Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review

Noted Scrutiny 5 papers

AI summaryCrawley scrutiny commission noted a report asking Cabinet to ringfence £3,904,413 of Community Infrastructure Levy funds for Three Bridges station, Hazelwick and Tushmore junction schemes in 2026 to 2029, and will pass views to Cabinet.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedComments to go to Cabinet
Money£3,904,413 recommendedTo be ringfenced across three schemes
What happens nextComments to CabinetVia the Commission Comment sheet
Who it affectsBorough residents and travellersThree major transport schemes

What was decided

The Commission noted the report and asked that views from the debate be passed to Cabinet through the Commission's Comment sheet.

Why

To confirm Crawley's priority CIL Strategic Infrastructure Strand schemes for 2026 to 2029. Report 3.1

To ringfence CIL Strategic Infrastructure Strand monies for the three priority projects so that sufficient funds are available to deliver the schemes going forward. Report 3.2

To align with the evidence base in the adopted Crawley Local Plan 2023 to 2040 and the supporting Infrastructure Delivery Schedule. Report 4.1, P41, 6.2

What happens next

The Commission's views will be passed to Cabinet through the Commission's Comment sheet.

Cabinet will be asked to approve the proposed CIL strategic infrastructure spend priorities 2026 to 2029 and the ringfenced amounts for the three projects. Report P3, P4

The funding programme will be reviewed each year, with projects taken forward in priority order if receipts fall short. Report 5.4, 8.3

The money

  • £2,585,608 Three Bridges Railway Station Improvement project Report P4, P50, P55
  • £360,000 A2011 Crawley Avenue / A2004 Northgate Avenue improvements (Hazelwick) Report P4, P51, P55
  • £958,804 A2011 Tushmore Junction (including £184,321.79 from surcharges), as in the recommendation to Cabinet Report P4, P52
  • £958,805 A2011 Tushmore Junction total as shown in the ringfencing table Report P55
  • £3,904,413 Total ringfenced from current Strategic Infrastructure Strand receipts Report P55
  • £3,720,090.75 Balance of Strategic Infrastructure Strand monies available after deductions Report P47
  • £5,190,113.43 Total CIL received to 31st December 2025 Report P18, P19
  • £520,561.88 Outstanding CIL receipts due to the Council at 31st December 2025 Report P20

Options considered

  • Chosen: Focus Strategic CIL on Critical and Essential schemes in the Infrastructure Delivery Schedule. Aligns with the adopted Crawley Local Plan 2023 to 2040 evidence base and the established CIL governance framework Report 6.2
  • Rejected: Distribute CIL more widely across non IDS schemes. Would not comply with CIL Regulations or support the infrastructure needed to deliver growth in the Local Plan Report P77
  • Rejected: Hold funds in reserve. Would not comply with CIL Regulations or support the infrastructure needed to deliver growth in the Local Plan Report P77
  • Rejected: Defer decisions until after Local Government Reorganisation. Would delay delivery of priority schemes and undermine partnership funding opportunities Report P77

Implications

  • Financial: There is a risk that the spend profile of priority projects will not match CIL receipts, particularly if income is delayed or reduced by affordable housing relief. Report 8.1, P23
  • Legal: CIL is governed by the Planning Act 2008 and the Community Infrastructure Levy Regulations 2010 as amended, and took effect in Crawley on 17th August 2016. Report 4.1, 4.3, 8.4
  • Climate: The Three Bridges station, Hazelwick and Tushmore schemes aim to shift travel away from private cars by improving public transport, walking and cycling, supporting climate objectives. Report 8.10, 8.11, 8.12, 8.13
  • Equalities: An Equality Impact Assessment has been completed and is set out in Appendix D. Report 8.18
  • Staffing: A CIL Technical and Monitoring Officer has been recruited, funded from the 5% CIL administration allowance. Report P62
  • Risk: Around £5.1m of potential CIL income has been lost since 2016 through affordable housing relief, nearly equating to total CIL receipts to end December 2025. Report P23

Who and where

  • Rail passengers and Three Bridges area users Report P49, P50
  • Crawley road users at Hazelwick and Tushmore junctions Report P49, P51, P52
  • Crawley residents and neighbourhoods benefiting from Neighbourhood Improvement Strand schemes
  • West Sussex County Council as the Highway Authority and a delivery partner Report P50, P51, P56
  • NHS Sussex, invited to bring forward future CIL eligible proposals Report P60

Timeline

  • 17th August 2016: CIL charging took effect in Crawley Report 4.3, 8.4
  • 31st December 2025: Date of the CIL financial position reported in the paper Report P18
  • 19th January 2026: Transport and Infrastructure Management Group considered emerging proposals Report 7.2
  • 9th March 2026: Overview and Scrutiny Commission considered the report
  • 2026 to 2029: Period covered by the proposed CIL strategic infrastructure spend priorities Report 2.2, 3.1, P3
  • 2029/30 to 2033/34: Medium term delivery window for further CIL allocations Report P59, P72
  • 2034/35 to 2039/40: Long term delivery window for further CIL allocations Report P59, P72, P76

