Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review

Approved Executive 5 papers

AI summaryCrawley Cabinet ringfences £3,904,413 of Community Infrastructure Levy Strategic Infrastructure Strand money for three transport schemes to be delivered between 2026 and 2029, including £2,585,608 for Three Bridges Station improvements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCIL strategic spend priorities 2026-29
Money£3,904,413Total ringfenced across three schemes
What happens nextAnnual reviewFunding programme reviewed each year
Who it affectsThree transport schemesStation and two junction upgrades

What was decided

Cabinet approved the proposed CIL strategic infrastructure spend priorities for 2026 to 2029 as set out in section 5.4 of report PES/510. Report P3

Cabinet ringfenced £2,585,608 of Strategic Infrastructure Strand CIL monies for the Three Bridges Station Improvement scheme, an increase of £535,608 on the previous £2,050,000 allocation. Report P4, P50

Cabinet ringfenced £360,000 for the A2011 Crawley Avenue and A2004 Northgate Avenue (Hazelwick roundabout) improvements and £958,804 for the Tushmore Junction improvements. Report P4

Why

To confirm Crawley's priority CIL Strategic Infrastructure Strand schemes for 2026 to 2029, focusing on schemes classed as Critical or Essential in the Infrastructure Delivery Schedule. Report 3.1, 6.2, P44

To ringfence CIL monies for the three priority projects so that sufficient funds are secured to deliver the schemes, in line with the Crawley Local Plan 2023 to 2040. Report 3.2, P38, P41

What happens next

The ringfenced funding programme will be reviewed annually, with projects prioritised or revised if CIL receipts fall short or new priorities emerge. Report P56, 8.3

Future Cabinet reports will seek formal allocation of an anticipated further £14.8m of Strategic CIL receipts to projects in the Infrastructure Delivery Schedule for 2029/30 to 2039/40. Report P58, P59

NHS Sussex will be invited to review its infrastructure priorities and put forward schemes that could receive CIL Strategic Infrastructure Strand funding. Report P60

The money

  • £2,585,608 Three Bridges Railway Station Improvement project ringfenced from Strategic CIL Report P4, P55
  • £360,000 A2011 Crawley Avenue and A2004 Northgate Avenue (Hazelwick) improvements ringfenced from Strategic CIL Report P4, P55
  • £958,805 A2011 Tushmore Junction ringfenced from Strategic CIL, including £184,321.79 from surcharges Report P55
  • £958,804 Tushmore Junction ringfenced from current CIL receipts (decision wording) Report P4
  • £3,904,413 Total Strategic CIL ringfenced across the three priority schemes Report P55
  • £4,411,596.42 Total Strategic CIL received to 31st December 2025 Report P19, P46
  • £3,720,090.75 Balance of Strategic Infrastructure Strand CIL monies available after deductions to 31st December 2025 Report P47
  • £520,561.88 CIL receipts outstanding from site developers as of 31st December 2025 Report P20
  • £24,244,496.11 Total projected CIL contributions to the Council by 2039/40 (including receipts to date and outstanding, after affordable housing and self-build reliefs) Report P29
  • £2,167,000 Estimated total cost of the Hazelwick roundabout scheme delivered with the Highway Authority Report P51

Options considered

  • Rejected: Distribute CIL more widely across schemes not in the Infrastructure Delivery Schedule. Would not comply with CIL Regulations or support infrastructure needed for Local Plan growth Report P77
  • Rejected: Hold Strategic CIL funds in reserve. Would not support the infrastructure required to deliver Crawley Local Plan growth Report P77
  • Rejected: Defer decisions until after Local Government Reorganisation. Would delay delivery of priority schemes and undermine partnership funding opportunities Report P77
  • Chosen: Focus Strategic CIL on schemes identified as Critical or Essential in the Infrastructure Delivery Schedule. Aligns with the adopted Crawley Local Plan 2023 to 2040 evidence base and the established CIL governance framework Report 6.2

