road, subject to planning approval Report P27
April 2026: Contract awards expected for Breezehurst Drive (Phase 2) and Little Trees Cemetery (Phase 2), subject to budget approval for the latter Report P27
Spring/summer 2027: Longley House site development (new build) estimated to commence, following demolition works due to start this year Report P27
Plain English for the jargon
MSCP: Multi Storey Car Park
Procurement Code: The Council's internal procurement rules, which form part of its Constitution and require Cabinet approval for contracts above £500k over their duration
Procurement Act 2023: The primary law governing how the Council buys goods, works and services
Public Contracts Regulations 2015: Regulations that apply where procurement frameworks are used
Generic Delegations 2 and 3: Standing delegations used to enact the legal documentation approvals
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED That the Cabinet: a) approves the procurement forward programme January – June 2026 (appendix A of report FIN/713 ). b) delegates authority to the Leader of the Council in consultation with the relevant Cabinet Member, relevant Head of Service, and Head of Governance, People and Performance/Head of Law and Governance to approve the award of the contract following an appropriate procurement process. This is with the exception of Three Bridges Station Improvement Scheme procurement which will be subject to separate Cabinet report in early 2026. c) delegates the negotiation, approval and completion of all relevant legal documentation, following the awarding of the contracts to the relevant Head of Service, Head of Governance, People and Performance/Head of Law and Governance, Head of Corporate Finance, in consultation with the appropriate Cabinet Member. (Generic Delegations 2 & 3 will be used to enact this recommendation) Reasons for the Recommendations By approving the procurement forward programme there is greater transparency of future procurement processes allowing more scope for internal stakeholders to input into how future contracts are delivered. The approval of the forward programme provides a key decision that will enable the individual procurement processes to be awarded under delegated authority once the tender process has concluded giving the Council the ability to reduce the time required to complete a procurement process.
Word for word from the decision Crawley published for this meeting.Source: democracy.crawley.gov.uk
a) Approve the procurement forward programme January – June 2026 (appendix A of report FIN/713).
b) Delegate authority to the Leader of the Council in consultation with the relevant Cabinet Member, relevant Head of Service, and Head of Governance, People and Performance/Head of Law and Governance to approve the award of the contract following an appropriate procurement process. This is with the exception of Three Bridges Station Improvement Scheme procurement which will be subject to separate Cabinet report in early 2026.
c) Delegate the negotiation, approval and completion of all relevant legal documentation, following the awarding of the contracts to the relevant Head of Service, Head of Governance, People and Performance/Head of Law and Governance, Head of Corporate Finance, in consultation with the appropriate Cabinet Member. (Generic Delegations 2 & 3 will be used to enact this recommendation)
Reasons for the recommendations
3.1By approving the procurement forward programme there is greater transparency of future procurement processes allowing more scope for internal stakeholders to input into how future contracts are delivered.
3.2The approval of the forward programme provides a key decision that will enable the individual procurement processes to be awarded under delegated authority once the tender process has concluded giving the Council the ability to reduce the time required to complete a procurement process. 4. Background
4.1The Council’s procurement is governed by the Procurement Act 2023 alongside its own internal rules which are set out in the Procurement Code. The Procurement Code dictates that any contracts awarded above the total value of £500k (across its duration) must be approved by Cabinet.
4.2The attached forward programme at Appendix A identifies those high value procurement processes that the Council is currently aware of that are due to go out to tender in the next six months. This is subject to change.
4.3There may be additional projects that are identified that require procurement action that are not currently on the current forward plan however it is hoped that these will be minimal and are more likely to be one-off or construction-based procurements where additional funding / capital investment has been agreed.
4.4Appendix B gives a brief update on the procurement projects that were previously identified.
5. Description of Issue to be resolved
5.1It is hoped that there is greater transparency and awareness of key procurement projects.
5.2Allowing contracts to be awarded under delegation shortens the tender process.
6. Information & Analysis Supporting Recommendation
6.1By identifying procurement processes in a forward programme, internal stakeholders can input into the process at an earlier stage where there is more ability to influence and make decisions on the future contract delivery model. The organisation can manage resources more effectively
7. Implications
7.1Whilst every effort will be made to ensure that procurement processes are identified and reported in the forward programme there may be some instances where this is not achieved, an individual report will therefore be taken as per the previous model.
Financial Implications 7.2 The financial and procurement processes will be followed for individual projects and programmes. The financial and reporting considerations are set out throughout the report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a...
Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual...
2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.