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge on new development used to fund infrastructure
  • Strategic Infrastructure Strand: Up to 85% of CIL receipts spent on infrastructure to support growth
  • Neighbourhood Improvement Strand: 15% of CIL receipts spent in agreement with local communities
  • IDS: Infrastructure Delivery Schedule, evidence base for infrastructure priorities
  • IBP: Infrastructure Business Plan, the CIL funding programme document
  • UPIP: Unsupervised Play Investment Programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back to the Cabinet through the Commission’s Comment sheet.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Overview and Scrutiny Commission

Recommendations

2.1That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.

2.2To the Cabinet: That the Cabinet is recommended to:

a) Approve the proposed CIL strategic infrastructure spend priorities 2026-29 as set out in section 5.4 of report PES/510,

b) Approve the ringfencing of the following total amounts of CIL Strategic Infrastructure Strand monies for the priority spend priorities for 2026-29: • Three Bridges Station Improvement scheme - £2,585,608 • A2011 Crawley Avenue / A2004 Northgate Avenue improvements - £360,000 • Tushmore Junction improvements - £958,804

Reasons for the recommendations

3.1To confirm Crawley’s priority CIL Strategic Infrastructure Strand schemes for 2026-2029.

3.2To ringfence CIL Strategic Infrastructure Strand monies for the above three priority projects as set out in 2.2b of report PES/510 to ensure sufficient funds to enable delivery of the schemes going forward.

Background

4.1The Community Infrastructure Levy (CIL) is a charge which can be levied by local authorities on new development in their area. CIL was introduced by the Planning Act 2008 and is governed by the Community Infrastructure Levy Regulations 2010 (as amended). It is an important tool for local authorities to secure financial resources to help them deliver the infrastructure needed to support development in their area on the basis that it accords with infrastructure priorities identified in the Infrastructure Delivery Schedule (Appendix B) to facilitate population and employment growth set out in the Crawley Local Plan 2023-2040.

4.2The CIL charge is based on a calculation related to £’s per m2 of net additional floorspace and is payable on ‘buildings that people normally go into’. The charge applies to development of 100m2 or more, or the creation of a single residential dwelling, even if under 100m2. In keeping with the CIL Regulations, the rates set out in the charging schedule are index‑linked, with any necessary adjustment taking place at the start of each calendar year. Further details: Annual Community Infrastructure Levy rate summary 2026.pdf (crawley.gov.uk).

4.3CIL rates payable for different types of development are set by the council’s CIL Charging Schedule, which took effect in Crawley on 17th August 2016. There are also a number of exemptions and reliefs, including affordable housing and self-build housing: https://www.gov.uk/guidance/community-infrastructure-levy#relief-and-exemptions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review: Appendix AAppendix 127 KB Download
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review: Appendix BAppendix 156 KB Download
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review: Appendix CAppendix 94 KB Download
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand ReviewReport 172 KB DownloadRead as text
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review- EIA Appendix DAppendix 86 KB Download

At this meeting

Whole meeting

Who was there

10 of 26 attended
JR
Councillor Justin RussellChair, present
HH
Councillor Hazel HellierVice-Chair, present
KA
Councillor Khayla Abu MosaCommittee Member, present
OA
Councillor Olu AdeniyiCommittee Member, present
MA
Councillor Marion AylingCommittee Member, absent
TB
Councillor Thomas BidwellCommittee Member, present
JH
Councillor Jilly HartCommittee Member, present
IK
Councillor Imtiaz KhanCommittee Member, apologies
KK
Councillor Kiran KhanCommittee Member, present
BL
Councillor Bob LanzerCommittee Member, present
SP
Councillor Steve PritchardCommittee Member, present
TR
Councillor Tahira RanaCommittee Member, present

All 26 on the meeting page

On this subject at Crawley

Search all
  1. Community Infrastructure Levy (CIL) Strategic Infrastructure Strand ReviewThis decision
  2. Community Infrastructure Levy (CIL) Strategic Infrastructure Strand ReviewApproved
  3. Community Infrastructure Levy (CIL) Strategic Infrastructure Strand ReviewApproved
  4. Annual Community Infrastructure Levy (CIL) StatementApproved
  5. Allocating Monies Collected Through Community Infrastructure Levy - Infrastructure Business Plan 2019/20Approved
  6. Allocating Monies Collected Through Community Infrastructure Levy - Infrastructure Business Plan 2019/20Agreed

More from Crawley Overview and Scrutiny Commission

All decisions
MeetingDecisionOutcome
7 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate were fed back ... Noted Open
7 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open