Implications

  • Financial: Risk that CIL receipts will not match the spend profile of priority projects, particularly if developments are delayed or qualify for affordable housing relief; the council cannot borrow against anticipated CIL income but can retrospectively repay infrastructure spend from CIL. Report 8.1, 8.2, P23
  • Legal: Allocations must comply with the Planning Act 2008 and the Community Infrastructure Levy Regulations 2010 (as amended); 15% of CIL must go to the Neighbourhood Improvement Strand and 5% to administration, with 85% to the Strategic Infrastructure Strand. Report 4.4, 8.4, 8.5, 8.6
  • Climate: The Three Bridges Station, Hazelwick and Tushmore schemes support sustainable transport, walking, cycling and bus priority, and are expected to reduce congestion and transport related carbon emissions over time. Report 8.10, 8.11, 8.12, 8.13
  • Equalities: An Equality Impact Assessment has been completed and is appended at Appendix D of the report. Report 8.18, P100
  • Staffing: A CIL Technical and Monitoring Officer has been recruited, funded from the 5% administration allowance, with no further staffing implications identified. Report 8.9
  • Other: No direct crime and disorder implications arise from this decision. Report 8.15

Who and where

  • Residents and transport users in Crawley, including rail passengers at Three Bridges and road users at Hazelwick and Tushmore junctions Report P49, 8.16
  • West Sussex County Council, as the Highway Authority and partner in the Crawley Growth Programme and Three Bridges Station scheme Report P50, P51
  • National Highways, engaged through the Crawley Transport and Infrastructure Management Group Report 7.2, P41
  • Site developers in Crawley, who pay CIL on new development over 100m2 or on new dwellings Report 4.2, 4.3
  • Future Neighbourhood Improvement Strand projects and the Unsupervised Play Investment Programme, supported by 15% of CIL receipts Report P63

Timeline

  • 17th August 2016: CIL charging took effect in Crawley following Cabinet adoption Report 4.3, 8.4
  • February 2018: Cabinet first approved CIL strategic infrastructure spend priorities for 2018/19 to 2021/22 Report 4.5
  • 15 January 2025: Most recent prior Cabinet review of CIL Strategic Infrastructure Strand priorities (report PES/470) Report 4.9, P103
  • 31st October 2025: Natural England withdrew its Water Neutrality Position Statement, ending water neutrality restrictions in the Sussex North Water Supply Zone including Crawley Report P22
  • 31st December 2025: Date of the CIL financial position reported in the report Report P19
  • 9 March 2026: Overview and Scrutiny Commission considered the report and referred it to Cabinet Report 2.1
  • 11 March 2026: Cabinet approved the CIL strategic infrastructure spend priorities and ringfenced the three amounts
  • 2026/27 to 2028/29: Priority spend period for the three ringfenced transport schemes Report P3, 5.4
  • 2029/30 to 2039/40: Medium and long term period during which a further £14.8m of Strategic CIL receipts is expected and further projects will be brought forward for Cabinet approval Report P58, P59

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge local authorities can levy on new development, governed by the Planning Act 2008 and CIL Regulations 2010.
  • Strategic Infrastructure Strand: Up to 85% of CIL receipts (after 5% administration), ringfenced for infrastructure to support Crawley's growth.
  • Neighbourhood Improvement Strand (NIS): 15% of CIL receipts, spent in agreement with local communities in unparished areas such as Crawley.
  • IDS (Infrastructure Delivery Schedule): Assessment of infrastructure needed to support Local Plan growth, with schemes classed as Critical, Essential or Desirable.
  • IBP (Infrastructure Business Plan): Annual document setting out the proposed CIL funding programme and priorities.
  • UPIP (Unsupervised Play Investment Programme): Multi-year programme of play facility improvements partly funded by CIL Neighbourhood Improvement Strand monies.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED That the Cabinet approves: a) the proposed CIL strategic infrastructure spend priorities 2026-29 as set out in section 5.4 of report PES/510 . b) the ringfencing of the following total amounts of CIL Strategic Infrastructure Strand monies for the priority spend priorities for 2026-29: · Three Bridges Station Improvement scheme - £2,585,608 · A2011 Crawley Avenue / A2004 Northgate Avenue improvements - £360,000 · Tushmore Junction improvements - £958,804 Reasons for the Recommendations a) To confirm Crawley’s priority CIL Strategic Infrastructure Strand schemes for 2026-2029. b) To ringfence CIL Strategic Infrastructure Strand monies for the above three priority projects as set out in 2.2b of report PES/510 to ensure sufficient funds to enable delivery of the schemes going forward.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1That the Commission consider the report and decide what comments, if any, it wishes to submit to the Cabinet.

