Corporate Measures and Performance Update

Decided Scrutiny 2 papers

AI summaryCrawley Borough Council's Overview and Scrutiny Commission has endorsed the 2025/26 corporate performance update covering housing, the economy, leisure, communities and reorganisation, with no major areas of concern identified.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommission received, acknowledged and endorsed the 2025/26 performance report
Money£4.9m social valueCrawley Leisure Contract social value generated in 25/26
What happens nextNovember update reportNext twice-yearly performance update to Commission
Who it affectsCrawley residents and servicesCovers housing, leisure, economy, community safety

What was decided

The Commission received, acknowledged and endorsed the 2025/26 corporate measures and performance report, with any actions to be documented by officers. Report 2.1

The report sets out performance against the Corporate Plan's five strategic objectives: thriving local economy, tackling the housing emergency, a vibrant town, connected communities, and preparing for local government reorganisation. Report 5.3, 5.4, 5.5, 5.6, 5.7

Overall performance is positive, with no major areas of concern and good progress made during the first eight months of the new Corporate Plan. Report 5.8

Why

The Corporate Plan sets out the council's strategic direction until its powers and responsibilities transfer to the new authority, and the measures update shows how priorities are being delivered. Report 3.1

The Constitution gives the Commission the remit to monitor and review internal and external delivery and performance of services. Report 3.2

Cabinet agreed the performance measures and milestones on 26 November 2025, with twice-yearly updates to this Commission and yearly updates to Cabinet. Report 4.2

What happens next

Performance reports will continue on a twice-yearly basis to the Commission and yearly to Cabinet. Report 4.2

The first data report on Corporate Plan delivery will be published in Q1. Report P38

Preliminary housing development and commercial floor space data, and apprenticeship data, should appear in the November update report, with confirmed housing figures at the end of 26/27. Report P16

The money

  • £4.9m Social value generated by the Crawley Leisure Contract over the past year Report P28
  • £311.53 Total core spending power per dwelling in 24/25 Report P40
  • £316.03 Projected total core spending power per dwelling in 25/26 Report P40

Options considered

  • Chosen: Receive, acknowledge and endorse the 2025/26 performance report. Allows the Commission to discharge its scrutiny role on service delivery and performance Report 2.1, 3.2

Implications

  • Financial: Delivery of Corporate Plan priorities is managed within the council's existing budget and resources. Report 6.1
  • Legal: The report does not have any direct legal implications; it sets out measures against which progress is assessed. Report 6.2
  • Staffing: Delivery of Corporate Plan priorities is within existing staff resources. Report 6.3
  • Climate: The report includes measures demonstrating progress towards the council's climate change commitments. Report 6.4
  • Other: The report sets out measures on areas improving safety and reducing crime and disorder for residents. Report 6.5
  • Equalities: An Equalities Impact Assessment is not required for this report; some measures do not impact people with protected characteristics. Report 6.7, 6.8

Who and where

  • Crawley residents, who will have greater access to information about council service performance Report 6.6
  • Council tenants, with improving satisfaction and energy efficiency ratings Report P22
  • Visitors to council leisure and cultural facilities including The Hawth and K2 Crawley Report P28
  • Local businesses and job seekers supported through Employ Crawley and skills programmes Report P16
  • Households at risk of homelessness and in temporary accommodation Report P20, P22

Timeline

  • 2024: Council underwent a Corporate Peer Challenge Report 4.1
  • 26 November 2025: Cabinet agreed the performance measures and milestones Report 4.2
  • Q1: Stock Condition Survey due for completion and first Corporate Plan delivery data report to be published Report P20, P38
  • Q2: Forge Wood 1B construction handover expected; final decision on new Town Council Governance Review Report P20, P32
  • Q3: Food waste collection due to begin Report P26
  • Q3/4: Three Bridges Station to be on site; nighttime economy plan begins Report P14
  • End of June 2026: 25/26 household waste figures to be available Report P28
  • End of July 2026: 2026 Green Flag award announcements expected Report P28
  • November 2026: Next performance update report to the Commission; preliminary housing and apprenticeship data expected Report P16, 4.2