2.2To the Cabinet: That the Cabinet is recommended to:

a) Approve the proposed CIL strategic infrastructure spend priorities 2026-29 as set out in section 5.4 of report PES/510,

b) Approve the ringfencing of the following total amounts of CIL Strategic Infrastructure Strand monies for the priority spend priorities for 2026-29: • Three Bridges Station Improvement scheme - £2,585,608 • A2011 Crawley Avenue / A2004 Northgate Avenue improvements - £360,000 • Tushmore Junction improvements - £958,804

Reasons for the recommendations

3.1To confirm Crawley’s priority CIL Strategic Infrastructure Strand schemes for 2026-2029.

3.2To ringfence CIL Strategic Infrastructure Strand monies for the above three priority projects as set out in 2.2b of report PES/510 to ensure sufficient funds to enable delivery of the schemes going forward.

Background

4.1The Community Infrastructure Levy (CIL) is a charge which can be levied by local authorities on new development in their area. CIL was introduced by the Planning Act 2008 and is governed by the Community Infrastructure Levy Regulations 2010 (as amended). It is an important tool for local authorities to secure financial resources to help them deliver the infrastructure needed to support development in their area on the basis that it accords with infrastructure priorities identified in the Infrastructure Delivery Schedule (Appendix B) to facilitate population and employment growth set out in the Crawley Local Plan 2023-2040.

4.2The CIL charge is based on a calculation related to £’s per m2 of net additional floorspace and is payable on ‘buildings that people normally go into’. The charge applies to development of 100m2 or more, or the creation of a single residential dwelling, even if under 100m2. In keeping with the CIL Regulations, the rates set out in the charging schedule are index‑linked, with any necessary adjustment taking place at the start of each calendar year. Further details: Annual Community Infrastructure Levy rate summary 2026.pdf (crawley.gov.uk).

4.3CIL rates payable for different types of development are set by the council’s CIL Charging Schedule, which took effect in Crawley on 17th August 2016. There are also a number of exemptions and reliefs, including affordable housing and self-build housing: https://www.gov.uk/guidance/community-infrastructure-levy#relief-and-exemptions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review: Appendix AAppendix 127 KB Download
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review: Appendix BAppendix 156 KB Download
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review: Appendix CAppendix 94 KB Download
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand ReviewReport 172 KB DownloadRead as text
PDF
Community Infrastructure Levy (CIL) Strategic Infrastructure Strand Review- EIA Appendix DAppendix 86 KB Download

At this meeting

Whole meeting

Who was there

7 of 20 attended
MJ
Councillor Michael JonesChair, present
NH
Councillor Nick HiltonCommittee Member, present
II
Councillor Ian IrvineCommittee Member, present
YK
Councillor Yasmin KhanCommittee Member, present
CM
Councillor Chris MullinsCommittee Member, present
SM
Councillor Sue MullinsCommittee Member, present
AN
Councillor Atif NawazCommittee Member, present
BN
Councillor Bob NoyceCommittee Member, apologies
JR
Councillor Justin RussellObserving, in attendance
KJ
Councillor Kim JaggardObserving, in attendance
JB
Jocelyne BerreenOfficer, in attendance
JC
Jane CryerOfficer, in attendance

All 20 on the meeting page

On this subject at Crawley

Search all
  1. Community Infrastructure Levy (CIL) Strategic Infrastructure Strand ReviewThis decision
  2. Community Infrastructure Levy (CIL) Strategic Infrastructure Strand ReviewNoted
  3. Community Infrastructure Levy (CIL) Strategic Infrastructure Strand ReviewApproved
  4. Annual Community Infrastructure Levy (CIL) StatementApproved
  5. Allocating Monies Collected Through Community Infrastructure Levy - Infrastructure Business Plan 2019/20Approved
  6. Allocating Monies Collected Through Community Infrastructure Levy - Infrastructure Business Plan 2019/20Agreed

More from Crawley Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a... Approved Open
9 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual... Approved Open
9 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ... Approved Open
9 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Cabinet: a) approves the Crawley Homes Annual Complaints Performance and Service Improvement Plan R... Approved Open
9 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Cabinet: a) approves the Crawley Homes Asset Management Strategy ( appendix A of report CH/222 ) fo... Approved Open