Plain English for the jargon

  • KPI: Key Performance Indicator, used to track delivery of the Corporate Plan
  • CPC: Corporate Peer Challenge, a sector-led review undertaken in 2024
  • CSP: Core Spending Power, an estimate of total revenue funding available to the council per dwelling
  • TSM: Tenant Satisfaction Measures introduced by the Regulator for Social Housing
  • EPC: Energy Performance Certificate, rating the energy efficiency of homes
  • EfW: Energy from Waste, treatment of residual waste
  • EDI: Equality, Diversity and Inclusion, considered in committee reports
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED That the Commission receives, acknowledges and endorses the report with any actions being documented by the officers.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Overview and Scrutiny Commission

Recommendations

2.1To the Overview and Scrutiny Commission:

That the Commission considers, acknowledges and endorses the report and associated appendix A of report DCE/023.

Reasons for the recommendations

3.1The Corporate Plan sets out the council’s strategic direction until its powers and responsibilities transfer to the new authority. The measures and milestones update provide an overview of how those priorities are being delivered.

3.2Within the Constitution the Overview and Scrutiny Commission has within its remit to monitor and review the internal and external delivery and performance of services.

Background

4.1The council underwent a Corporate Peer Challenge in 2024. Cabinet agreed an action plan in response to the CPC in which it committed to updating a corporate plan to see the council through the period of local government reorganisation and to establish a set of key performance indicators (KPIs) to ensure transparency of delivery of the plan.

4.2The performance measures and milestones were agreed by Cabinet on the 26 November 2025 with update reports being reported on to Overview and Scrutiny Commission on a twice-yearly basis and Cabinet on a yearly basis as agreed in the Corporate Plan to ensure that members have oversight of the council’s performance. 4.3 The Corporate Plan was agreed to renew the strategic context for the Council as requested by partners, staff and residents. It ensures that the Council is clear about its priorities and can allocate its resources to deliver the priorities of the council and the community, as well as ensuring that the council is able to transition to a new council effectively so that residents continue to receive high quality services locally.

5. Information & Analysis Supporting Recommendation

Corporate Measures and Performance update

5.1The Corporate Measures and Performance update at Appendix A of report DCE/023 provides an overview of performance for the financial year ended 25/26. Measures and milestones are set out under each of the Corporate Plan’s strategic objectives. Where available quarterly and annual data has been provided for 25/26 and the outturn for 24/25 by means of a comparison. For some measures, there is a lag of up to 3 years in the latest data available, which has been indicated in the table. Progress updates for the milestones are expressed as a commentary.

5.2A column has been included to show the direction of improvement (whether a higher or lower value indicate good performance). Some measures are marked as contextual as they track key activity rather than performance or new measures where the baseline is to be set.

5.3A thriving local economy with new, diverse and green jobs

To enable sustainable economic growth which benefits the local community and improves job opportunities for local residents.

Key achievements

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Measures and Performance Update: Appendix AAppendix 132 KB Download
PDF
Corporate Measures and Performance UpdateReport 105 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 20 attended
JR
Councillor Justin RussellChair, present
TC
Councillor Tim ChartersVice-Chair, present
OA
Councillor Olu AdeniyiCommittee Member, present
MA
Councillor Marion AylingCommittee Member, present
SB
Councillor Shelly BushnellCommittee Member, present
GC
Councillor Grainne ConwayCommittee Member, present
MH
Councillor Mandie HainsCommittee Member, apologies
MH
Councillor Marilyn HiltonCommittee Member, present
KK
Councillor Kiran KhanCommittee Member, present
DR
Councillor Dominic RamsayCommittee Member, present
JT
Councillor James TidyCommittee Member, present
EW
Councillor Emma WhiteoakCommittee Member, present

All 20 on the meeting page

On this subject at Crawley

Search all
  1. Corporate Measures and Performance UpdateThis decision
  2. Corporate Performance and MeasuresApproved
  3. Corporate Performance and MeasuresNoted

More from Crawley Overview and Scrutiny Commission

All decisions
MeetingDecisionOutcome
7 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate were fed back ... Noted Open
7 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open